“91. Belfields accept that the area is in need of regeneration. The site is significant due to its size (2.2 hectares) and the number of dwellings it could accommodate. Belfields accept that its timely redevelopment is vital to transform the area. There is nothing between the parties as to the need for the development of the site, the nature of the redevelopment or the timescale. The dispute is how that can be delivered in line with the timescales that the Council has to meet under the Deed of Variation. 92. Belfield’s objection is that there is no need for the CPO, as they have their own proposals which have the benefit of planning permission. The Council would be content if the objector delivered the redevelopment of the Penpoll site within the timetable they have offered, subject to ensuring that the Council’s aspirations are met. The difference between the objector and the Council is whether there should be any mechanism to ensure that development should take place in the event of default.”
“With this background, the issue between the parties is a narrow one, and focuses on the mechanism by which the development of the site can be guaranteed. The concern is whether there is sufficient assurance that development will actually take place, in the light of access to funding and expertise.”
“353. In conclusion, although there is evidence of informed developer interest, there is no formal relationship with any developer. Therefore there is considerable uncertainty that this key development will go ahead without the Council’s intervention. Likewise there is no expertise on the part of the objector themselves to carry out the development. There is therefore no assurance that the development would actually take place, and confirmation of the CPO would provide this necessary certainty.”
“382. It was accepted at the inquiry that the Mel Inn would consider relocation within their current catchment area. This catchment area includes the Penpoll site on the opposite side of Hawthorne Road and, in 2005, the Council considered community facilities in the area, and this process identified a need for a facility of a similar scale to the Mel Inn. 383. The Bellway reserved matters scheme (2006) for the Penpoll site includes a social club, intended to take account of the Mel Inn. The ‘alternative’ reserved matters approval obtained by the owners (Belfields) of the Penpoll site also includes a licensed function room, and the landowners have acknowledged their willingness to include a community facility. The Mel Inn was identified as a possible anchor tenant in 2006 for such a new facility, but it was stated that the Mel Inn had indicated that it did not want to take on that role. 384. There therefore seems no reason in physical terms why the Mel Inn should not relocate onto the Penpoll site. The Council stated that an offer, including a disturbance payment, was made to the Mel Inn in February 2006, and that the only remaining obstacle was one of price. The Mel Inn declined to comment on this assertion at the inquiry, and there is no reason to doubt the Council’s uncontested statement… 386. Overall, the Mel Inn should clearly be acquired under the CPO given its pivotal position. The continuing presence of the existing building would detract from the redevelopment of the area. There is no reason why it should not continue to function from within its existing catchment area.”
“12. The Secretary of State agrees that, in respect of the Penpoll site, the owner (Belfields) has alternative plans for the redevelopment of their site and has made substantial progress towards implementation, and that there is an extant planning permission obtained by Belfields for a scheme similar to that of Bellway (IR341). She also agrees, however, that there is considerable uncertainty that this key development will go ahead without the Council’s intervention. The Secretary of State agrees, therefore, that there is no assurance that the development would actually take place, and confirmation of the CPO would provide this necessary certainty (IR353).”
“14. In respect of the Mel Inn, the Secretary of State agrees that it provides a range of entertainment, functions and sporting facilities seven days a week. She also agrees that there is no dispute between the objector and the Council that there is a need for a facility of the type currently provided by the Mel Inn and that the need for such a facility may well increase once redevelopment has taken place and the population increases (IR374). However, she agrees with the Inspector that at best it could be described as utilitarian, resembling an industrial shed. She agrees that even in its current setting, surrounded by cleared sites, it adds nothing to the appearance of the area. She agrees that when the surrounding sites are redeveloped, it will look even more out of place, and will eventually detract from its surroundings (IR377). She agrees that this is clearly an important site in a prominent location and that the existing building would provide neither the massing nor the quality required for this important corner site (IR378). She agrees that there seems to be no reason in physical terms why the Mel Inn should not relocate onto the Penpoll site (IR384). The Secretary of State agrees with the Inspector, therefore, that the Mel Inn should clearly be acquired under the CPO given its pivotal position at the centre of the order lands. She agrees that the continuing presence of the existing building would detract from the redevelopment and that there is no substantial reason why it should not continue to function from within its existing catchment area (IR386).”
“17. A compulsory purchase order should only be made where there is a compelling case in the public interest. An acquiring authority should be sure that the purposes for which it is making the compulsory purchase order sufficiently justify interfering with the human rights of those with an interest in the land affected. 18. The confirming Minister has to be able to take a balanced view between the intentions of the acquiring authority and the concerns of those whose interest in land it is proposed to acquire compulsorily.”
“(iv) Whether the purpose for which the acquiring authority is proposing to acquire the land could be achieved by other means. This may involve considering the appropriateness of any proposal put forward by the owners of the land, or any other persons for its use.”
“I regard it as a principle of our constitutional law that no citizen is to be deprived of his land by any public authority against his will, unless it is expressly authorised by Parliament and the public interest decisively so demands…If there is any reasonable doubt on the matter, the balance must be resolved in favour of the citizen.”
“She agrees, however, that there is considerable uncertainty that this key development will go ahead without the Council’s intervention.”
“347. The site has an important frontage onto Hawthorne Road, and would include a substantial proportion of the overall new housing planned for the Order Lands, as well as retail uses, community facilities, and environmental improvements. It would make a key contribution to the regeneration of the area, and if there is a significant level of uncertainty over the ability of the objector to undertake the development, this would justify the CPO. There are three remaining uncertainties related to the objector’s intention to redevelop the site.”
“372. In conclusion, although there is evidence of some developer interest, there is no formal relationship with any developer. Likewise there is limited expertise on the part of the objector to carry out the development. There is no persuasive explanation as to how the objector can go from the current position to completion of development in 2 years, and there is no provision in the submitted S106 obligation to enable the Council to undertake the work in default. There is therefore considerable uncertainty that this important development will go ahead, and confirmation of the CPO is therefore justified.”
“415. The whole process of a CPO carries with it inherent uncertainty. It is not a persuasive argument to suggest that, in a CPO covering a wide range of interests, omission of individual sites would cause the entire scheme underpinning the CPO to fall. That would be to assume that the bodies seeking to promote and support the CPO have excessively rigid systems, which are unable to react to changing circumstances.”
“348. Firstly, although it is clear that substantive discussions have taken place with a major developer, these discussions have not resulted in a concluded agreement. The most recent evidence is that technical investigations need to take place before any exchange of contracts, and there is a reference to gaps in the technical data. In addition, George Wimpey Main Board approval would need to be sought. In the absence of a concluded agreement, these matters cause a substantial amount of uncertainty. 349. Secondly, neither the objector nor any potential developer partner have been in discussions with the Riverside Housing Association, who would be likely to be the social housing provider. Only very initial comments have been received from Riverside, instigated by the Council’s consultation on the planning application submitted by the objector. It is true that house builders such as Wimpey can bid for Housing Corporation funding for social housing, but there is nothing to suggest that this has happened. At the very least, this could lead to redesign and delay. 350. Thirdly, should Wimpeys or another developer not be confirmed, it has not been suggested that the objector themselves has the necessary expertise to undertake the development. If final agreement is not forthcoming with Wimpeys or another developer, there is considerable doubt as to whether the objector would be in a position to undertake the work themselves. 351. The Council’s suggested Development/Suspension Agreement would have enabled the objector to go ahead with their proposal, but would have provided the important fallback that the council could step in. No response was made by the objector to the suggested Agreement, nor any explanation of any perceived problems. The suggested Agreement would have provided that the Council would not act upon it until it was reasonably apparent that the objector was unable to comply with and/or procure the development of the site.”
“85. The letters from Persimmon and George Wimpey demonstrated clear and obvious developer interest. This has been progressed further by a more recent letter from Wimpey, which states their preparedness to purchase the site, subject to matters set out in the letter (sections of the letter redacted for reasons of commercial confidentiality). The developers are competent, experienced and extremely well resourced. Self evidently, whilst there remains a CPO it is unrealistic to expect the conclusion of a joint venture agreement. However, the fact remains that this is a demonstration of the high level of interest. Both developers were made aware of the contents of the S.106 Obligation and the proposed timescales contained within it.”
“371. Fifthly, there is doubt as to the costs of remediation [111, 114, 118-120, 141-142]. The objector accepts that this may have caused uncertainty in the past, although recent work may have gone some way towards resolving this. However, there remains a considerable difference (estimates from around£0.5m to£2.2m ) between the objector’s position and that of the Council, and although the eventual costs would have to be carried by any developer, this adds to uncertainty.”
“There is now an agreed statement between the experts, noting that the current investigative work is insufficient to be able to develop a detailed remediation strategy. The cost of carrying out such work is in the range£0.5m to£2.2m , and it is agreed that the objector’s estimate of remedial work does not include the provision of a clean capping layer or the provision of ground gas protection measures.”
“369. Thirdly, there is doubt whether the objector has the ability to undertake the development themselves, if a development partner does not materialise. The disputed question of the financial resources available to Nextdom was not resolved. However, whatever resources may be available to the objector, there is the additional concern that the company does not have the necessary expertise to undertake a development of this nature, as their track record of developing purely residential developments is limited. The combined effect of these matters is to cast doubt on whether the objector would be in a position to undertake the work themselves, in the event that no developer partner were forthcoming.”
“367. Firstly, although it is clear that some discussions have taken place with developers, these discussions have not resulted in a concluded agreement. The objector purchased the site in 2002, although discussions with the Council until 2004 focused on employment uses. Since that time, the objector has stated that discussions have taken place with a number of housebuilders, although it was sated that a number had been put off by the threat of the CPO or concerns about the Council’s even-handedness. However, these allegations were not substantiated. It was clear at the beginning of the Inquiry that a contract with a developer was anticipated, but this did not materialise by the time the Inquiry closed over three months later. The length of time during which the site has been in the objector’s ownership and has not been developed lends a substantial degree of uncertainty to the position.”
“356. However, Nextdom considers that the site can and will be developed without the CPO. The Council has stated that if there is evidence that the owner of a site or a developer can progress the development, in accordance with the SPG for the area, then the Council would see no need to acquire the land by compulsion. It is agreed that there is no need for the entire development underpinning the CPO to be carried out by a single developer, and that there is no reason why the objector or their developer partner should not carry out the development.”
“361. Secondly, the ODA is said to fetter the Council’s discretion by restricting the circumstances in which, if the CPO is confirmed, the Council can choose not to acquire a given site. The argument is that the ODA requires the Council to implement the confirmed CPO on particular sites, which conflicts with the assurance that it would not necessarily do so. This would not leave open the possibility of the landowner developing the site. However, the ODA obliges the Council to use all reasonable endeavours to secure the vesting of all outstanding interests. If the Council had agreed not to enter onto an objectors land on condition that the objector carry out the development in accordance with an agreed timescale, then it would not be reasonable to secure entry. This gives the Council the necessary flexibility.”
“Now, there is no doubt that under those agreements the Council was offered financial support under the regeneration of pathfinder areas programme and that certain targets were set for the acquisition of properties, the demolition of properties and so forth, and funding was provided upon the basis that those targets would be met. However, the answer to this point is to be found in both the skeleton argument of Mr Maurici and in the skeleton argument of Ms Patterson QC on behalf of the local authority. Clearly there cannot be any dispute that the Secretary of State does have a policy of encouraging the regeneration of pathfinder areas in the manner proposed by this council and, that because there is such a policy, funding is provided for its implementation. But that is a very long way from saying that the outcome of any particular compulsory purchase order or the fate of any particular property in a compulsory purchase order is effectively a foregone conclusion. As the Franklin case (Franklin v Minster of Town and Country Planning[1948] AC 87 ) demonstrates, while there may in principle be unlawful pre-determination, it exists only if the Secretary of State has forejudged any genuine consideration of objections to a Compulsory Purchase Order and simply does not genuinely consider the objections that have been made. One only has to read the Inspector's report for it to become perfectly obvious that the Inspector did very carefully consider all of the points made in respect of each individual objector, and reached conclusions in respect of them. I accept that the objectors do not agree with those conclusions, but the conclusions were open to the Inspector on the evidence. The Secretary of State has accepted those conclusions. Thus there is no evidential basis for the claim that there was in some way prior approval.”
“That criticism of the change in the rules is wholly misconceived. The change in the rules reflected the reality in planning and Compulsory Purchase Order inquiries and other inquiries of a similar kind. It is very difficult to disentangle straightforward findings of fact from matters of judgment or opinion and thus one very often sees findings of fact and conclusions and opinions mixed up. Thus, whether a site is a particular acreage or not is a question of fact; whether it is unduly prominent, whether it is run down, why it is run down, those are matters of opinion, and judgment. Thus it is that conclusions are required from an Inspector and those conclusions will embrace both matters of fact and matters of opinion or judgment on which the Inspector will ultimately make his or her recommendation. If it can be demonstrated that in reaching his or her conclusions the Inspector has omitted to make an essential finding of fact, not a matter of disputed judgment, then that may form the basis of a legal challenge, because if the Inspector has not found an essential fact then neither the Inspector nor the Secretary of State would have been able to take it into account as a relevant consideration. So the rules first of all reflect the reality, that is to say the difficulty of distinguishing between fact and opinion in cases like this but, secondly, they do not preclude the possibility of a legal challenge upon the basis that it was necessary to find a particular fact and that fact was not found.”
“As a result significant facts which emerged through cross-examination, supporting the objectors case, are not reported.”
“186. The general case is largely taken from closing submissions, as no general evidence (apart from the particular experience of individuals affected) was submitted. 187. Over the last 2/3 years the area has been in decline, and local residents have reported a lack of security and no faith in the future. The effects of the MHRI programme have been negative, with many residents moving away from the area. 188. In closing, Venus introduced a report 197 from summer 2006, which updated the key findings of the 2005 Housing needs Assessment Update. Particular attention was drawn to the fact that Sefton’s house prices are significantly above the regional average and are the highest in Merseyside. The increase in house prices in Bootle was also stressed 198. The report notes that Bootle has moved from having an excess of affordable housing in 2003, to having the second most pressing needs in Sefton 199. The report also that HMRI pathfinder is not tasked with meeting affordable housing needs, except as they arise from the HMRI process 200. 189. The CPO is based on the assumption of housing market failure, but this itself was based on the discredited CURS Report201. In closing, Venus presented a table 202 of tenure profile and voids on the Klondyke Estate from 2000 to 2006. None of the Council’s evidence shows information on vacancies or voids, and the whole concept of housing market failure is challenged. 190. There is a continuing need for the type of properties which exist on the Klondyke estate, as is shown by the Council’s Housing Register. Only when voluntary acquisition and tinning up began did voids begin to grow. The Council’s own evidence 203 demonstrates a Borough wide shortage of smaller accommodation – the type of accommodation which the Council are proposing to demolish on the Klondyke estate. 191. The decision not to relet properties (September 2003) has had a consequential harmful effect on the area. This is demonstrative of housing management failure, not housing market failure.”
“308. The cumulative effect of these factors, as presented in a convincing and comprehensive manner by the Council, is that the area has gone beyond the point of no return, and that radical intervention is necessary. The overwhelming balance of the evidence is that the residential part of the Order lands and the wider South Sefton area have been experiencing low demand and increasing vacancy rates for many years, and that this has led to housing market failure.”