“Development shall not commence until a scheme (including construction details) for the following on site works have been submitted to and approved in writing by the Local Planning Authority. The construction (to an adoptable standard) of the carriageway widening to 5.0m, the provision of a 2m wide footway along site frontage and the provision of a turning shown on the approved plans. The development shall not be brought into use until the above works have been carried out in accordance with the approved details and, unless otherwise approved in writing by the Local Planning Authority, the works have been vested on the highways authority.”
“12. Within one month of this decision, a scheme, including construction details, surface finishes and drainage provision, for the carriageway widening, the footway/verge crossings, the 1m wide footway and the turning facility (of minimum dimensions 5.0m by 7.m) shall be submitted to and approved in writing by the local planning authority. The works shall be carried out in accordance with the approved details and shall be completed within three months of the date of this decision. These works shall be retained at all times thereafter, be kept free from obstruction and available for use for their intended purposes at all times. 13. Within three months of this decision, 2.0m by 2.0m vehicle/pedestrian intervisibility splays shall be provided on both sides of the access/drive such that there is no obstruction to visibility greater than 600mm above the level of the adjacent footway. Such splays shall thereafter be retained.”
“1. The Council is satisfied that the use of the building as a dwelling (Class C3) without compliance with conditions on permission Ref. 04/99/63308/A is lawful by virtue of having been authorised as a result of permission Ref. 09/1307/FUL granted on appeal on7th September 2010 and the operation of section 75 of the 1990 Act. 2. However, for the avoidance of any doubt, the Council is not satisfied that any non-compliance with conditions on permission Ref. 09/1307/FUL granted on appeal on7th September 2010 is or would be lawful. Such non-compliance remains capable of being enforced against. 3. Furthermore, for the avoidance of any doubt, the Council is not satisfied that, in the absence of permission Ref. 09/1307/FUL granted on appeal on7th September 2010 , the use of the building as a dwelling would be lawful since the relevant provision for establishing immunity for such a use would be section 171B(3) which would require the use to have continued for a period of ten years, rather than sections 171B(1) and (2) as relied upon in the application.”
“7. It is common ground that the 2004 Permission was not lawfully implemented because of the failure to comply with a number of conditions precedent. The Council also accepts that the building operations involved in the erection of nos.15 & 17 are immune from enforcement as they were substantially complete more than 4 years ago and no enforcement action was taken against them in that period, pursuant to s.171B(1) of the Act. 8. What remains in dispute is whether the 2010 permission was implemented and, if not, whether the use of no. 15 as a dwelling is lawful as that use commenced more than 4 years ago and no enforcement action was taken against it in that period. 9. The appellant argues that the 2010 permission was never implemented. However, it is clear that both dwellings were substantially complete by the time of the application (in 2009) and, to that extent, implementation had already taken place. I agree with the Council that what the application sought was effectively the grant of planning permission with a retrospective effect under s.73A of the Act. The wording of the replacement conditions 12 and 13 in the 2010 appeal decision reflect the fact that the development had already occurred. There is no question of a breach of planning control by failure to comply with conditions precedent in such a case. The grant of the 2010 planning permission, albeit retrospective, conveyed consent for the use for which the buildings were designed, in accordance with s.75(3) of the Act, hence the grant by the Council of the LDC with the added wording which is the subject of this appeal. 10. The actions of the appellant in response to the 2010 permission appear consistent with his having relied upon the permission. He did not challenge the decision in any way or make a revised application. On the contrary, albeit late, he submitted a scheme to discharge the new condition 12. This was approved by the Council in January 2011. 11. A further test of whether the 2010 permission was implemented is whether the Council would have been in a position to issue an enforcement notice against either the buildings or their use during the relevant time period. The answer must surely be no, because the appellant would have had the ready defence, by reference to that permission, that no breach of planning control had occurred. It would make nonsense of the legislation if the appellant could shelter under the protection of a planning permission without being bound by any of the conditions to which it is subject. I conclude that the 2010 permission was implemented and that the Council’s decision to modify the grant of the LDC to include reference to that wording was well-founded. 12. In the event that I am wrong on the first matter, I now go on to address the second matter, that of the appropriate timescale to achieve lawfulness. It is common ground that the building operations to erect 2 dwellings, commenced in 2006 and substantially completed in 2007/08, were not lawful. Both parties refer to the Supreme Court decision in Welwyn Hatfield Borough Council v SSCLG and another [2011]. In that case, the Council granted planning permission for a barn. What was built was a new building which had the external appearance of a barn but was, in fact, designed and constructed to be used as a single dwelling. There, it was held that when the building was first used as a single dwelling, there was no active change of use from a former use (in that case a nil use was argued) which would have triggered the 4 year immunity period set out in s.171B(2) of the Act. Instead, the relevant period was held to be 10 years, pursuant to s.171B(3). 13. That appears to be very much the situation at the present appeal property. It had no permitted use as s.75 of the Act applies only to development which has received planning permission. It was not put to any other use, including a nil use, prior to residential occupation. Therefore, there was no active change of use to trigger s.171B(2) of the Act. Accordingly, I am led to conclude that the immunity period in the present case is 10 years pursuant to s.171B(3). This confirms my view that the Council’s decision to modify the grant of the LDC to include reference to the 2010 permission was well-founded.”
“(1) Where an application is made to a local planning authority for planning permission— (a) subject to sections 91 and 92, they may grant planning permission, either unconditionally or subject to such conditions as they think fit; or (b) they may refuse planning permission.” (a) subject to sections 91 and 92, they may grant planning permission, either unconditionally or subject to such conditions as they think fit; or (b) they may refuse planning permission.”
“(1) Without prejudice to the generality of section 70(1) conditions may be imposed on the grant of planning permission under that section… (3) Where— (a) planning permission is granted for development consisting of or including the carrying out of building or other operations subject to a condition that the operations shall be commenced not later than a time specified in the condition; and (b) any building or other operations are commenced after the time so specified, the commencement and carrying out of those operations do not constitute development for which that permission was granted.”
“73. Determination of applications to develop land without compliance with conditions previously attached (1) This section applies, subject to sub-section (4), to applications for planning permission for the development of land without complying with conditions subject to which a previous planning permission was granted. (2) On such an application the local planning authority shall consider only the question of the conditions subject to which planning permission should be granted, and— (a) if they decide that planning permission should be granted subject to conditions differing from those subject to which the previous permission was granted, or that it should be granted unconditionally, they shall grant planning permission accordingly, and (b) if they decide that planning permission should be granted subject to the same conditions as those subject to which the previous permission was granted, they shall refuse the application. (3) Special provision may be made with respect to such applications— (a) by regulations under section 62 as regards the form and content of the application, and (b) by a development order as regards the procedure to be followed in connection with the application. (4) This section does not apply if the previous planning permission was granted subject to a condition as to the time within which the development to which it related was to be begun and that time has expired without the development having being begun. (5) Planning permission must not be granted under this section to the extent that it has effect to change a condition subject to which a previous planning permission was granted by extending the time within which— (a) a development must be started; (b) an application for approval of reserved matters (within the meaning of section 92) must be made.” (a) if they decide that planning permission should be granted subject to conditions differing from those subject to which the previous permission was granted, or that it should be granted unconditionally, they shall grant planning permission accordingly, and (b) if they decide that planning permission should be granted subject to the same conditions as those subject to which the previous permission was granted, they shall refuse the application. (a) by regulations under section 62 as regards the form and content of the application, and (b) by a development order as regards the procedure to be followed in connection with the application. (a) a development must be started; (b) an application for approval of reserved matters (within the meaning of section 92) must be made.”
“73A. Planning permission for development already carried out (1) On an application made to a local planning authority, the planning permission which may be granted includes planning permission for development carried out before the date of the application. (2) Sub-section (1) applies to development carried out— (a) without planning permission; (b) in accordance with planning permission granted for a limited period; or (c) without complying with some condition subject to which planning permission was granted. (3) Planning permission for such development may be granted so as to have effect from— (a) the date on which the development was carried out; or (b) if it was carried out in accordance with planning permission granted for a limited period, the end of that period.” (a) without planning permission; (b) in accordance with planning permission granted for a limited period; or (c) without complying with some condition subject to which planning permission was granted. (a) the date on which the development was carried out; or (b) if it was carried out in accordance with planning permission granted for a limited period, the end of that period.”
“(1) Where, at any time after the end of the period for compliance with an enforcement notice, any step required by the notice to be taken has not been taken or any activity required by the notice to cease is being carried on, the person who is then the owner of the land is in breach of the notice. (2) Where the owner of the land is in breach of an enforcement notice he shall be guilty of an offence. (3) In proceedings against any person for an offence under sub-section (2), it shall be a defence for him to show that he did everything he could be expected to do to secure compliance with the notice.”
“(1) This section applies where planning permission for carrying out any development of land has been granted subject to conditions. (2) The local planning authority may, if any of the conditions is not complied with, serve a notice (in this Act referred to as a ‘breach of condition notice’) on— (a) any person who is carrying out or has carried out the development; or (b) any person having control of the land, requiring him to secure compliance with such of the conditions as are specified in the notice. (3) References in this section to the person responsible are to the person on whom the breach of condition notice has been served. (4) The conditions which may be specified in a notice served by virtue of sub-section (2)(b) are any of the conditions regulating the use of the land. (5) A breach of condition notice shall specify the steps which the authority consider ought to be taken, or the activities which the authority consider ought to cease, to secure compliance with the conditions specified in the notice. (9) If the person responsible is in breach of the notice he shall be guilty of an offence. (11) It shall be a defence for a person charged with an offence under sub-section (9) to prove— (a) that he took all reasonable measures to secure compliance with the conditions specified in the notice; or (b) where the notice was served on him by virtue of sub-section (2)(b), that he no longer has control of the land.” (a) any person who is carrying out or has carried out the development; or (b) any person having control of the land, (a) that he took all reasonable measures to secure compliance with the conditions specified in the notice; or (b) where the notice was served on him by virtue of sub-section (2)(b), that he no longer has control of the land.”
“9. The Appellant argues that the 2010 permission was never implemented. However, it is clear that both dwellings were substantially complete by the time of the application (in 2009) and to that extent, implementation had already taken place. I agree with the Council that what the application sought was effectively the grant of planning permission with a retrospective effect under s.73A of the Act. …”
“I agree with the Council that what the application sought was effectively the grant of planning permission with a retrospective effect under s.73A of the Act”
“We accept, as does counsel for the Prosecution, that the phrase ‘everything he could be expected to do’ must implicitly be read as ‘reasonably expected’. It applies an objective criterion of reasonableness, having regard to all the relevant circumstances, in particular any disabilities to which the owner of the land is subject.”
“We … confirm that we are aware that criminal proceedings are being brought against Lawson Builders Ltd. For the avoidance of any doubt, we will not allow Lawson Builders LTD or any other third parties or person onto our land to carry out any works whatsoever.”