“[T]he development of this land is seen as one of the critical elements in meeting the Council’s plan for new housing delivery over the next 5 years.”
“For this just to be an approach to the connection with the [Link Road] could jeopardise the viability and deliverability of the overall scheme. This is a key issue in terms of overall feasibility. Whilst the intention is to do everything that the developer can to promote the link, the development cannot be held to ransom by this.”
“At this moment in time, the County Council, as Local Highway Authority has no option but to recommend refusal of the application on highway grounds. There is no objection in principle to the development proposed per se, but an issue arises with the potential late delivery of the connection of the internal roads within the site to the [Link Road] which runs through the adjacent former [RNSD] site to the west. Should this issue be satisfactorily resolved I would be content to remove my objection. I understand that it has been provisionally agreed that this connection need not be made until, effectively, the final phase of development of the [Dart Site] for viability reasons. This is unfortunate and means that, in practical terms, traffic emerging from the site in the morning peak traffic period and wishing to head north towards the A379 and beyond will opt to turn right from the site and then right again into the RNSD [i.e. into the Link Road], a distance of approximately 350 metres. The level of traffic likely to make this movement is, in turn, likely to result in unacceptable levels of queuing on Topsham Road and this is likely to continue for a significant period of time, until the internal connection to the [Link Road] is finally made.”
“Having considered the revised traffic flows based upon 650 dwellings being constructed prior to the northern connection within the site being made to the [Link Road] there are no capacity concerns about the [junctions of the Dart Site and Topsham Road]. However, the [Link Road Junction] is at capacity and sensitive to the right turn from Topsham Road towards Newcourt. There is some disparity between our view of the saturation flow and those of the applicant. Whilst the situation at the [Link Road Junction] is not ideal and could be significantly improved if the northern RNSD link were to be provided, it is not feasible to mount an argument against the development on capacity grounds as this could not be defended at appeal. Following the revised information and discussions, I am now prepared to remove my objection to the development provided that the matters outlined below are taken into consideration of the application. The planning agreement must clearly state the need to construct the Link Road at the appropriate time. The number of houses that can be built before the connection to the link road is made should preferably be limited to 600 to have due regard to the capacity issues at the [Link Road Junction]…”
“The relative late delivery of the connection, which had been discussed at meetings between the Highway Authority, your Council and the applicant, is related to the deliverability of the site for residential development and, at those meetings, that issue was explained and discussed in some detail. It was subsequently agreed that the applicant need not make the connection until the occupation of the 650th dwelling in recognition of maximising the potential for the scheme to be delivered early. … As stated, the Transport Assessment is based upon the scenario that the connection to the [Link Road] is not made, in order to test the worst case scenario and it does indicate that the development can operate in such a case, subject to the very substantial Residential Travel Plan provisions being approved and implemented. … A third party [i.e. of course, the Claimant] has raised the issue what he considers to be the unacceptable impact of traffic generation from the site on the local road network as a direct consequence of the later delivery of the connection of internal roads within the application site to the [Link Road] or, indeed, the non-delivery of same. Full account has been taken of the objector’s case and, as previously stated, the Transport Assessment provided in support of the application has been based upon the worst case scenario of the connection not being in existence. Balanced against the proposed sustainable transport initiatives and contributions, and the deliverability issues of the site for substantial additional housing provision in the city, it is considered an objection on highway grounds could not reasonably be pursued or substantiated. In conclusion, having taken all relevant matters into consideration the [Highway Authority] raises no objection to the application subject to a Section 106 agreement requiring the following…”
“35. A road (to an agreed specification) to be built to the Dukeminster boundary north of the school site (at a point to be agreed within the 50m corridor specified in the Dukeminster approval) before the occupation of the 301st house or opening of the school, whichever is the earlier. Reason: to ensure that the facility to connect the proposed development to adjacent development is made available and not negated by the development. 36. Not more than 650 dwellings to be occupied prior to the construction and opening of the northern road connection within the site to the [Link Road].”
“The relative late delivery of the connection, which had been discussed at meetings between the Highway Authority, your Council and the applicant, is related to the deliverability of the site for residential development and, at those meetings, that issue was explained and discussed in some detail. It was subsequently agreed that the applicant need not make the connection until the occupation of the 600th dwelling in recognition of maximising the potential for the scheme to be delivered early”
“Balanced against the proposed sustainable transport initiatives and contributions, and the deliverability issues of the site for substantial additional housing provision in the city, it is considered an objection on highway grounds could not reasonably be pursued or substantiated”
“Specific trip generation was not included for these uses as they were not considered to be significant generators especially during local highway peak hours as they will be aimed at providing local facilities for local people. Moreover, they are neither likely to be attractive to passing traffic along Topsham Road or become a destination in their own right.”
“to ensure that the facility to connect the proposed development to the adjacent development is made available and not negated by the development”