“We will take responsibility for having the work done to put right the physical damage to the homes, if the cost to us is above the excess. Alternatively, if we choose to, we will pay you what it will cost us to have the work done, less the excess amount applicable.”
“[A] Option 1 – Insolvency cover before practical completion [B] When this section applies This section applies if you lose the amount paid to the contractor in accordance with the building contract or have to pay more to complete the building of the home(s), because the contractor is insolvent or commits fraud. [C] When you can claim You can only claim under this section up to the date of the Buildmark Choice certificate. Contact us and tell us if you have lost the amount you paid to the contractor or the contractor has not completed the home(s). [D] What we will do We will pay you the reasonable extra cost above the contract price including professional fees, for work necessary to complete the home(s) to the NHBC requirements; or We will reimburse the amount paid to the contractor in accordance with the building contract which cannot be recovered from them. [D1] In addition, we will pay the cost of reasonable precautions to secure the work defined in the building contract against unauthorised entry, theft and vandalism until work resumes. [E] Conditions and limitations This option will only apply if included on the quotation and the additional premium has been paid to and accepted by us. There are limits to how much we will pay (as explained on pages 14 & 15) Some things are not NHBC's responsibility under Buildmark Choice (as explained on page 16).” [B] When this section applies [C] When you can claim [D] What we will do [E] Conditions and limitations Some things are not NHBC's responsibility under Buildmark Choice (as explained on page 16).”
“The Contractor: a) has died b) is declared bankrupt or in Scotland sequestrated c) is in liquidation d) has had an administrator appointed e) has an administrative receiver or a receiver manager appointed over any or all of their property, assets or undertakings; or f) is subject to any other insolvency procedure by whatever means or has a judicial factor appointed to its undertakings.”
“So the additional costs on the insured units is approximately£1,358,000 , more than the max 10% claim. However this is based on build cost only and we also have a lot of additional fees, abortive works costs, legal costs, payments to Vantage post administration etc.”
“In the course of my review of the matter, it became evident to me that Catalyst’s claim had become statute-barred on29 June 2022 pursuant tosection 5 of the Limitation Act 1980 , by virtue of more than six years having passed since Vantage went into administration on29 June 2016 .”
“20…Mr London put forward three alternative ways, in principle, of ascertaining the point in time when Peabody "had to pay" extra costs. The first would be to conduct a deductive exercise from the dates of final accounts (the earliest of which is July 2017); Peabody alleges that this has always been NHBC's position, that it could not finalise what it had to pay until final accounts were prepared. The second would be to analyse cumulative costs over time as the work progressed. The third would be to instruct an independent expert quantity surveyor to retrospectively analyse the letting of the individual works contracts packages, and individual interim applications for payment, and compare the outputs of those analyses with a hypothetical analysis where Vantage did not enter insolvency. 21. Mr London's essential point is that, at the time of insolvency, only some£1.5m had been paid to Vantage, and that there was approximately£8.8m left in the tank, as it were, before the Contract Price for the units (c.£10.3m ) would be exceeded. And that it is at the least realistically arguable that, depending on what approach is taken, the moment of "having to pay more" did not arise before March 2020, alternatively June 2020, alternatively certainly not prior to July 2017 (being six years prior to the Claim Form).”
“57. In my judgment, Option 1 cover does not apply (i.e. is not triggered) if the insured did not "have to pay more to complete" the units, or if the insured did not lose any money paid to the contractor, despite the contractor going insolvent. The event insured against is not the insolvency (or fraud of the contractor) per se, but rather the insured being required to pay more above the contract price to complete. The requirement to pay more must have been caused by the insolvency (or fraud) of the contractor, but the insolvency (or fraud) itself is not the risk which is covered. Peabody is correct therefore in its submission that the insured losses (the extra costs, or lost payments) are an essential and definitional part of the insuring clause itself [B], and not matters which simply go to the delineation of quantum [D]. It would have been easy enough to draft [B] to make clear that the claim arose on insolvency itself, regardless of whether any extra expense (or lost payment) was caused by it, if that had been intended.”
“It seems to me that the best way to define an indemnity insurance is that it is an agreement by the insurer to confer on the insured a contractual right which, prima facie, comes into existence immediately when loss is suffered by the happening of an event insured against, to be put by the insurer into the same position in which the insured would have been had the event not occurred, but in no better position.”
“66. As to whether the [D1] claim is time-barred, on the basis that the costs were incurred more than six years before the Claim Form, the Court is faced with the difficulty that, no doubt because this point did not appear as part of the Application or the evidence, Peabody did not address it either in its evidence or its skeleton argument. There is limited evidence about the costs in question. For example, the letter of18 January 2018 relied upon by NHBC stated that the costs were incurred to secure the site and to remove squatters. But the detail of the costs was set out in Section E of the claim document, which is not in evidence.”
“It seems to me that the best way to define an indemnity insurance is that it is an agreement by the insurer to confer on the insured a contractual right which, prima facie, comes into existence immediately when loss is suffered by the happening of an event insured against, to be put by the insurer into the same position in which the insured would have been had the event not occurred, but in no better position.”
“There is a consistent line of authority for the proposition that the date on which the assured’s action accrues is the date on which the insured peril occurs and not on the later dates when the loss is manifested, the assured incurs expenditure or the insurers deny liability, the principle being that the insurer has agreed to hold the assured harmless against the occurrence of an insured event so that when the event takes place the insurers are in immediate and automatic breach of contract and are liable for unliquidated damages.”
“The core principle is that an insurance policy, like any other contract, must be interpreted objectively by asking what a reasonable person, with all the background knowledge which would reasonably have been available to the parties when they entered into the contract, would have understood the language of the contract to mean. Evidence about what the parties subjectively intended or understood the contract to mean is not relevant to the court’s task … In the case of an insurance policy of the present kind, sold principally to SMEs, the person to whom the document should be taken to be addressed is not a pedantic lawyer who will subject the entire policy wording to a minute textual analysis (cf Jumbo King Ltd v Faithful Properties Ltd(1999) 2 HKCFAR 279 , para 59). It is an ordinary policyholder who, on entering into the contract, is taken to have read through the policy conscientiously in order to understand what cover they were getting.”
“This section applies if there is physical damage to the home(s) because the contractor failed to build the following parts of the home(s) to comply with the NHBC requirements [they are then set out]”
“You cannot claim for something under this section if you can claim for it under … Option 1, or if you could have done when you first knew about it.”
“First, the reliance placed in some cases on commercial common sense and surrounding circumstances … should not be invoked to undervalue the importance of the language of the provision which is to be construed. The exercise of interpreting a provision involves identifying what the parties meant through the eyes of a reasonable reader, and, save perhaps in a very unusual case, that meaning is most obviously to be gleaned from the language of the provision. Unlike commercial common sense and the surrounding circumstances, the parties have control over the language they use in a contract. And, again save perhaps in a very unusual case, the parties must have been specifically focussing on the issue covered by the provision when agreeing the wording of that provision.”
“Fourthly, while commercial common sense is a very important factor to take into account when interpreting a contract, a court should be very slow to reject the natural meaning of a provision as correct simply because it appears to be a very imprudent term for one of the parties to have agreed, even ignoring the benefit of wisdom of hindsight. The purpose of interpretation is to identify what the parties have agreed, not what the court thinks that they should have agreed. Experience shows that it is by no means unknown for people to enter into arrangements which are ill-advised, even ignoring the benefit of wisdom of hindsight, and it is not the function of a court when interpreting an agreement to relieve a party from the consequences of his imprudence or poor advice. Accordingly, when interpreting a contract a judge should avoid re-writing it in an attempt to assist an unwise party or to penalise an astute party.”