“5.7.6 … the Appellant’s Environmental Appraisal concluded that, in the absence of suitable mitigation, the proposal may have an adverse impact on the pink-footed geese population and, therefore, Morecambe Bay SPA … 5.7.8 Two mitigation areas, measuring a combined total of 12.1 hectares in size have been identified. Both areas are capable of being managed in such a way as to provide food for geese. Accordingly, by reference to these two areas, an outline mitigation proposal has been produced which both Natural England and the RSPB agree constitutes adequate compensation for the precautionary 50 casualties per annum predicted by the collision risk model. Work towards the production of a detailed mitigation proposal is now in train. ”
“Although there may be some significant effects from a visual perspective occasioned by the proposal, they will be highly localised and have been judged to be acceptable in impact terms. As regards the ecological impact of the proposal, it is acknowledged that due to collision risk there will be an adverse impact on the pink-footed geese population which roosts within the Morecambe Bay SPA and RAMSAR site. However, Natural England and the RSPB agree that the outline mitigation proposal drawn up on behalf of the Appellant is acceptable and that it constitutes adequate compensation for the number of collisions and resulting casualties predicted, thereby addressing the significant adverse impact which has been identified. …”
“3. We confirm that the Development has the potential to give rise to environmental effects relating to matters such as noise, landscape and visual impacts, shadow flicker and ecological impacts. However, we would draw the Secretary of State’s attention to the screening opinion adopted by the Council in respect of the First Application … which concluded that such effects are likely to be localised and would not, of themselves, warrant the submission of an EIA.”
“The appellants have prepared an environmental appraisal of the scheme which comprehensively covers the likely significant environmental impacts and areas of concern …”
“3. If either of the wind turbines hereby permitted fails to produce any electricity to the grid for a continuous period of 12 months, and if so instructed by the LPA, the wind turbine and its associated equipment shall be removed from the site within 12 months after the end of that 12 month period in accordance with a decommissioning and restoration scheme including a time table for its implementation which shall have been submitted to the LPA for approval not later than 3 months after the date of the LPA’s instruction to remove the turbine; … 12. No development shall take place until the developer’s outline mitigation scheme for compensatory feeding grounds for pink-footed geese has been worked up into a fully detailed mitigation scheme. The detailed scheme shall include arrangements for its implementation, management and maintenance for the lifetime of the proposed wind turbines. No development shall take place until the detailed scheme has been submitted to and approved in writing by the LPA. The turbines hereby approved shall not be brought into use until the approved mitigation scheme has been implemented in accordance with the approved details. If at any time during the lifetime of the wind turbines the mitigation scheme ceases to be maintained in accordance with the approved details the turbines shall not be operated until an alternative package of mitigation measures has been implemented in accordance with details that shall first have been submitted to and approved in writing by the LPA. The turbines shall not be operated during any period when any continuing requirements of the mitigation measures fail to be adhered to; … 17.
“Whether there is a “realistic prospect” of the Secretary of State changing his or her opinion as to the likely environmental effects of the development is pre-eminently a matter of planning judgment for the Inspector. The Inspector’s judgment on that issue can be challenged on rationality grounds. … It is not for the court to decide for itself whether there was or was not a “realistic prospect” of the Secretary of State making a different screening direction. … 24. "However, an applicant under section 288, which is of course concerned with an error of law on the part of the Inspector determining the appeal will face a formidable task in such a case … [which] … will succeed only if the court is satisfied that any rational Inspector would on the facts before the Inspector on that appeal have concluded that they should exercise the power to refer the matter back notwithstanding the fact that they had not been asked to do so by any party to the appeal”
“While there are considered [sic] significant potential impacts visually in terms of the two turbines, taking account of location and number of turbines and environmental information submitted I would not consider likely impacts of such significance in wider terms as to warrant ES”
“The 1999 Regulations are concerned to protect the environment in the public interest. Whilst this may have the effect of avoiding harm to residential amenity, the purpose of the 1999 Regulations is not to protect the amenity of individual dwelling-houses. There may be “significant” impact upon a particular dwelling or dwellings without there being likely “significant effect on the environment” for the purposes of the regulations. … In reality, there is a severe, but highly localised, shadowing effect upon a relatively few properties … that does not, in the context of the Regulations, amount to a likely significant effect on the environment such as to warrant an EIA”
“When forming a screening opinion, the council were not required to ignore either the conditions proposed to limit the scope of the development or the conditions providing for ameliorative or remedial measures. The consequences of providing the additional seating, and other changes, could not be predicted with certainty but as Collins J noted, the Council had extensive knowledge and experience, supported by surveys, of the impact of existing football league and cup matches on the environment. On the basis of that, and the studies as to future impact, they were entitled to assess the likely impact of the additional capacity proposed in the context of the continuing ameliorative measures also proposed and form the screening opinion that they did.” 41. The Claimant argued that I should not adopt the approach reflected in these authorities to which I have referred above but that I should instead refer the issue to the ECJ. This approach was said to be appropriate in light of a letter from Mr Buxton, the Claimant’s solicitor, to the EC Commission dated4th September 2007 and a short response from an official at the Commission dated30th January 2008 . The EC official maintained that the Commission’s view was that mitigation measures should be considered only once the requirement for an EIA had been established. I do not consider this to be a sound basis for inviting me to refer the issues I am now considering to the ECJ. At best this letter reflects the view of the Commission in January 2008. There is no authority cited for the view expressed by the Commission’s official and there is nothing in the EIAD that would appear to justify it. It ignores the logic of the reasoning set out in the authorities to which I have referred and does not appear to have been followed up with any administrative action. Given these factors, and that the domestic authorities clearly establish the approach to be adopted as a matter of English law, in my judgment the appropriate course for me to adopt is to follow the domestic authorities to which I have referred, one of which is binding upon me and with both of which I respectfully agree. 42. In my judgment this case is one of those that falls squarely within the parameters identified by Pill LJ as being one where the decision maker (here the SoS) was entitled to consider the effect of the proposed scheme together with the mitigation proposed for the purpose of arriving at a judgment as to whether there was a significant effect. This is plainly what the SoS did – see the question and answer referred to above. There is thus no basis for concluding that taking account of the effect of the mitigation elements of the scheme rendered the decision of the SoS either unlawful or irrational or that the Inspector acted unlawfully or irrationally in failing to remit the screening decision for further consideration by reference to this point. Whether the mitigation elements of the scheme were sufficient to overcome the objections raised by reference to the Habitats Issue to enable planning permission to be granted or granted subject to conditions was a matter for the planning judgment of the Inspector. 43. Finally in relation to this part of the case, it was submitted that the mitigation elements of the proposal could not rationally be treated as eliminating the likelihood of significant adverse environmental effect because of the qualifications contained in the NE letter of20th July 2010 . I am not able to accept this submission. First, it ignores the essential effect of that letter which is that (a) the scope of the mitigation elements of the scheme had been agreed between CLP, NE and RSPB and (b) that the effect of the mitigatory elements of the scheme was that the development no longer posed a likely significant threat to the integrity of the SPA. Secondly, the first three reservations on the second page of the letter were all drafting points not points of substance as is apparent from the acknowledgement that the scope of mitigation elements had been agreed. The remaining issue was that of funding and that was provided for under the terms of the detailed plan that had been produced. All that remained was to secure compliance. NE’s suggestion was that compliance ought to be secured by s.106 agreement. If and to the extent the Claimant relied on these points as justifying an unlawfulness or irrationality attack on the SoS’s decision to give a negative screening direction that is unarguable. The scheme taken as a whole was not likely to have a significant effect. The ways and means in which the scheme was to be carried into effect depended first on whether planning permission was granted at all and if so on what terms all of which were matters of planning judgment for the Inspector. If and to the extent that it is asserted that the Inspector ought to have remitted the proposal to the Secretary of State for him to reconsider his negative screening direction by reference to the issue I am now considering that is not arguable for similar reasons. If and to the extent it is argued that the Inspector’s decision to grant permission on appeal ought to be quashed by reference to the point I am now considering that is also unarguable because whether compliance was to be secured by s.106 agreement or by conditions was a matter of planning judgment as well. Condition 12 provides a comprehensive means of ensuring that the mitigation scheme is fully detailed, and is implemented, managed and maintained throughout the life of the turbines. No development can commence until a scheme has been approved by the LPA; the turbines cannot be used unless the mitigation scheme is first implemented and if the scheme ceases to be maintained then operation of the turbines has to cease. If they remain out of operation for a year then the LPA can require their removal. In this regard, the wording of Condition 12 makes it clear that the starting point for the detailed scheme that was to be worked out was the outline scheme that had led NE and RSPB to conclude that significant risk to the SPA had been eliminated. There is no basis on which it could credibly be said that the Inspector was intending the local authority to depart from the constraints of the scheme that had been agreed and approved as eliminating any significant relevant risk. It could not credibly be contended that the LPA could in effect reconsider the impact on the environment and depart from the essential elements of the mitigation elements of the scheme. For these reasons, I consider that this case falls within the parameters for conditions identified by the Court of Appeal in Smith v. SSETR[2003] EWCA Civ 262 [2003] Env.L.R. 693 44. In those circumstances, I am not able to conclude that the screening Decision or the Appeal Decision is tainted by either unlawfulness or irrationality in the ways relied on. Thus I reject the suggestion that the Inspector acted either unlawfully or irrationally in refusing to remit the decision to make a negative screening direction. To the extent that it is submitted that the Inspector acted unlawfully or irrationally by granting planning permission and not dismissing the appeal by reference to the Habitats Issue or other environmental issues that were relied on, I reject that submission as well. These were classically issues for the planning judgment of the Inspector. He was entitled to weigh the issues relied on in relation to the impact on the environment against the other factors he considered and to come to the conclusion that he came to. In relation to the Habitats Issue he was entitled to conclude that permission ought to be granted subject to a condition that left the fine detail of the mitigation elements of the proposal to be agreed with the local authority. Ground 1 whether of itself or in combination with the additional ground identified by Mr McCracken in the penultimate paragraph of his submissions does not justify quashing the Appeal decision. Ground 2 45. The challenge as set out in the Claim Form is that the Inspector erred in failing to conduct an Appropriate Assessment under Article 6(3) of the Habitats Directive. This refers to the need for such an assessment in relation to any plan or project “ … not directly connected with or necessary to the management of the site but likely to have a significant effect thereon …”