"Mineral planning authorities should assess the need for wharf and rail facilities for the handling and distribution of imported materials and processed materials, and identify strategic sites for safeguarding in their mineral development frameworks. These strategic facilities should be safeguarded from other inappropriate development in local development documents."
"Dibden Bay is an area of former intertidal saltmarsh reclaimed over many decades by the deposit of dredged material from early development of the Port of Southampton. The site has, for many years, been identified as a possible site for port activities. Planning policies have, in one way or another, safeguarded the site from development pending a decision on the need to develop the site and it is identified in the current local plan as a Strategic Gap. However, the emergence of commercial arguments for port development on the site has coincided with the designation of the foreshore as a Special Protection Area and the growing awareness of the potential impact of all forms of development on the New Forest."
"Port development requiring access to deep water may be permitted at Dibden Bay provided that it can be demonstrated that the need for the development outweighs its impact on: (i) areas of importance to nature conservation; (ii) the conservation, landscape or ecology of the New Forest; or (iii) local communities; and (a) sufficient provision is made to offset the impact, including replacement or substitution of habitats or features lost and conservation of ecological networks; and (b) that the required access can be achieved without serious disturbance to the countryside, coastal areas or communities affected and that maximum use is made of rail and sea routes; and that appropriate contributions are secured to fund infrastructure and services required as a result of the development."
"If port proposals on this site meet the requirements of Structure Plan Review Policy EC6, are granted planning permission and are carried out, the need for the Strategic Gap between Marchwood and Hythe will be overridden."
"If port proposals on this site meet the requirements of Structure Plan Review Policy EC6, are granted planning permission and are carried out, then that part of the Strategic Gap would be overridden, but the amount of land taken for development should be minimised to retain as much of the Strategic Gap as possible. " (Emphasis supplied)
"The only site that has been suggested to date by prospective developers as being physically suitable for high capacity new deep-water wharfage for the large scale landing of sea-borne aggregates is at Dibden Bay on the western side of the River Test. In the event of any proposal for development at Dibden Bay which does not include provision of an aggregates wharf being put forward, an appropriate area of land (approximately 8 ha) will be safeguarded for a deep-water aggregates wharf. In the event that no other port development at Dibden Bay takes place, a high capacity deep-water aggregates wharf may be permitted provided that: (a) it can be demonstrated to the satisfaction of the local planning authorities that the need for the development outweighs its impact on: (i) areas of importance to nature conservation; (ii) the conservation, landscape or ecology of the New Forest; (iii) local communities; (b) sufficient provision is made to offset the impact, including replacement or substitution of the habitats or features lost and conservation of ecological networks; and (c) the required access can be achieved without serious disturbance to the countryside, coastal areas or communities affected."
"The core strategy should set out the key elements of the planning framework for the area. It should be comprised of a spatial vision and strategic objectives for the area; a spatial strategy; core policies; and a monitoring and implementation framework with clear objectives for achieving delivery. It must be kept up-to-date and, once adopted, all other development plan documents must be in conformity with it..."
"The local planning authority should ensure that policies and proposals in the core strategy provide certainty for the future. The time horizon of the core strategy should be for a period of at least 10 years from the date of adoption. However the core strategy should aim to look ahead to any longer-term time horizon which is set out in the relevant regional spatial strategy. The core strategy should be kept under review and the horizon rolled forward in subsequent reviews of the document." (Emphasis supplied)
"Policies relating to the delivery of site specific allocations, such as critical access requirements or broad design principles which may be sought, must be set out in a development plan document. They may be in the site allocation(s) development plan document(s), in an area action plan or in a separate development plan document. They should not form part of the core strategy ..."
"... strategic decisions cannot be left to subsequent [development plan documents]. If strategic decisions are devolved to subsequent [development plan documents], Inspectors will find it difficult to test the relationship between the [development plan documents]."
"[Local planning authorities] should be clear at the outset that the Core Strategy is where real and probably tough decisions have to be made. It is erroneous to presume that important strategic decisions can be devolved to subsequent [development plan documents], where it becomes more difficult to determine the effects at the strategic level. The Core Strategy should provide a clear guide for the preparation of the subsequent [development plan documents] or provide a base against which those [development plan documents] can be assessed. A Core Strategy must provide a strategic framework for lower level plans to target the delivery of issues and objectives of the Core Strategy through subsequent [development plan documents] An example of how that was intended to work, which serves as a useful illustration for present purposes, was set out in para. 5.2 of the document, which reads: "
"The purpose of an independent examination is to determine in respect of the development plan document - (a) whether it satisfies the requirements of sections 19 and 24(1)..., (b) whether it is sound."
"The presumption will be that the development plan document is sound unless it is shown to be otherwise as a result of evidence considered at the examination. The criteria for assessing whether a development plan document is sound will apply individually and collectively to policies in the development plan document. A development plan document will be sound if it meets the following tests: Procedural i. it has been prepared in accordance with the local development scheme; ii. it has been prepared in compliance with the statement of community involvement, or with the minimum requirements set out in the Regulations where no statement of community involvement exists; iii. the plan and its policies have been subjected to sustainability appraisals; Conformity iv. it is a spatial plan which is consistent with national planning policy and in general conformity with the regional spatial strategy for the region or, in London, the spatial development strategy and it has properly had regard to any other relevant plans, policies and strategies relating to the area or to adjoining areas; v. it has had regard to the authority's community strategy; Coherence, consistency and effectiveness vi. the strategies/policies/allocations in the plan are coherent and consistent within and between development plan documents prepared by the authority and by neighbouring authorities, where cross boundary issues are relevant; vii. the strategies/policies/allocations represent the most appropriate in all the circumstances, having considered the relevant alternatives, and they are founded on a robust and credible evidence base; viii. there are clear mechanisms for implementation and monitoring; and ix. the plan is reasonably flexible to enable it to deal with changing circumstances."
"The emerging South East Plan encourages the use of sustainable transport for the movement of minerals ... and given Hampshire's two commercial ports [the other being Portsmouth] and railway infrastructure, it should be possible to increase the use of sustainable transport. Hampshire currently has ten wharves with planning permission for landing dredged material; seven of these are located within and around Southampton, the rest around Portsmouth. Crushed rock is predominantly landed at Southampton docks but for commercial reasons this cannot be guaranteed in the future. Hampshire also has one wharf in Southampton that is used for the shipping of scrap metal to overseas markets, there are very few similar facilities in the region and it is therefore considered of strategic importance. However this site is identified in Southampton's Local Plan for redevelopment. If this proceeds, consideration will need to be given to relocation, preferably in Hampshire. Various bodies are investigating opportunities to use sustainable transport to move minerals other than by road. Any new developments in this area will need to be taken account of during preparation of the Hampshire Minerals ... Plan."
"The sustainable transport of minerals ... is supported and provision will be made for rail depots, sidings and wharves for the reception and movement of aggregates [and] recyclables ... by rail and short-sea shipping."
"Increasing the amount of sustainable transport of minerals ... is a key principle of this Strategy. It is important that development control decisions enable more minerals ... to be transported by sustainable means, this includes a policy framework that supports additional infrastructure for sustainable transport."
"New or extended wharves, rail depots and other transport infrastructure that enables the sustainable transport of minerals ... and resources by rail or sea will be permitted, provided the site is suitable for the use and it will not impede planned regeneration."
"A review of wharves and depots will be carried out during the preparation of the Hampshire Minerals ... Plan. This review will [assess] the ongoing suitability of existing sites, particularly in the light of their transport connections and regeneration proposals. It is likely that some new requirements will be identified and these should be generally supported."
"22.1 The emerging South East Plan recommends that Minerals ... Frameworks ... should safeguard infrastructure facilities ... 22.2 Given the conflicting demands for land and the increased premium on the price of housing land, it is important to safeguard minerals ... sites to preserve capacity for the future. However, sites should not be safeguarded where there is little realistic possibility of them being required in the future."
"All existing minerals ... sites, including associated transport infrastructure, which are needed for future requirements will be safeguarded. These requirements will be determined by a review of all such sites. Pending the outcome of this review, all existing sites will be safeguarded. Incompatible development, within 250 metres of existing or planned quarries and landfills or within 50 metres of other mineral ... operations, will not be supported."
"22.3 With the exception of sites already allocated in existing Local Plans for alternative uses, all existing permitted or operational minerals ... facilities, and 'saved' Preferred Areas are safeguarded. Planning bodies should consult the Mineral ... Planning Authorities prior to the consideration of proposals for development, on or within 250m of existing or planned quarries or landfill sites or in the case of other types of mineral ... site on the site of or within 50m. 22.4 A review will be carried out, and the Proposals Map updated accordingly, as part of the development of the Hampshire Mineral ... Plan. The purpose of the review will be to: (i) Assess whether all existing, permitted or operational minerals ... facilities, including wharves and depots, are appropriate for safeguarding taking into account operational effectiveness, overall future mineral ... needs and the degree to which alternative use of the land would promote positive regeneration on that site; (ii) Assess whether non-developed Preferred Areas, identified in the existing Local Plan, are suitable for future development."
"Sites and locations for the minerals ... development required by this Strategy will be identified in the ... Hampshire Minerals Plan, using the methodology and factors identified in Appendix 2."
"21.3 A combination of deep water accessibility for large vessels, access to the rail network and a central south coast location means that Southampton has historically provided valuable facilities for the import of crushed rock in large vessels, to the benefit of Hampshire and a wider area of southern and south west England. However, as a low value high weight commodity, crushed rock is now unable to compete for space in the docks against higher value uses. The trade therefore ceased in 2006, and it is neither possible to safeguard a site within the existing docks for its resumption nor identify a new site within the existing docks. 21.4 During the lifetime of the Strategy, there will nonetheless be a continuing need for facilities for the import of crushed rock, which is most sustainably carried by sea, for distribution within Hampshire and further afield. Investment is therefore required to provide a new wharf. Within the New Forest Local Plan a site within the Port of Southampton, with easy access to deep water has been allocated for port development subject to certain criteria being met. The Minerals Planning Authorities will seek the provision of a high-capacity deep water aggregate wharf in this location, either separately or as part of those proposals."
"The sustainable transport of all types of minerals ... is supported. and Provision will be made for all rail depots, sidings and wharves for the reception and movement of all types of aggregates [and] recyclables ... by rail and sea short sea shipping ."
"Wharves and Rail Depots Key issue - Is the Strategy for Wharves and Rail Depots consistent with national and regional guidance, soundly based and appropriate for Hampshire & the New Forest, particularly in terms of the adequacy of provision for importing crushed rock? 7.94 Policy S13 supports the sustainable transport of minerals and waste and provides for associated rail depots, sidings and wharves. RPG9 Policy M5 requires [mineral planning authorities] to assess the need for wharf and rail facilities for handling and distributing imported minerals and processed materials and identify strategic sites for safeguarding. The emerging [South East Plan] encourages the use of sustainable transport for movement of minerals and waste, whilst both national and regional policy envisage an increased supply of marine-dredged sand and gravel in the future. All this points to a need to identify and safeguard the necessary facilities for handling, transporting and distributing minerals and waste materials. However, RPG9 does not set out any apportionment for the import of such materials, or identify capacity requirements. 7.95 The [mineral and waste planning authorities] confirm that the [Core Strategy] safeguards all wharves and depots for the import of crushed rock and marine-dredged sand and gravel, apart from the Port of Southampton, for which ABP is the statutory authority. This [development plan document] does not itself identify strategic sites for wharves and depots or indicate whether present capacity will be maintained, increased or reduced, since this will be considered in a review of existing/future capacity in the subsequent Hampshire Minerals Plan. Until the results of this review are known, all existing wharves and rail depots are safeguarded under Policies S13 & S14, in line with MPS1 (¶ 13) & RPG9 Policy M5. At present, considerable quantities of crushed rock are imported into Hampshire, either by rail or via dockside wharves. Topic Paper [TP2J provides an overview of the current capacity at existing wharves, and estimates current throughput of some 2.29 [million tonnes per annum] and a maximum capacity of 4.39 [million tonnes per annum]. 7.96 Policies S13 & S14 provide the general safeguarding necessary for existing wharves and rail depots, without being specific. Initial work on the review of facilities confirms that existing wharves have the capacity to handle almost twice as much material as currently occurs. Future requirements, including any additional capacity necessary will be identified in the subsequent [development plan document], following completion of the review of existing facilities. In the meantime, the potential capacity available at existing wharves and depots will enable increased demand to be met. In my view, this strategy reflects national and regional policy (including the latest guidance in MPS1), will ensure sufficient protection of existing facilities and enable specific provision to accommodate the required capacity. 7.97 There is some concern that existing facilities will not be able to accommodate future handling and distribution of minerals, particularly the import of crushed rock at wharves in the Southampton area. Although Southampton Docks has imported considerable quantities of crushed rock into Hampshire, due to commercial considerations it now handles other materials, but the previous importer does not see the constraints over its availability as a problem. Crushed rock is also imported at other wharves and depots in the Southampton area. The [Core Strategy] (¶ 20.6) confirms that the import of crushed rock is an invaluable aggregate mineral resource for Hampshire, particularly since it has no indigenous hard rock resources. 7.98 However, although there are no controls on the quantities of crushed rock and other materials that are imported into Hampshire, such materials do not form part of the sub-regional apportionment for the county, since it is to some extent dependent on market demand. Furthermore, there are no estimates available at county-level of the future quantity of crushed rock imports. I recognise that Southampton Docks is one of the few deep-water docks able to handle long vessels, but the use of this facility to import and handle crushed rock or other minerals is not directly within the [mineral planning authorities'] control, and largely depend on commercial considerations and operators' needs. 7.99 I realise that Dibden Bay is allocated as a new deep-water wharf in the approved Structure Plan and adopted New Forest Local Plan (2005), which acknowledges its national and regional significance. It is also a location where deep-draught ships (such as those carrying aggregates) can be handled. However, there are no current plans to bring forward such a facility, and a similar proposal was rejected by the Secretary of State in 2003. There is no certainty that such a proposal (including an aggregates wharf) would be developed within the period of this [development plan document], particularly given the timescale involved, the history of this project and its potential impact on habitats, biodiversity and designated landscapes. The regional need for such a facility, including potential locations and the role of Southampton, has not been established in RPG9 or the emerging [South East Plan]. No recent assessment or [environmental impact assessment/sustainability appraisal/appropriate assessment] of a specific site or proposal has been undertaken, which would be needed if the site was to be highlighted or proposed in this [development plan document]. Consequently, I find there is insufficient evidence to justify the inclusion of such a strategic proposal in this Core Strategy at this time, either as a new proposal or to offset any lack of availability of Southampton Docks. If such a proposal came forward as part of the site-selection stage in subsequent [development plan documents], it could be considered against the framework of this [development plan document], either as a proposal or an 'omission' site. 7.100 In all these circumstances, particularly given the potential capacity available for importing crushed rock and other minerals at existing wharves and depots, I can see no need to identify the need for additional facilities at this stage, in advance of the detailed review envisaged in the subsequent [development plan document]. In the meantime, there seems to be sufficient potential for the existing wharves and depots to accommodate any increased demand for additional capacity to import crushed rock and marine aggregates without the need for further facilities, deep-water or otherwise. Consequently, I cannot see sufficient justification to make specific provision for new deep-water wharves to handle long-distance transportation of crushed rock in this strategic [development plan document] at this stage. 7.101 However, the [mineral and waste planning authorities] suggest amending Policy S13 to recognise the significance of longer sea voyages for minerals, as well as short-sea shipping, since this is an important aspect of the movement of such materials. The [mineral and waste planning authorities] also suggest amendments to the accompanying text (¶ 21.2) to properly reflect the existing situation. With these suggested amendments, I consider the strategic policy relating to wharves and rail depots is soundly based. 7.102 Policy DC18 supports additional infrastructure to enable sustainable transport of minerals and waste materials, including new or extended wharves and rail depots, subject to site suitability. As part of the review of wharves and depots, any new facilities would be subject to Policy S18 and the process and factors set out in Appendix 2. I am satisfied that this provides an appropriate and supportive policy framework to consider proposals for new and extended facilities at the planning application stage and in subsequent [development plan documents] Recommendation 10 In order to make the Strategy sound, the following changes are required: (a) amend Policy S13 to acknowledge the need for longer distance sea shipping of minerals and waste materials; (b) amend paragraph 21.2 to more accurately reflect the existing situation in terms of import of crushed rock; (Change Nos. 28-29 in Annex A of my report)."
"The emerging South East Plan encourages the use of sustainable transport for the movement of minerals ... and given Hampshire's two commercial ports and rail infrastructure, it should be possible to increase the use of sustainable transport. Hampshire currently has ten wharves with planning permission for landing dredged material; seven of these are located within and around Southampton, the rest around Portsmouth. Crushed rock is landed in two locations, however it is predominantly landed at Southampton docks but and for commercial reasons this cannot be guaranteed in the future. Whilst the emerging South East Plan gives no direction on the need or significance of the landings at Southampton docks, it is known that crushed rock also enters Hampshire by rail into depots at Eastleigh, Botley and Fareham, in small amounts at one other wharf and small amounts into the south west of Hampshire by road. Anecdotal evidence indicates a market preference in the South Hampshire area for rail importation. In the absence of regional guidance on this matter, it is not proposed to actively seek sites for deep-water crushed rock wharves, however should suitable opportunities arise out of nominations from industry and landowners, and/or as a result of the review of existing sites detailed in Appendix 2 paragraph 1.3, they will be included in the Hampshire Minerals Plan. Hampshire also has one wharf in Southampton that is used for the shipping of scrap metal to overseas markets, there are very few similar facilities in the region and it is therefore considered to be of strategic importance. However, this site is identified in Southampton's Local Plan for redevelopment. If this proceeds, consideration will need to be given to relocation, preferably in Hampshire. Various bodies are investigating opportunities to use sustainable transport to move minerals ..., other than by road. Any new developments in this area will need to be taken account of during preparation of the Hampshire Minerals ... Plan"
"The sustainable transport of minerals ... is supported and provision will be made for rail depots, sidings and wharves for the reception and movement of aggregates [and] recyclables ... by rail and sea, including short-sea shipping."
"Sites identified, in the Hampshire Minerals ... Plan, or on the Proposals Map, to fulfil the requirements of this Strategy, will also be safeguarded."
"In the meantime, the potential capacity available at existing wharves ... will enable the increased demand to be met."
"If such a proposal came forward as part of the site-selection stage in subsequent [development plan documents], it could be considered against the framework of this [development plan document] ..."
"Foster Yeoman has closed the dock operation on good terms with the port operator but the reality has always been that land has only been available when not required for higher value uses. Unless there is land safeguarded for development (e.g. container handling facilities) it is very likely that there will be none available for aggregates as and when the market can sustain the very high port costs generated by other commercial uses. A similar position is now faced on the Thames where pressure for redevelopment of berths for commercial and housing uses means that sites that are otherwise available for the import of aggregates are not released by landowners because of the huge disparity between commercial and housing value and that sustainable by an aggregates operation. This has resulted in the adoption of a safeguarding policy by the GLA backed up by CPO powers and currently being tested on appeal. The difficulty at Southampton is that it is not currently economic to import through the dock for the general aggregates market but undoubtedly the pressure for an alternative to crushed rock from the Mendips and locally won sand and gravel will grow. In order to keep this option open it will be necessary to safeguard a potential site, alongside deep water berthing in open (undeveloped) use, retaining the option for aggregates as and when this becomes viable again" (Emphasis supplied)
"It would need to be done. You are talking of [a] procedural requirement that can easily be done."
"... recyclables ... by rail and sea, including short-sea shipping"