"Member States shall take the necessary measures to ensure that waste is recovered or disposed of without endangering human health and without using processes or methods which could harm the environment and in particular - ... without causing a nuisance through noise or odours..."
"... the competent authority shall discharge their specified functions insofar as they relate to the recovery or disposal of waste with the relevant objectives."
"ensuring that waste is ... disposed of without endangering human health and without using processes or methods which could harm the environment and in particular without ... (ii) causing nuisance through noise or odours."
"An objective in my judgment is something different from a material consideration. I agree with Richards J that it is an end at which to aim, a goal. The general use of the word appears to be a modern one. In the 1950 edition of the Concise Oxford Dictionary the meaning now adopted is given only a military use: 'towards which the advance of troops is directed'. A material consideration is a factor to be taken into account when making a decision, and the objective to be attained will be such a consideration, but it is more than that. An objective which is obligatory must always be kept in mind when making a decision even while the decision-maker has regard to other material considerations. Some decisions involve more progress towards achieving the objective than others. On occasions, the giving of weight to other considerations will mean that little or no progress is made. I accept that there could be decisions affecting waste disposal in which the weight given to other considerations may produce a result which involves so plain and flagrant a disregard for the objective that there is a breach of obligation. However, provided the objective is kept in mind, decisions in which the decisive consideration has not been the contribution they make to the achievement of the objective may still be lawful. I do not in any event favour an attempt to create an hierarchy of material considerations whereby the law would require decision-makers to give different weight to different considerations."
"Existing ambient noise levels have been measured at four sensitive noise locations around the proposed site boundary and a detailed analysis of the potential impacts has been submitted with the application. It shows the predicted noise impact to be within MPG 11 criterion at all properties. In the event of a grant of planning permission the Environmental Health Officer agrees that it would be appropriate to condition noise levels as above and to require ongoing monitoring."
"There are two principal sources of odour from landfill sites; freshly deposited waste and landfill gas (LFG). Like dust, the generation and dispersal of odours is dependent on the wind speed, temperature and precipitation. The applicant is proposing to adopt a number of good working practices that can substantially reduce the generation and disposal of odour. These are: • minimising the extent of the operating area; • the daily application of cover materials, such as inert soils; • progressive restoration; • any waste previously identified with an odour problem should be deposited directly in pre-prepared trenches excavated into dry waste and immediately covered. In the long-term, the applicant proposes that upon cessation of landfill operations, continued odour mitigation would be provided by the engineered containment liner and cap preventing the escape of odourous gases to the atmosphere and the active abstraction and burning/flaring of landfill gas. Some objectors have raised odour as an issue and I acknowledge that some individuals may be more sensitive to smells than others. To minimise future odour impact I recommend that a detailed scheme for the control of odour should be submitted for approval if planning permission is granted and that the following are incorporated as agreed by the Environmental Health Officer: • implementation of a monitoring scheme; • results of smell monitoring to be submitted to the Council together with details of any remedial action taken and any complaints received by the operator about smell. I am satisfied that, subject to rigorous adherence to the above practices and conditions that could be imposed as part of a planning permission, long term nuisance impacts associated with odour should not arise."
"This ground of the challenge relates to the objectives under the 'Waste Framework Directive' relating to human health and harm to the environment. The claimant refers to an obligation on the part of the County Council to have had in mind the objective of avoiding impacts such as noise and dust, as explained by the Court of Appeal in Thornby Farms v Daventry District Council; Murray v Derbyshire County Council[2002] EWCA Civ 31 by refusing permission rather than just reducing them to below a threshold. Your reporting officers consider that the report of 11 March does demonstrate that the Council did keep the relevant objectives in mind."
"18) All plant and machinery shall be silenced at all times in accordance with the manufacturers' recommendations. 19) The noise levels arising from the developments, with the exception of temporary operations, shall not exceed 55dB(A)Leq (1hr) at any noise sensitive property. 20) Noise levels arising from temporary operations shall be minimised as far as is practicable, shall not exceed 70dB(A)Leq (1hr) measured at any noise sensitive property and shall not continue for more than eight weeks in any 12 month period. Any bund or mound constructed under this exemption shall be in accordance with a scheme that shall have received the prior approval of the Waste Planning Authority. The scheme shall provide for the minimum impact on the landscape and upon nearby residential property. The commencement of all temporary operations carried out in accordance with this condition shall be notified to the Waste Planning Authority before such works commence. 21) No development authorised by this permission shall take place until a scheme for noise monitoring at the site has been submitted to and approved by the Waste Planning Authority. The noise levels from the site shall be monitored in accordance with the approved scheme."
"22) A scheme for the monitoring of smells generated by the site shall be submitted to the Waste Planning Authority three months before the first deposit of waste. Monitoring and control of smells shall be undertaken in accordance with an approved scheme or as subsequently modified in writing by the Waste Planning Authority. The scheme shall include: ... (vi) what would trigger remedial action; (vii)details of remedial action that would be taken... "
"'environmental statement' means a statement - (a) that includes such of the information referred to in Part I of Schedule 4 as is reasonably required to assess the environmental effects of the development and which the applicant can, having regard in particular to current knowledge and methods of assessment, reasonably be required to compile, but (b) that includes at least the information referred to in Part II of Schedule 4."
"1. A description of the development comprising information on the site, design and size of the development. 2. A description of the measures envisaged in order to avoid, reduce and, if possible, remedy significant adverse effects. 3. The data required to identify and assess the main effects which the development is likely to have on the environment. 4. An outline of the main alternatives studied by the applicant or appellant and an indication of the main reasons for his choice, taking into account the environmental effects. 5. A non-technical summary of the information provided under paragraphs 1 to 4 of this Part."
"13.4.36. The potential health effects of landfill sites have been the subject of epidemiological studies, and the presentation of the findings of a recent study has caused some concern in respect of proposed new facilities. However, the evidence available does not support a causal link between the health effects studied and proximity to landfill sites. 13.4.37. The proposed landfill at Smiths Void would be operated to the highest environmental standards and the operation would be independently regulated by the Environment Agency. The management and regulation of the site would ensure that the potential risk to the site employees, local communities and the wider environment were minimised."
"A report subsequently amended to include congenital anomalies data has been produced on the impact of the proposal on the local population. It is held in the Environmental Services Department for Members' inspection and will be available at Committee. The covering response states: "
"I accept that in this case fear regarding adverse health effects as expressed by objectors should not be viewed as baseless, since the possibility of risk to health cannot entirely be dismissed. Accordingly, it is appropriate to afford some weight to this genuinely held view. The Area Health Authority's (AHA) amended report and correspondence evaluates recent studies, takes account of specialist advice and examines rates of congenital anomalies in the electoral Wards adjacent to Glapwell compared to the North Derbyshire average. The results over a four year period from 1997 to 2000 illustrate no significant difference. The AHA's conclusions would not, in my view, support a rejection of the application on health related grounds. I am also mindful of the fact that the ongoing 'health' debate has not led to health issues being accorded significance within national planning policy guidance relating to waste management facilities including landfill. Notwithstanding the above, the AHA has pointed out that anxiety relating to operations at landfill sites can lead to a variety of health concerns. I would agree with its conclusion that this could largely be avoided if the local population have confidence in the site operator to maintain a clean and safe site. The early establishment of a Liaison Committee for the duration of the operations as agreed by the applicant can also be an effective way of alleviating concerns. Additionally, I have raised with the applicant the possibility of a condition specifically restricting the deposit of hazardous waste as a means of providing assurance to the public. While I believe that there is general recognition of the meaning and character of municipal domestic waste, there is less public understanding of the terms commercial and industrial waste. There is also widespread concern that this is likely to involve toxic substances as evidenced by the objection notices displayed locally. I have suggested a condition to the application the wording of which makes reference to the Hazardous Waste directive 91/689/EEC. As described in Article 6(c) of the Directive, only non-hazardous commercial and industrial waste would be acceptable at the site with the exception of stable, non-hazardous wastes that have for example been solidified or vitrified. I consider that a condition linking the range of waste coming to the site to the Landfill Directive's classification of waste would be appropriate and would be warranted on planning grounds as a means of calming public fear. The applicant has agreed that such a condition would be acceptable to them."
"In relation to commercial and industrial waste, the site shall be used for the landfill of only non-hazardous waste, except for stable, non-reactive hazardous wastes as described in article 6(c(iii) and Annexe II of the Landfill Directive 1999/31/EC."
"4.5.1 On completion of the initial earthworks, the engineering of the landfill void would be carried out for Cell 1. 4.5.2 The formation below the lining system would be graded to falls of approximately 1 in 50, to ensure positive drainage. The proposed lining system, comprising a minimum of 1.0m of mineral liner, with a maximum permeability of 1 x 10-9 m/s, or equivalent, would then be installed. The installation would be the subject of a rigorous Construction Quality Assurance programme. 4.5.3 The clay would be excavated from the area of Cell 3, above the cell formation levels. During the landfilling of Cell 1, Cell 2 would be constructed, taking further clay from the area of Cell 3. 4.5.4 The construction of Cell 3 would comprise completion of the formation levels. The quantity of clay above the formation levels would be sufficient to construct the clay liner within the cell. 4.5.5 Each cell would be constructed independently, and would be separated from adjacent cells by internal bunds constructed to a similar standard to the basal lining. 4.5.6 The liner would be overlain by a comprehensive leachate collection system, comprising 300 mm of free draining material, within which would be situated a network of slotted pipes to collect leachate. The leachate would be directed via this system to leachate collection points situated at the low point of each cell. 4.5.7 Upon completion of landfilling in each cell, the waste would be capped. The capping system would include a stabilisation layer, overlain by a mineral liner or equivalent geosynthetic material to minimise rainfall infiltration and leachate generation within the waste mass. 4.5.8 Typical details of the proposed engineering systems are indicated on Figure 11; Typical Construction Details."
"12.1.1 The landfilling of biodegradable wastes has the potential to cause environmental impact on the local water environment. The source of this potential impact is leachate produced through the percolation of rainwater through the waste mass. Leachate has the potential to pollute any adjacent water bodies it is able to reach. 12.1.2 In order to assess the potential impact, an examination of the geological, hydrogeological and hydrological conditions at the site has been undertaken."
"12.3.1 During the construction phase of the landfill, the principal potential impact would be the discharge of polluted surface water run-off to the local watercourses. 12.3.2 To mitigate the potential impact of polluted discharges, a system of perimeter cut-off ditches would be installed, to intercept polluted run-off and direct it to settlement facilities where suspended solids would be removed prior to discharge. 12.3.3 Such measures would be designed to ensure that surface water discharges complied with the requirements of a Consent to Discharge issued by the Environment Agency."
"12.4.1 The potential impacts associated with the operation of the landfill would include those identified during the construction phase, and in additional potential impacts from the uncontrolled discharge of leachate from the site. ... 12.4.9 The uncontrolled discharge of landfill leachate has the potential to pollute any adjacent water it is able to reach. Given the position of the site in relation to surface watercourses, and the groundwater table, it is predicted that potential impacts would be low to medium. 12.4.10 To minimise the potential for such impacts, the following mitigation measures would be implemented: • The installation of a full containment system, constructed within a rigorous Construction Quality Assurance regime, to prevent uncontrolled discharge of leachate. • The provision of a comprehensive leachate collection system. • Regular monitoring and removal of excess leachate 12.4.11 The design of the above measures would be finalised based upon the results of a quantitative Risk Assessment, in agreement with the Environment Agency. 12.4.12 With the implementation of the above measures, and good working practices, the operation of the site would be in accordance with Environment Agency policy, and the residual impact associated with the operation of the landfill would be low."
"The site will be operated as a containment site with a liner equivalent to or better than a clay composite liner as required by the IPPC Regulations and Landfill Directive. The appropriateness of the lining system and the site design will be assessed as part of the assessment of emissions to groundwater (Regulation 15 Risk Assessment) as part of the PPC Permit application. ... Leachate management systems at the site will result in the leachate levels being maintained at 1 m above the base of the site. This is approximately 1 m below the water levels within the made ground and consequently the site will be hydraulically contained with respect to the shallow groundwater."
"The remediation options currently available which are considered suitable for the site include the interception of potentially contaminated groundwater adjacent to the development area and/or capping the area to reduce the infiltration and the production of contaminated groundwater."
"In summary by developing the site, the reduction in infiltration will improve the quality of the Stockley Brook by decreasing the impact from contaminated groundwater on the stream from that observed today and will not limit the application of future remediation operations."
"Based on the conclusion that the contamination is disseminated throughout the colliery spoil the potential remediation options which could be implemented include the interception of groundwater and/or capping of the site to reduce the infiltration. By developing Smith's void as a landfill site, the groundwater quality would be improved by: • Reducing the infiltration to the made ground and therefore the volume of contaminated groundwater; • Decreasing the residence times of the groundwater within the made ground therefore potentially decreasing the contaminant loading. In addition, the development would not impeded the interception of groundwater, should it be required at a later date. The risks posed by the landfill development to the perched groundwater (and consequently surface water streams) and the groundwater in the Coal Measures will be assessed as part of the PPC application for the assessment of emissions to groundwater."
"Generally speaking the report satisfies the majority of the matters raised. The issues pertaining to managing existing contamination have been discussed but no final remediation strategy has been proposed. The other outstanding matters that have not been addressed in this submission will need to be resolved through the IPPC authorisation application process. The Agency has no objections, in principle, to the proposed development but recommends that if planning permission is granted the following planning conditions are imposed: CONDITION: No development approved by this permission shall be commenced until: a) The application site has been subjected to a detailed desk study and site investigation, and remediation objectives have been determined through risk assessment, and approved in writing by the Local Planning Authority. b) Detailed proposals for the removal, containment or otherwise rendering harmless any contamination (the 'Reclamation Method Statement') have been submitted to and approved in writing by the Local Planning Authority. REASON: To protect the environment and ensure that the remediated site is reclaimed to an appropriate standard. ... CONDITION: There shall be no discharge of foul or contaminated drainage from the site into either groundwater or surface waters, whether direct or via soakaways. REASON: To prevent pollution of the water environment. CONDITION: No soakaway shall be constructed in contaminated ground. REASON: To prevent pollution of groundwater. INFORMATION The waste disposal operations shall be subject to an IPPC permit under thePollution Prevention and Control Regulations 1999 ."
"I have received an 'Addendum Report' from the applicant dealing with ground water issues in response to a request from the Environment Agency. The Agency's observations upon it are referred to below. Additional ecological information to that contained in the Environmental Statement has also been supplied and, subject to conditions that could be required as part of a planning permission, the relevant statutory consultees are content with the development proposal. Further background noise assessment has also been submitted at the request of the District of Bolsover Environmental Health Officer. I am satisfied that, with the inclusion of the additional material referred to above, these issues have been thoroughly covered. My assessment of these issues is addressed with the Planning Considerations section of this report. The submission of additional information on these issues does not in any event detract from the adequacy of the Environmental Statement which I am satisfied meets relevant legal requirements. The claimant's solicitors had complained: "• The application does not deal adequately with ground water issues and this matter should be properly addressed as part of the planning process rather than being left to the Integrated Pollution Prevention Control Authorisation application. Comment: The Environment Agency has confirmed that its Hydrology Section has examined the planning application and the Addendum Report requested by the Agency and has reiterated that it has no objections in principle to landfilling at this location. The Agency indicates that further detailed work will be required through the IPPC process to ensure that the requirements of the relevant legislation can be met. A ground water risk assessment will be required as part of this process, to address ground water protection issues in greater detail. Planning Policy Guidance (PPG) Note 23 gives advice to planning authorities on whether or not concerns about potential releases can be left for the pollution control authority or, in the case of wider impact of potential releases, may appropriately be considered unacceptable on planning grounds. PPG 23 also advises that planning authorities should work on the assumption that pollution control regimes will be properly applied and enforced. In this case I am satisfied that it would be appropriate for this issue to be addressed within any IPPC Authorisation application that would have to follow a grant of planning permission. Of course, planning permission would not pre-empt the Agency's proper consideration of an IPPC Authorisation application. If matters could not be resolved to the Agency's satisfaction then Authorisation would not be granted and the development could not proceed."
"Chapter 12 of the Environmental Statement provides information relation to Geology, Hydrogeology and Hydrology. It identifies groundwater levels including those from 'perched' groundwater within the colliery spoil deposits at the site. It identifies the potential for impacts on local water resources. The proposed mitigation measures include a full containment system for the landfill cells. Apart from the ES itself, the 'Addendum Report' that the applicant subsequently submitted to the Council gives further technical details in relation to, amongst other things, hydrogeology, groundwaters and mitigation measures. This report was not produced at the Council's request, but was submitted following discussions between the applicant and the Environment Agency. The report made it quite clear that the leachate management system that was proposed would be designed to maintain leachate levels within the site below the groundwater levels in the colliery spoil. The proposals included a free draining groundwater drain and the hydraulic containment of the landfill by means of an impermeable liner system The Council is always particularly mindful of the responses made by the Environment Agency (EA), which is a statutory consultee, on such matters. The Agency, after careful consideration of the geological and hydrogeological details, raised no objections to the application in principle and recommended a number of conditions to be included if planning permission was granted. The EA letter in response to this application confirmed that other outstanding matters which it had discussed with the application would be resolved through its Pollution Prevention and Control (PPC) authorisation application process. These matters would include a 'groundwater risk assessment'. Your reporting officers understand this to be a reference to an assessment that would be carried out under the PPC process in order to ensure that the final detailed technical specifications for the liner system of the landfill cells would be adequate to fully contain the leachate as proposed in the planning application. There is a specific allegation within this ground of the challenge that the ES did not provide any estimate of emissions to soil and water including, in particular, of leachate to groundwater, nor of the likely effect of the landfill on soil or groundwater of such emissions. The ES did identify potential impacts of the proposed landfill on groundwaters. Measures are included in the proposals in order to ensure that any negative impacts are prevented from happening. Your officers have no reason to doubt that this will be achieved through the detailed PPC process referred to above. The ES's estimate of the emissions to groundwater and soils is that there would not be any because the landfill cells would be fully contained. The ES also identified potential benefits in reducing the impact on groundwaters of the site compared to that which would be expected to continue into the future if the site were to be left in its existing undeveloped state. The proposals include the continued monitoring of groundwater quality which is considered to be a sensible precautionary approach. In our opinion the ES should not be regarded as deficient."
"Regulation 19 of theTown and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 1999 requires a planning authority, if it considers that a submitted Environmental Statement should contain additional information in order to be an Environmental Statement, to so notify the applicant in writing ... These circumstances did not apply in this case, the Council never has taken such a view on the ES and the submission of the Addendum Report was not in response to a notification by the Council. The Council nevertheless considered the contents of the Addendum Report once it was received, and duly forwarded it to consultees for their comments and it was placed on the planning register."
"No part of the development shall be commenced until: (a) The application site has been subject to a detailed desk study and site investigation, and remediation objectives have been determined through risk assessment, and approved in writing by the Waste Planning Authority. (b) Detailed proposals for the removal, containment or otherwise rendering harmless of any contamination (the 'Reclamation Method Statement') have been submitted to and approved in writing by the Waste Planning Authority."
"There shall be no discharge of foul or contaminated drainage from the site into either ground water or surface waters, whether direct or via soakaways."
"Third, the planning authority or the Inspector will have failed to comply with article 4(2) if they attempt to leave over questions which relate to the significance of the impact on the environment, and the effectiveness of any mitigation. This is so because the scheme of the regulations giving effect to the Directive is to allow the public to have an opportunity to debate the environmental issues, and because it is for those considering whether consent to the development should be given to consider the impact and mitigation after that opportunity has been given... Fourth, (and here it seems to me one reaches the most difficult area) it is certainly possible consistent with the above principles to leave the final details of for example a landscaping scheme to be clarified either in the context of a reserved matter where outline planning consent has been granted, or by virtue of a condition where full planning consent is being given as in the instant case."
"In my view it is a further important principle that when consideration is being given to the impact on the environment in the context of a planning decision, it is permissible for the decision-maker to contemplate the likely decisions that others will take in relation to details where those others have the interests of the environment as one of their objectives. The decision-maker is not however entitled to leave the assessment of likely impact to a future occasion simply because he contemplates that the future decision-maker will act competently. Constraints must be placed on the Planning Permission within which future details can be worked out, and the decision-maker must form a view about the likely details and their impact on the environment."
"The Secretary of State has to make a practical judgment as to whether the project would be likely to have significant effects on the environment by virtue of factors such as its nature, size or location. The extent to which remedial measures are required to avoid significant effects on the environment, and the nature and complexity of such measures, will vary enormously but the Secretary of State is not as a matter of law required to ignore proposals for remedial measures included in the proposals before him when making his screening decision. In some cases the remedial measures will be modest in scope, or so plainly and easily achievable, that the Secretary of State can properly hold that the development project would not be likely to have significant effects on the environment even though, in the absence of the proposed remedial measures, it would be likely to have such effects. His decision is not in my judgment pre-determined either by the complexity of the project or by whether remedial measures are controversial though, in making the decision, the complexity of the project and of the proposed remedial measures may be important factors for consideration."
"40. In my judgment the Secretary of State erred in the test he has expressed in paragraph 19 of his final decision letter. I read the second part of paragraph 19 as including an assumption that Condition VI provides a complete answer to the question whether significant effects on the environment are likely. That is too narrow an approach. In the circumstances, it was necessary to consider the stage which the site investigation had reached (Condition VI requires a further site investigation in detail to be undertaken), the nature and extent of the scheme for remediation, including its uncertainties, the effects on the environment during the remediation and the likely final result. The condition is properly drafted but itself demonstrates the contingencies and uncertainties involved in the development proposal, as does the evidence of Mr Simmons already quoted. 41. When making the screening decision, these contingencies must be considered and it cannot be assumed that at each stage a favourable and satisfactory result will be achieved. There will be cases in which the uncertainties are such that, on the material available, a decision that a project is unlikely to have significant effects on the environment could not properly be reached. I am not concluding that the present case is necessarily one of these but only that the test applied was not the correct one. The error was in the assumption that the investigations and works contemplated in Condition VI could be treated, at the time of the screening decision, as having had a successful outcome."
"Where the Secretary of State is contemplating an application for planning permission for development which, but for remedial measures, may or will have significant environmental effects, I do not say that he must inevitably cause an EIA to be conducted. Prospective remedial measures may have been put before him whose nature, availability and effectiveness are already plainly established and plainly uncontroversial; though I should have thought there is little likelihood of such a state of affairs in relation to a development of any complexity. But if prospective remedial measures are not plainly established and not plainly uncontroversial, then as it seems to me the case calls for an EIA."
"Except as may otherwise be required by conditions of this permission, the development shall be implemented in accordance with the submitted details and accompanying Environmental Statement dated8 February 2001 as amended by letters dated18 June 2001 ,17 July 2001 and29 August 2001 with enclosures and Addendum Report, provided that nothing otherwise required or prohibited by this condition shall prevent the making of any alterations to any detailed technical specifications and operations of waste management processes that the Environment Agency might require in accordance with theLandfill Regulations 2002 ."
"Waste Strategy 2000, which is the current national waste strategy sets out the changes considered necessary to deliver more sustainable waste management. It sets a series of challenging targets to increase the value that is recovered from municipal waste and to reduce the amount of biodegradable municipal waste that is sent to landfill. Waste Strategy 2000 expects planning decisions on suitable sites for treatment and disposal to be based on a local assessment of the 'Best Practicable Environmental Option' (BPEO) for each waste stream. However, the courts have held that, whilst BPEO is material to land use planning, it is for local planning authorities to decide how much weight to attach to it. The BPEO process was defined in the 12th Report of the Royal Commission on Environmental Pollution as: "
"The document advises that Waste Planning Authorities should consider the provision of waste management facilities within the context of the following ... the best practicable environmental option for each waste stream including consideration of the 'Waste Hierarchy' and 'Proximity Principle'."
"... reflects national policies. In particular Chapter 10: Waste Management Policies, acknowledges the strategic principles set out in Waste Strategy 2000 and confirms that its policies accord with the framework established in national, regional and local waste strategies. The principle policies that are relevant to consideration of this application are as follows: Waste Management Policy 1: Waste Management Sites and Facilities states: Provision will be made for sufficient sites and facilities to cater for the waste management needs of Derbyshire, having regard to the national, regional and local strategies for waste management. Particular account will be taken of: 1) The need to pursue objectives which further the aim of achieving sustainable waste management, such as to find the Best Practicable Environmental Option for individual waste streams."
"The Strategy recognises that movement up the waste hierarchy will take time to achieve and, secondly, despite being at the bottom of the waste hierarchy, indicates that landfill will continue to be the best environmental option for some waste types. This is particularly likely to be so for municipal waste."
"The need for the development is two-fold; to deliver the comprehensive reclamation of the current despoiled site and to facilitate the disposal of wastes arising in the area."
"3.2.11 The proposed development of a landfill site at Smiths Void is intended to address at least part of this shortfall and to provide continuity of waste disposal capacity at the locality. The proposed waste void has a capacity of approximately 850,000 m3, which represents 4 to 5 years life at an input rate of approximately 200,000 tonnes per annum. The capacity generated would be available during the plan period. 3.2.12 The development of the landfill would also enable Derbyshire Waste Ltd to fulfil its obligations under the long term contract with Derbyshire County Council in the surrounding area, ensuring that MSW [Municipal Solid Waste] arising continues to be disposed of locally, thus complying with the 'proximity principle'."
"Work that I am currently undertaking in connection with the production of a waste local plan, does not assume an increase in waste due to economic growth contrary to the DWMS. My calculations suggest that there may be a sufficiency of landfill within the county as a whole up to 2010 provided that there is no growth in waste and the Government's recovery targets are achieved. However, further work and refinement of figures is ongoing and as yet there is no published information. At that stage the methodology would be open to public scrutiny. ... ... given my preparatory local plan work and having regard to the degree of uncertainty on this issue, I can only conclude that the case in relation to need is, in my view, not proven although seems not to be in conflict with Waste Management Policy 1."
"Glapwell 2 has, until its recent closure, taken waste including a large proportion of municipal solid waste, from Chesterfield, North-East Derbyshire and the Bolsover area. The applicant indicates that municipal waste from this area is currently deposited at the Hall Lane, Steveley landfill site and at Sutton Landfill in Nottinghamshire. As an extension of an existing disposal facility, this site would make an effective, albeit small, contribution to the facilities available. Notwithstanding the Sub-Area supply position, I am satisfied that the proposal is not large enough that it would transform the local supply situation and, of itself, create substantial excess capacity. Whilst the application site is particularly accessible from the north-east of the County, the site also has good connections to the M1 Motorway and A38 trunk route to serve the wider needs of Derbyshire and I am mindful of the imminent shortage of landfill space in the south-east of the county. Thus, I consider that landfilling at this site would be in accordance with the key considerations - Proximity Principle and Regional Self-sufficiency and technically suitable for landfilling as proposed thereby providing a Best Practicable Environmental Option for the disposal of waste in accordance with criteria 1 of this policy."
"The case for additional landfill space within the County for the period specified in the Derbyshire Waste Management Strategy to 2011 is not proven although I am satisfied that the proposal is not of a sufficient size that it would transform the local supply situation and, of itself, create substantial excess capacity. Further, preparatory waste local plan works suggests that a shortage of landfill space in the county as a whole will arise by 2010 and in the south-east of Derbyshire, a shortage is imminent. This site could help meet that shortage. Notwithstanding the availability of alternative sites both currently, and which may become available in the north-east of the County within the Waste Management Plan period referred to this report, I consider that there are compelling reasons to accept the infilling/land raising/restoration of the site as submitted to restore the site satisfactorily and conserve and enhance its ecology thereby providing a significant benefit. I consider that there is no realistic likelihood of an appropriate restoration being achieved without the importation of waste in the manner proposed."
"The Director of Environmental Services written report referred to there being no shortage of landfill space within the County as a whole to 2010, provided that reduced waste production and landfill targets were achieved. If waste arisings increased due to economic growth as forecast by the applicant then a shortfall of landfill space would arise. There was some uncertainty on this issue but he was satisfied that the proposal was not large enough that it would transform the local supply situation and create substantial excess capacity. He was mindful that preparatory waste local plan work showed that a shortfall of landfill space was about to arise in the south east of the County and given its good accessibility, this site could assist in meeting the waste disposal needs of that area. The officer also reported verbally that ongoing work in connection with the production of the waste local plan for Derby and Derbyshire now indicated that there was likely to be sufficient landfill space both in the North East Derbyshire Sub-Area and the plan area as a whole up to the end of the current Structure Plan period in 2011, but that an overall shortage was currently predicted to develop in the subsequent period up to 2015 (the year to which that plan would run). In his report the Director of Environmental Services considered that there were compelling reasons to accept the infilling/landraising/restoration of the site as submitted, to restore the site satisfactorily and conserve and enhance its ecology thereby providing a significant benefit. He considered that there was no realistic likelihood of an appropriate restoration being achieved without the importation of waste in the manner proposed. ... Members of the Committee commented on the proposal, and asked for clarification from officers on a number of issues raised, to which officers responded. Members, having considered the report and heard the comments made and explanations provided by officers, generally considered that there were not any substantial planning grounds for refusal of the application. It was felt that the site was in need of improvement but that it would be unlikely to regenerate in a satisfactory manner on its own. An officer explained that satisfactory restoration without use of waste was a technical possibility but was not feasible except at great expense and that no such alternative scheme was likely to be being promoted."
"Lack of a Compliant Best Practicable Environmental Option (BPEO) Assessment The report to Committee of 11 March explained the concept of BPEO (ie the option that provides the most benefits or the least damage to the environment as a whole, at acceptable cost, in the long term as well as the short term), and analysed it in the context of this proposal. The challenge essentially alleges that the Council's treatment of BPEO, as referred to in the Government's published Waste Strategy 2000, was insufficient. In particular, the level of detail that should be taken into account in determining a planning application, including the lack of identification of the specific BPEO for particular waste streams. The Courts have held that in appropriate cases BPEO is an objective to which planning authorities should have regard as a material consideration. It is for local planning authorities to decide how much weight to attach to it. In this case the waste hierarchy and the proximity principle were considered and reference was made to the relevant Planning Policy Guidance, Waste Strategy 2000, Regional Planning Guidance and the Derbyshire Waste Management Strategy. The ES made reference to the applicant's own waste management strategy and proposed recycling rates. In particular, the report identified the waste hierarchy, the proximity principle and self sufficiency as considerations. It addressed the issues of the targets for reducing, re-using and recovering value from waste and the requirements for landfill capacity for the residual wastes. In the context of Structure Plan policies it identified the use of waste as a positive resource to reclaim this site. Although extensive reference has been made under this ground of challenge to Chapter 3 in Part 2 of Waste Strategy 2000 ('the decision making framework'), this Part of the Strategy appears to be concerned with waste management decisions by local authorities in general rather than with waste planning authority decision-making on particular planning applications. Your reporting officers remain of the view that the relevant factors relating to the planning application in terms of BPEO were properly taken into account."
"(b) implementing so far as material any plan made under the plan making provisions."
"'plan making provisions' means paragraph 5 below, section 50 of the 1990 Act ...Part II of the Town and Country Planning Act 1990 ... andsection 44A of the Environmental Protection Act 1990 ..."
"(1) The Secretary of State shall as soon as possible prepare a statement ('the strategy') containing his policies in relation to the recovery and disposal of waste in England and Wales. (2) The strategy shall consist of or include - (a) a statement which relates to the whole of England and Wales; or. (b) two or more statements which between them relate to the whole of England and Wales. (3) The Secretary of State may from time to time modify the strategy. (4) Without prejudice to the generality of what may be included in the strategy, the strategy must include - (a) a statement of the Secretary of State's policies for attaining the objectives specified in Schedule 2A to this Act ..."
"Decisions on waste management, including decisions on suitable sites and installations for treatment and disposal, should be based on a local assessment of the Best Practicable Environmental Option."
"The right way to treat particular waste streams cannot be determined simply. The objective is to choose the Best Practicable Environmental Option, (BPEO) in each case. BPEO varies from product to product, from area to area and from time to time. It requires waste managers to take decisions which minimise damage to the environment as a whole, at acceptable cost in both the long and short term. A more detailed description of how decision makers can identify the BPEO is at Chapter 3 section starting 3.3 in Part 2 of this strategy."
"Waste Planning Authorities are responsible for identifying suitable sites for waste treatment or disposal installations. The Government and the National Assembly look to Waste Planning Authorities to: • take full account of the policies described in this strategy, in particular: • the importance of establishing the BPEO ..."
"Furthermore, this waste strategy is an advisory document. The 1990 Town and Country Planning Act requires local planning authorities in England and Wales to have regard to national policies in drawing up their development plans, and therefore this document will be an important source of guidance. These development plans will then provide a framework for individual planning decisions ..."
"When taking waste management decisions on suitable treatment options, sites and installations, local authorities must follow the framework set out below. This framework should act as a guide for other decision makers, including business waste managers."
"The process that should be used for considering the relative merits of various waste management options in a particular situation is the Best Practicable Environmental Option (BPEO). This was defined in the 12th Royal Commission on Environmental Pollution as ..."
"Identifying the most sustainable mix of waste management options, environmentally, economically and socially, can be a daunting task. However, the process can be simplified by breaking it down into smaller, more manageable tasks: Step 1: set the overall goals for making the waste management decision, subsidiary objectives and the criteria against which the performance of different options will be measured Step 2: identify all the viable options. Step 3: assess the performance of these options against the criteria. Step 4: value performance. Step 5: balance the different objectives or criteria against one another. Step 6: evaluate the rank the different options. Step 7: analyse how sensitive the results are to variations in the assumptions made or the data used."
"Under the Town and Country Planning legislation, planning authorities must have regard to national and regional policies, including policies on waste management, in drawing up their waste development plans. This waste strategy will be a material consideration for planning authorities in drawing up their development plans and for determining individual planning applications."
"Whereas, because of the particular features of the landfill method of waste disposal, it is necessary to introduce a specific permit procedure for all classes of landfill in accordance with the general licensing requirements already set down in Directive 75/442/EEC and the general requirements of Directive 96/61/EC ..."
"Member states shall take measures in order that: (a) the competent authority does not issue a landfill permit unless it is satisfied that ... (b) the landfill project is in line with the relevant waste management plan or plans referred to in Article 7 of Directive 75/442/EEC."
"Decisions on waste management, including decisions on suitable sites ... for disposal should be based on a local assessment of the BPEO"; "
"there was no realistic likelihood of an appropriate restoration being achieved without the importation of waste in the manner proposed"