“Member States shall adopt all measures necessary to ensure that, before consent is given, projects likely to have significant effects on the environment by virtue inter alia of their nature, size or location are made subject to an assessment with regard to their effects. Those projects are defined in Article 4.”
“Where it appears to the relevant planning authority that -- (a) an application which is before them for determination is a Schedule 1 application or schedule 2 application; and (b) the development in question -- (i) has not been the subject of a screening opinion or screening direction; or (ii) in the case of a subsequent application, was the subject of a screening opinion or direction before planning permission was granted to the effect that it is not EIA development; and (c) the application is not accompanied by a statement referred to by the applicant as an environmental statement for the purposes of the Regulations.”
“If an application for development consent for an Annex I project is made without the environmental information required by the Directive, the authority must require the EIA procedure to be completed”
“contrary to the very purpose of the amended directive to allow any urban road project to fall outside its scope solely on the ground that the directive does not expressly mention among the projects listed in Annexes I and II those concerning that kind of road.”
“Applying the wide scope and broad purpose required by the ECJ in Ecologistas it would be astonishing to exclude the Cwmbargoed project. Moreover, the narrow interpretation of para 2(e) alleged by the opposing parties would be unduly restrictive for a number of other projects. It would, for instance, exclude all underground aspects of deepshaft coal mining for which environmental impacts are likely to be significant”
“The attempt to rely on the wide purpose of the EIA Directive to show that the developments permitted were within Schedule 2 is without merit. The opencast mining was dealt with through an enquiry and a fall EIA as it fell within 2(e). The DP (which has been doing the same for previous coal mines in Wales as it now does for Ffos-y-fran) cannot by any stretch of the schedule be within 2(e). To regard it as within 10(b) is an unjustifiable extension of the purpose of that and, since it does not itself fall within Schedule 2, and extension or modification equally cannot fall within it.”
“It is far too late to allow any claim to proceed against those.”
“…one is beyond the 3 month limit, one not, but both clearly stand or fall together and there has been a failure to act promptly. Delay in itself would justify a refusal of permission.”
“She considers that she will not have a fair trial. Opencast coal mining in Wales is highly contentious and the Claimant is concerned that any regional court may not be impartial. Further, she has continuing concern for her own safety and tension is likely to increase if the matter is heard in Cardiff. This will not be conducive to a fair and impartial hearing.”