“(a) is entered into by the Secretary of State … on or before the earlier of31st December 2015 and the date on which a definition of an “eligible generator” comes into force by virtue of section 10(3)… (b) includes an obligation for the parties to make payments under the contract based on the difference between a strike price and a reference price in relation to electricity generated; and (c) is laid before Parliament in accordance with sub-paragraph (5).”
“(a) that the Secretary of State considers that the payments falling within sub-paragraph 1(c) which would be made under the contract would encourage low carbon electricity generation, (b) that the Secretary of State considers that without the contract there is a significant risk that the electricity generation to which the contract relates will not occur or will be significantly delayed, and (c) summarising the regard the Secretary of State has had, in deciding to enter the contract, to the matters set out in subsection (2) of Section 5.”
“ • It no longer appears from your submissions that the actual conversion of the Unit 3 plant itself is at significant risk of delay without an investment contract. This is in contrast to your submissions at Phase 1 and Phase 2 which indicated that conversion of Unit 3 depended on securing the rights to sufficient sustainable biomass. • Your recent submissions do not explain in a satisfactory manner how the alleged delays in fuel supply chain investment caused by the absence of an investment contract would prevent or delay generation. For example if Drax is making the case that, without an investment contract, Unit 3 may convert but may not operate at full capacity, your submissions do not identify the amount of generation that might be delayed or the point at which delay might occur. • Your recent submissions do not explain why, in the absence of an investment contract, the delay referred to in your clarification letter could not be avoided by converting the plant under the Renewables Obligation (RO). This is in contrast to your submissions at Phase 1 and Phase 2 which indicated that a private law contract was important in enabling sufficient fuel to be sourced for Unit 3.” • It no longer appears from your submissions that the actual conversion of the Unit 3 plant itself is at significant risk of delay without an investment contract. This is in contrast to your submissions at Phase 1 and Phase 2 which indicated that conversion of Unit 3 depended on securing the rights to sufficient sustainable biomass. • Your recent submissions do not explain in a satisfactory manner how the alleged delays in fuel supply chain investment caused by the absence of an investment contract would prevent or delay generation. For example if Drax is making the case that, without an investment contract, Unit 3 may convert but may not operate at full capacity, your submissions do not identify the amount of generation that might be delayed or the point at which delay might occur. • Your recent submissions do not explain why, in the absence of an investment contract, the delay referred to in your clarification letter could not be avoided by converting the plant under the Renewables Obligation (RO). This is in contrast to your submissions at Phase 1 and Phase 2 which indicated that a private law contract was important in enabling sufficient fuel to be sourced for Unit 3.”
“ • Create the necessary confidence in the UK renewables support regime at both Drax and through the biomass supply chain both in the UK and elsewhere in the world to underpin the investments required; • Facilitate the signing of long-term pellet contracts in 2013 to secure the full biomass supply requirements for the converted unit; • Bring forward the upstream supply chain investments in pellet capacity and other necessary infrastructure, and • Make the contribution of the renewable generation from Drax to the HMG 2020 targets more certain and secure. • Create the necessary confidence in the UK renewables support regime at both Drax and through the biomass supply chain both in the UK and elsewhere in the world to underpin the investments required; • Facilitate the signing of long-term pellet contracts in 2013 to secure the full biomass supply requirements for the converted unit; • Bring forward the upstream supply chain investments in pellet capacity and other necessary infrastructure, and • Make the contribution of the renewable generation from Drax to the HMG 2020 targets more certain and secure. In contrast, not granting an [IC] would mean a potential delay of at least 18 months in execution at this crucial stage. This would risk damaging potentially fragile supply chain confidence in the UK regime and creating a hiatus that will result in higher risk and significantly more than the 9-12 month delay in waiting for a normal CfD.”
“Developer states that IC will enable them to access additional funds earlier to make the required investments to guarantee the fuel supply (compared to the RO). Without an IC there could be a potential delay of at least 18 months in execution.”
“Developer states that the development of the pellet supply chain is the critical element on the timing of the conversion of Unit 1.”
“…it is the issues with development of the pellet supply chain that are critical to the timing of our conversions (which we have explained in detail both in our application, and in the supplementary response) and it is this issue which will cause the 15-18 month delay. Failing to act promptly will undermine our ability to place the necessary full-chain contracts for the delivery to Drax for the full volume of pellets (2.3-2.5mt/yr) required for each of these converted units. So the implications of not getting an [IC] and waiting perhaps 9-12 months for a normal CfD will add an additional period we estimate to be of around 6 months to the time it will take us to put in place all the contracts for the pellets necessary for either unit – i.e. 15-18 months total delay for each…”
“as confirmed in the re-submission of our Phase 1 application (attached as Annex A of the submission) the board still considers that securing an [IC] for [Unit 3] will significantly improve our ability to execute our plans to convert this unit to biomass and to maximise renewable output from this unit in a timely manner”
“We confirm that the proposed change in the TCD will not have any potential impact on the Qualification Criteria or the Evaluation Criteria for the Drax Unit 3 project. In particular, the justification for the award of an Investment Contract was to support the need for timely investment in the development of the capacity of the longer-term sustainable biomass supply chain, which remains exactly as set out in our Phase 1 and 2 submissions.”
“As set out in our Phase 1 and Phase 2 submissions, the need to secure and deliver to Drax the required sustainable biomass feedstock on the right timescales and at enduringly competitive prices is essential to support the conversion to biomass of Unit 3 and generation from that Unit.”
“Please therefore clarify in respect of your binding application for Unit 3 whether, by referring to the statements made in your Phase 1 and Phase 2 submissions, you continue to consider those statements concerning the significant risk of delay and the minimum 18 months delay to be the case, and if so clarify how, in respect of Unit 3, this delay continues to arise.”
“Our current assessment is that if Unit 3 were not awarded an Investment Contract on the current timetable in April 2014, we would then have to wait to apply for an enduring CfD before being able to proceed with further investments in the supply chain and transportation infrastructure and contracting for fuel for Unit 3 beyond the short-term. As we have outlined before, security of supply of fuel for the duration of the Investment Contract is uncertain and critical for the overall delivery and viability of the project.”
“particularly as regards our ability to progress fuel contracts and pellet plant and infrastructure investments.”
“It no longer appears from your submissions that the actual conversion of the Unit 3 plant itself is at significant risk of delay without an investment contract. This is in contrast to your submissions at Phase 1 and Phase 2 which indicated that conversion of Unit 3 depended on securing the rights to sufficient sustainable biomass.”
“Your recent submissions do not explain why, in the absence of an investment contract, the delay referred to in your clarification letter could not be avoided by converting the plant under the Renewables Obligation (RO). This is in contrast to your submissions at Phase 1 and Phase 2 which indicated that a private law contract was important in enabling sufficient fuel to be sourced for Unit 3.”
“The contractual certainty from a private law Investment Contract will provide the necessary increased confidence that our biomass supply and logistics chain is looking for in order to make the investment it needs to guarantee delivery of sufficient volumes of sustainable biomass to fuel the electricity generation from biomass conversion of this Unit.” (Emphasis added).