“If any person aggrieved by a compulsory purchase order desires to question the validity thereof, or of any provision contained therein, on the ground that the authorisation of a compulsory purchase thereby granted is not empowered to be granted under this Act or any such enactment as is mentioned in section 1(1) of this Act, he may make an application to the High Court.”
“…the court may by interim order suspend the operation of the compulsory purchase order or any provision contained therein, or of the certificate, either generally or in so far as it affects any property of the applicant, until the final determination of the proceedings.”
“If on the application the court is satisfied that— (a) the authorisation granted by the compulsory purchase order is not empowered to be granted under this Act or any such enactment as is mentioned in section 1(1) of this Act, or (b) the interests of the applicant have been substantially prejudiced by any relevant requirement (as defined in section 23(3) above) not having been complied with, the court may quash the compulsory purchase order or any provision contained therein, or the certificate, either generally or in so far as it affects any property of the applicant.”
“It is not my place, nor am I legally able, to tell you what documents should be before the court and what shouldn’t but I would advise you to consider what documents you would wish to have before the Court;”
“From the time of the first CPO enquiry, the Barrister acting for the Local Authority was asking the inspector to adjust and change their various mistakes. Likewise the Inspector was assisting the Authority in pointing out their various mistakes which left me very dissatisfied as they kept ‘moving the goalpost’.”
“However, this alternative site was the subject of a planning application which was refused and dismissed on appeal as recently as October 2005. That application was an application for a school.”
“The access was extremely dangerous with narrow pavements and on a steep hill. There would be dangers and disruption to the children during the construction period of the new school as a result of the contractors’ traffic, noise, dust, fumes etc. The alternative site he suggested (Doc 15) gave the opportunity of a more suitable school site with good, safe and convenient access. It also gave the opportunity for the provision of recreational facilities at no cost to the Council.”
“The only new evidence in this respect is Mr Boland’s plan showing an alternative site together with recreational facilities (Doc 15). That plan is a variation on the one produced at the last inquiry. That site is not allocated for development in the UDP and there has been no significant change in the planning policy background since previous proposals in the green wedge were refused by the Council and appeals dismissed (23). I do not consider that this alternative gives any grounds to reconsider the principle of re-building the school on the present site.”
“On this occasion I had no difficulty in finding the watercourse where it passes under the public footpath in a pipe on the day before the inquiry. It is a clearly defined and existing watercourse which physically is suitable to receive the proposed discharge. From the evidence before me I have no doubt that the capacity of the watercourse and the pipe under the driveway at the bottom of the field are sufficient that flooding of the field is most unlikely to occur (27 & 33). In the most extreme storm situations, which might fill the attenuation tank, the surface water would do no more than flow overland as it appears to now. The new drain would probably result in some improvement to existing flooding by capturing some of the current run off from the existing school site which appears to flow down the footpath and into the development below the site.”
“…there is a compelling case in the public interest for the acquisition of Plots 3-7 inclusive in the 2006 Supplementary Order and Plots 1, 2 and 5b in the 2009 Supplementary Order.”
“Consideration has been given to the statement that the local authority had not followed correct procedures (paragraphs 1-5 of the Inspector’s report). It is clear from the documents submitted by the local authority that although the timing of assembling the land within the Orders has been drawn out by the use of the Supplementary Orders, it is clear that the objectors to the Orders have been afforded the opportunity to present their case and have the issues they raised considered. Statutory notifications have been given in accordance with legislation, and there is no evidence that any party has been prejudiced.”
“Being landowners and farmers we have suffered contempt and have been ignored by the Authority on numerous occasions which I feel has contributed to my ill health and I therefore ask the Judge to the Court if he would adjourn the trial hearing of the25th January 2011 enabling me to regain my health so I can attend his Court in defence of the CPO for my family.”
“Thank you for this. I have a meeting this morning that may take up most of the day, but will endeavour to get a Consent Order prepared as soon as possible. Thank you for your assistance.”
“The CPOs that relate to the CRS have been confirmed pursuant to recommendations of an Inspector and decisions made by or on behalf of the Minister that were unreasonable having regard in particular to the severe road and construction site safety implications and the potential availability of a more suitable and safer location, with potential for further expansion of the school.”