“(5) In the light of the conclusions of the assessment, and subject to regulation 64, the competent authority may agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the European site … .”
“(1) If the competent authority is satisfied that, there being no alternative solutions, the plan or project must be carried out for imperative reasons of overriding public interest [“IROPI”] … it may agree to the plan or project notwithstanding a negative assessment of the implications for the European site … .”
“5.11.286 … In the ExA’s view, the Applicant’s stance … does not address the need to fully consider the cumulative assessment of the environmental effects of the proposed water supply solution that is fundamental to the operation of the Proposed Development. 5.11.287 The ExA agrees with NE, that it is unable to undertake a meaningful assessment of potential effects arising from the chosen solution for operational supply in combination with the Proposed Development from the evidence presented to the Examination. Accordingly, the ExA considers it has not been provided with sufficient information or certainty on the issue of permanent water supply.”
“5.11.292 In these circumstances we have to consider the possibility that a sustainable water supply may not be able to be identified. That being the case it is clear from what the ONR have set out there remains a possibility that the Proposed Development may not be able to operate.” and (in paragraphs 5.11.294 and 5.11.295): “5.11.294 No cumulative effects assessment has been provided in respect of the other potential solutions outlined by the Applicant and NWL. The Applicant’s position is that any water supply would be delivered under a separate statutory regime and as such any environmental assessment required would be undertaken as part of that process. The concerns expressed by NE about the implications for the HRA are discussed in more detail in Chapter 6 of this report. The ExA accepts the position reached by NE that the water supply is a fundamental component of the operational Proposed Development. 5.11.295 Taking into account that the Applicant has not identified a permanent water supply solution at the close of the Examination, we are not able to recommend that the DCO should be granted without greater clarity about a sustainable water supply solution and any consequential environmental effects.”
“7.5.7 … For the reasons we have explained in section 5.11 of Chapter 5 of this Report, the ExA prefers the position of NE to that of the Applicant on this matter. We consider that even if the Proposed Development and the water supply are considered to be two separate projects, the cumulative effects associated with it should be assessed at this stage. 7.5.8 … [For] the reasons we have explained, we consider that greater clarity is required at this stage in relation to the provision of a permanent sustainable water supply solution and the consequential cumulative environmental effects. Therefore, we are unable to recommend that this application be approved without additional information and reassurance on the provision of a permanent water supply. The ExA regards this as an important matter of such magnitude that it should not be left unresolved to a future date.”
“7.6.3 In view of the uncertainty around the permanent water supply solution, the ExA cannot preclude the potential identification of LSE on European sites and qualifying features during construction and operation of the Proposed Development, either alone (if considering the solution such as the preferred pipeline/transfer main as part of the project) or in combination with solutions such as the preferred pipeline/transfer main.”
“10.2.19 … With the exception of the permanent sustainable water supply issue, the ExA finds that the potential benefits of the Proposed Development including the contribution that the Proposed Development would make to satisfying the urgent need for low-carbon electricity generating infrastructure of this type would strongly outweigh the potential adverse impacts. However, the ExA concludes in relation to the water supply strategy that in the light of the issues which remained unresolved at the close of the Examination, we cannot recommend that the application as it stands should be granted development consent.”
“3.3 The Applicant should confirm if it would be possible for the proposed temporary desalination plant to permanently meet the full water supply demand for the lifetime of the proposed Development should no alternative water supply solution be identified. The response should include any further information that will assist the Secretary of State in understanding the water supply strategy for the lifetime of the proposed Development. 3.4 The information provided should be sufficiently detailed to enable the Secretary of State to understand and reach a reasoned conclusion on the cumulative environmental effects, including for Habitats Regulations purposes, of the different permanent water supply solutions.”
“2.1.8 NWL is obliged to plan for and supply the water required for the long-term operation of [the nuclear power station] and [NWL has provided] helpful confirmation that the necessary process is in place. In particular, the supply requirements for Sizewell C are included within the demand forecast on which NWL’s [WRMP24] will be based.”
“2.1.15 This background should provide more than sufficient comfort both for [Sizewell], but also for the Secretary of State, that NWLwill be in accordance with the statutory scheme plan to deliver the required infrastructure (so far as it is possible) to provide a long-term supply to [the nuclear power station]. 2.1.16 It is because the long-term planning of water supply is the subject of separate statutory provisions and processes that the identification of the source of Sizewell’s long-term supply cannot be known at this stage. Indeed, the source may well change during the lifetime of the power station as the undertaker develops and manages its water resources in response to changing demand and other considerations. For the same reasons, and because on the evidence the source of supply is unlikely to be a constraint to the construction and operation of the new power station, the source does not need to be known for the purposes of the DCO.”
“2.1.20 If it were to become apparent that there was any risk of NWL being unable to provide the supply, there are a range of actions open to [Sizewell C Ltd.]. … 2.2.1 There is no “in principle” difficulty with the supply of water from desalination being made permanent. … 2.2.3 In the unlikely event that [NWL] is unable to meet Sizewell C’s water supply demand, it would be possible for [Sizewell C Ltd.] to permanently meet the full water supply demand for the lifetime of the proposed Development using a desalination plant.”
“4.44… in addition to demand management options, NWL is appraising other options that include (but are not limited to): an import from Anglian Water; nitrate removal at Barsham [Water Treatment Works]; effluent reuse and desalination; and longer term (post-2035) winter storage reservoirs. The Secretary of State considers that these represent potentially viable solutions for the water supply strategy as would the fall back of the Applicant’s own permanent desalination plant if those solutions cannot be used. The Secretary of State is therefore content that if consent is granted for the development, there is a reasonable level of certainty that a permanent water supply solution can be found before the first reactor is commissioned.”
“4.49 The Secretary of State considers that the Proposed Development and the WRMP24 process for the sourcing of water are separate projects. This is evident from their separate ownership and because they are subject to distinct and asynchronous determination processes. The Secretary of State also considers that these projects are stand-alone, given that NWL has a duty to undertake its WRMP24 regardless of whether or not the Proposed Development proceeds.”
“4.50 The Secretary of State has considered the ExA’s view [ER 7.5.7] that, even if the Proposed Development and the water supply are considered to be two separate projects, the cumulative effects associated with it should be assessed at this stage. As set out below, the Secretary of State has considered the cumulative assessment of the proposed pipeline from the North/Central WRZ and agrees with the Applicant’s assessment that the pipeline is not likely to give rise to new or significant effects to those already identified in the ES. In addition, the Secretary of State agrees with the Applicant that the detail of the potential environmental impacts (including cumulative impacts) associated with the proposed permanent water supply to be provided by NWL will be sufficiently assessed and that the WRMP24 process is the appropriate means of undertaking that assessment. The Secretary of State agrees that further detailed assessment cannot be undertaken by the Applicant at this stage as the preferred option for long-term supply is not yet known given the current status of the separate WRMP24 process, which falls to be considered as a separate plan or project. The Secretary of State considers that it is because the long-term planning of water supply is subject to separate statutory provisions and processes … the identification of the source of the Proposed Development’s long-term water supply cannot be known by the Applicant at this stage.”
“4.52 The Secretary of State is satisfied that, based on current knowledge, there are no additional cumulative impacts if the Barsham pipeline were to be pursued. The Secretary of State has considered the information provided by the Applicant on cumulative effects and does not agree with the ExA’s criticisms and considers that there is sufficient information on which he can base his conclusion.”
“4.55 … While noting that the ultimate source of supply has yet to be identified by NWL, the Secretary of State considers that the information provided demonstrates sufficiently, in principle, the viability of a mains connection pipeline to the Proposed Development if some or all of the supply were able to come from that location. 4.56 The Secretary of State is satisfied that if NWL, through the regulatory processes associated with the WRMP24, put forwards a solution to the supply of potable water supply (sic) which requires a change to the pipeline connection to the Proposed Development (once it has established where it will source the water for the Proposed Development from) any such solution will be subject to its own environmental assessments, including those under the [Habitats Regulations Assessment]. 4.57 The Secretary of State notes that any such pipeline or connection will be applied for separately to the proposed development once there is certainty around its route and specification. 4.58 … [The] Secretary of State does not have detailed information as to the route or specification of the pipeline that would convey water to the Proposed Development given that it is subject to the outcome of the WRMP24 process which has not yet been completed. However, the Secretary of State considers that he has sufficient information for the purposes of taking a decision on the Proposed Development to conclude that there is the potential for a viable connection to be provided in principle. The Secretary of State considers that if the pipeline connects to a supply at Barsham it is not likely to give rise to significant environmental effects additional to those already identified in the Environmental Statement, but this will also fall to be re-examined and be subject to assessment once any such pipeline connection is finalised. If a different solution is required, then any such different solution will need to be the subject of its own assessment in due course. 4.59 The Secretary of State notes that … it is not possible for the Applicant to provide more specific details regarding the route or specification of the pipeline, or other connection, that will provide the Proposed Development with a connection to the water main or water supply at this stage, and notes that such a pipeline or alternative connection does not form part of the Application. This is due to the fact that the specific details of the route remain unknown until NWL identifies the source of the water that the pipeline will connect the Proposed Development to. The Secretary of State considers that such a pipeline or alternative connection cannot be subject to more detailed assessment as part of this Application given it is subject to WRMP24 … . The Secretary of State agrees that in light of the present state of knowledge, it is not possible for the Applicant to conduct any meaningful assessment of any different solution to emerge from the WRMP24 process but that any such different solution will necessarily be subject to its own assessment before it can proceed. 4.60 … [A] decision-maker should work on the assumption that relevant environmental regulatory regimes, including the abstraction licencing regime regulating activities that take water from the water environment, will be properly applied and enforced by the relevant regulator, and that a decision-maker should not seek to duplicate these regimes… The Secretary of State notes… that it is not always possible for all aspects of a proposal to be settled in precise detail. The fact that there is a lack of detailed information available regarding the source of a permanent water supply via NWL means that it is not possible for the Applicant to have assessed the effect, including the cumulative effects of all of the potential means of conveying water to the Proposed Development. The [water resources management plan] process is conducted by the water company and is not something that the Applicant can dictate. If (and only if) the [water resources management plan] process fails to provide a solution, the Applicant will have to consider its own permanent desalination plant.”
“4.61 The Secretary of State notes the concerns raised by IPs regarding the prospect of a permanent desalination plant. The Secretary of State agrees with the Applicant that further detailed assessment of the impacts associated with a permanent desalination plant would be required if the Applicant were ultimately to pursue this option as part of its water supply strategy which is not the current intention. The Secretary of State has not requested further detailed assessment from the Applicant of this option given that it does not form part of the Proposed Development and the Applicant’s position is that a bespoke permanent desalination plant for the Proposed Development is unlikely to be required. The Secretary of State notes the Applicant’s position that a permanent desalination plant is not likely to generate any materially new or materially different significant environmental effects on the marine environment … and on the terrestrial environment … . The Secretary of State has also considered the concerns raised by IPs regarding the fact that the Applicant had previously discounted desalination from its water supply options. The Secretary of State notes that the revision 1.0 of the Applicant’s Water Supply Strategy produced in May 2020 noted that benefits of desalination include potentially short lead times with equipment available for hire, and that it could be useful for temporary top-ups or in times of drought. The limitations of desalination were listed as ‘desalinated water being aggressive in pipe network and may require remineralisation’. 4.62 The Secretary of State acknowledges … that the Applicant’s conclusion in January 2021, in Appendix 2.2.D Water Supply Strategy of the ES Addendum Volume 3 Chapter 2, was to discount the installation of a modular desalination plant on the MDS and the abstraction of seawater for treatment and notes that the Applicant also stated in the same document that Essex and Suffolk Water had ‘identified means to provide a viable supply of potable water to Sizewell C’ with this option referred to as ‘transfer of surplus potable water via a new pipeline from Barsham’. This reflected the Applicant’s position that a new mains pipeline is preferable to a permanent desalination plant.”
“4.63 … The Secretary of State considers that if, contrary to expectation, the Applicant were to seek to provide water from a permanent desalination plant, that would require its own consent and would be subject to further detailed assessment at that stage before it could proceed. Accordingly, for essentially the same reasons as identified above in respect of the other potential solutions to the supply water strategy (sic), the Secretary of State does not consider it necessary for the effects of any such solution to be assessed in more detail as a permanent desalination plant does not form part of the Proposed Development and the Applicant is not relying on it as an integral part of the Proposed Development.”
“4.65 In relation to the Habitats Regulations, the Secretary of State does not agree with Natural England that the source of any permanent water supply is, in itself, integral to the application. There will need to be a permanent water supply solution and the Secretary of State is satisfied that such a solution can be found before the first reactor is commissioned. However, the Secretary of State does not consider that the source of that supply is an integral part of this application. There is no current certainty as to the final source of the permanent water supply, which does not need to be in place until the early 2030s. The Applicant has carried out a cumulative assessment of the potential pipeline route from Barsham/the North/Central WRZ which identifies that this will result in no new or different significant cumulative effects. However, it is not currently known whether this or some other means of connecting the development to the water supply network will be required and this is something that will only become known through the [Water Industry National Environment Programme] process. The Secretary of State agrees with the position of the Applicant that an assessment of the Habitats Regulations implications of the proposed permanent water supply solution will be undertaken by NWL. The Secretary of State does not agree with NE that any such assessment is likely to miss or underplay any effects of any kind, including any cumulative or in-combination effects. 4.66 In the unlikely event that NWL can find no solution, then the Applicant has confirmed that it would seek to take forward its own solution of the construction of a permanent desalination plant. As already noted, this in itself would require a further application, either to amend the DCO or for another form of planning consent and such an application would similarly trigger the requirement for the necessary environmental assessments including any required under the Habitats Regulations. Such assessment would consider the proposed permanent water supply solution in combination with the Proposed Development and address any cumulative effects.”
“4.67 … The Secretary of State is… satisfied that a long-term water supply is viable and that any proposed water supply solution to be supplied by NWL will be properly assessed under the WRMP24 process and/or other relevant regulatory regimes and considers that no further information is required regarding the proposed water supply solution for a decision to be taken on the Application. 4.68 The Secretary of State therefore disagrees with the ExA’s conclusions on this matter and considers that the uncertainty over the permanent water supply strategy is not a barrier to granting consent to the Proposed Development. 4.69 The Secretary of State considers that the matter of the water supply does not weigh for or against the Order being made, and attributes this matter neutral weight in the overall planning balance.”