“6. As I will explain in this statement the conduct of the Claimants in instructing an expert in breach of the Protocol (as happened in both claims) is in fact common practice in the industry, it results in Defendants being entirely excluded from the instruction of experts and renders the Protocol meaningless. For reasons I will detail below the effect of this practice is to ‘tie the hands’ of Defendant landlords and leave them little option but to settle a claim they don’t accept and pay the tenant’s legal costs which are often disproportionate to the underlying claim, or alternatively to obtain their own report and then fight the claim at significant cost and risk.….. 10… it is vanishingly rare for there to be either no expert or a single joint expert appointed save in those cases where we have sought the intervention of the court in an application such as the ones we have made in these two claims. In my view that is because of the steps almost all claimant solicitors take in the very early stages of each claim. In effect what they do is demand that a Defendant agrees with their choice of expert right at the outset in the letter of claim and if not the Defendant only has the option to have no expert at that stage or to appoint their own. There is a complete failure to properly engage with the question of what is actually in dispute, or what expert evidence is required to properly resolve such issues and it is extremely rare to see a Claimant give the Defendant a proper opportunity to be part of the agreement of, and instruction of the expert…”
‘Our client considers there to be potential issues to the roof. These issues may be aggravating the issues present within the roof.’
“It was unclear as to what exactly was referred to as the roof being defective as included in the letter of claim. The external roof covering was intact with no loose or missing tiles at all, and upon inspection of the loft space the insulation was found to be dry and there was no indication of any roof leaks at all with the roofing under felt intact and no holes or rips present.”
“Experts We do not consider that an expert is required in this case. Our client’s qualified surveyor has attended the property, confirmed the required works and steps will now be taken to carry out the goodwill works. We consider the next step in this matter is for you to consider this response, take your client’s instructions and return to us in order to narrow the issues and assess the extent of any dispute. Our client should also be allowed to carry out the work they have scheduled. If after proper consideration the parties consider an expert should be instructed then we can discuss the instruction of a single joint expert in accordance with the Protocol andCPR Part 35 .”
“We suspect these items have been included purely to increase costs, given that the value of the work without these superfluous items would be less than£1,000 The relevance of this assertionmay well be that where a claim for specific performance of a covenant to repair is alleged to cost more than£1,000 the Civil Procedure Rules suggest that the case should normally be allocated to the Fast Track (where costs are recoverable) rather than the small claims track (where costs are not generally recoverable). The unstated inference that it seeks to draw is that the cost of repair is not genuine, but tactically inflated. . Conclusion Mr. Hedges report has failed to identify any necessary works which were had (sic) not already been raised by our client. It was entirely unnecessary to obtain his report, which would have been obvious if you had taken the time to review and respond to the works raised by our client. His report has served only to increase costs and delay the claim. It is clear there is no claim here, and we look forward to receiving confirmation that the claim has been withdrawn”
“Please note we will be instructing the expert via TLB Services and, upon acknowledgement of the above, we will provide a copy of our proposed expert(s) for your consideration. Please note we will provide you with a copy of the CV and any proposed appointment dates in further correspondence. Please advise within 20 working days if you agree to this appointment and that you agree to pay 50% of fees if a single joint instruction can be agreed. If you object please advise us of your reasons within 20 working days. If you do not object to the expert being instructed as a single expert but wish to provide you own instructions you should send those directly to our expert within 20 working days of this letter. Please also provide a copy of the letter of instructions to us. If you wish to instruct a single expert, we will instruct an independent expert to inspect the property in any event and, as stated above, a copy of the CV will be provided in advance. If you wish for your expert to attend at the same time to carry out a joint inspection, please advise at your earliest opportunity to avoid any unnecessary delays. Please ensure all arrangements in respect of our client’s property are communicated through us during the time for which we are instructed in order to avoid any unnecessary delays in arranging inspections and subsequent works that may be required.”
“For the avoidance of doubt, it is the Claimant’s case that the Housing Conditions Protocol was engaged because, despite the Defendant’s knowledge of the disrepair, the matter remained unresolved due to the Defendant’s refusal and/or neglect to carry out works of repair and/or to carry out works of repair in a good and proper manner using good and proper materials, following notification of disrepair. Thereafter litigation became necessary after service of the Protocol letter of claim to promote the speedy and appropriate carrying out of repairs which are the Defendant’s responsibility and to ensure the Claimant receives appropriate compensation.”
“52. In response to the allegations….. that the Claimant’s intention was to instruct Mr. Smit come what may. This allegation is refuted on the basis that whilst Mr. Smit was the only available independent expert in the area, the expert was only nominated, and no formal instructions were provided. This is common practice in order to arrange a date in the diary outside of any protocol time limits. 53. In the event the Claimant disagreed with the Defendant’s in-house report then at that point instructions were provided to the Claimant’s solicitor to proceed with the instruction of Mr. Smit. The period between11 April 2024 and28 May 2024 , the date in which the appointment was due to take place provided sufficient time for the Claimant to allow access to the Defendant’s surveyor, proceed with an inspection and review the report albeit this was disclosed one month after the inspection, the Claimant’s solicitor still had time to review and take instructions on the same.”
“94. In these two claims, it is submitted that no expert was in fact necessary. The [Claimants’ expert] reports both largely identify work which the Defendant had already identified. That being the case, the onus ought to be on the Claimant to articulate whether there are any ongoing concerns about the property (confined of course to the issues which have been pleaded) before consideration is given to the need for expert evidence. It is impossible to tell from the pleaded claims (which do not acknowledge the work or explain what the Claimants’ cases is in light of it) whether there is a claim for specific performance or not.”
“27….. It was accepted he was instructed without a formal reply to the Defendant’s letter of response and schedule. He was not the surveyor named by the Claimants in their letter of claim. 28. I find he had been instructed notwithstanding significant outstanding issues and proposals raised by the defendant in their letter of response. Outstanding issue included requiring a response as to the need for an expert report, if one were required whether it should await the works the Defendant was proposing to undertake, comments on the categorisation of works proposed, an agreement as to a suitable expert acceptable to both parties and a response to the surveyor nominated by the defendant.”
‘[53]…..wholesale disregard by the claimants’ solicitors in both cases to [sic] the pre-action protocol applicable for housing disrepair cases in Wales. The solicitors proceeded to unilaterally instruct an expert notwithstanding unanswered objections raised by the defendant. I would emphasise it is not for either party to unilaterally seek to impose a particular surveyor on the other as a single joint expert. Relevant matters include the split of their work between claimant and defendant instructions, the cost and time scale in the preparation of the report, and that they have the requisite knowledge of the law applicable to Wales. 54. In cases where the defendant has responded to the letter of claim by providing its assessment of the property following an inspection by its suitably qualified employee it is incumbent on the claimant as noted in the pre-action protocol to set out reasons why it is believed necessary for there to be a single joint expert. It is even more incumbent on the claimant to accept whether it accepts or disputes the schedule of repair proposed prior to the appointment of such an expert. ….. 55. The aim of the protocol is to ensure that any items of disrepair are identified and where there is an obligation on the landlord to repair, those repairs are carried out swiftly. If the landlord confirms the items of disrepair and provides a schedule indicating the repair works to be undertaken the necessity of an expert’s report can only be properly assessed after the works are completed. If there is an issue which is fundamental to the case for example the Landlord in response to a letter of claim refuses to accept the responsibility for an alleged defect, which is said is their responsibility, it is probable an expert’s report will be required. However it is the claimant’s responsibility to explain to the Defendant the reason why such a report is required and in any event the engagement of an expert applying the pre-action protocol, the overriding objective and the provisions ofCPR 35 should be on a single joint basis unless there are cogent reasons. Those reasons would need to be explained in detail in advance of any instruction of an expert by one party only. One reason could be the extreme nature of the defects. That is not the position [here]. 56. The court expects parties to co-operate as to identifying suitable single joint experts. Each party for example providing the names, terms of engagement and CVs of three suitable experts is a commonly used means of resolving the issue. 57. Where the need for expert evidence is satisfied in housing disrepair cases it would be the exception given the relative low value of the cases for it to be proportionate to separately instructed (sic) experts. The pre-action protocol envisages where expert evidence is necessary it is to be provided by single joint expert.’
“Time limits 9 (a) The time scales given in the Protocol are long stops and every attempt should be made to comply with the Protocol as soon as possible. If parties are able to comply earlier than the time scales provided, they should do so. (b) Time limits in the Protocol may be changed by agreement. However, it should always be borne in mind that the court will expect an explanation as to why the Protocol has not been followed or has been varied and breaches of the Protocol may lead to costs or other orders being made by the court.”
“Taking stock 8 Where the procedure set out in this Protocol has not resolved the dispute between the landlord and the tenant, they should undertake a review of their respective positions to see if proceedings can be avoided and, at the least, to narrow the issues between them.”