“those permissions, consents, approvals, licences, certificates and permits as may be necessary to carry out and complete the Works, including without limitation any approval of reserved matters in respect of the planning permission granted for the Development, Building Regulation consent and bye-law approvals and the requirements of all competent authorities regarding the Development.”
“any directly applicable provisions of the EU Treaty or any EU Regulation, any statute, statutory instrument, regulation, rule or order made under any statute or directive having the force of law which affects the Works or performance of any obligations under this Contract and any approvals, requirements, codes of practice, regulation or bye-law of any local authority, competent authority or statutory undertaker which has any jurisdiction with regard to the Works or with whose systems the Works are, or are to be, connected.”
“The Contractor shall carry out and complete the Works in a proper and workmanlike manner and in compliance with the Contract Documents, the Construction Phase Plan and other Statutory Requirements, and shall give all notices required by the Statutory Requirements … .”
“The Contractor warrants that the Works when completed shall comply with the Requisite Consents and Statutory Requirements.”
“On the Date of Possession possession of the site or, in the case of a Section, possession of the relevant part of the site shall be given to the Contractor who shall thereupon begin the construction of the Works or Section and regularly and diligently proceed with and complete the same on or before the relevant Completion Date … .”
“… the Contractor shall not be liable under this Contract if the Works (other than the CDP Works) do not comply with the Statutory Requirements to the extent that the non-compliance results from the Contractor having carried out work in accordance with the documents referred to in clauses 2.15.1 to 2.15.4 [“Notice of discrepancies etc.”] (other than an instruction for a Variation in respect of the Contractor’s Designed Portion).”
“If, in the Architect/Contract Administrator’s opinion, on receiving a notice and particulars under clause 2.27 [“Notice by Contractor of delay to progress”]; .1 any of the events which are stated to be a cause of delay is a Relevant Event; and .2 completion of the Works or of any Section is likely to delayed thereby beyond the relevant Completion Date, then … the Architect/Contract Administrator shall give an extension of time by fixing such later date as the Completion Date for the Works or Section as he then estimates to be fair and reasonable.”
“The following are the Relevant Events referred to in clauses 2.27 and 2.28: .1 Variations and any other matters or instructions which under these Conditions are to be treated as, or as requiring, a Variation; … .6 any impediment, prevention or default, whether by act or omission, by the Employer, the Architect/Contractor Administrator, the Quantity Surveyor or any of the Employer’s Persons, except to the extent caused or contributed to by any default, whether by act or omission, of the Contractor or of any of the Contractor’s Persons; … .13 force majeure.”
“During the Pre-Construction Period: … .1 any of the events which are stated to be a cause of delay is a Relevant Event; and .2 completion of the Works or of any Section is likely to delayed thereby beyond the relevant Completion Date, then … the Architect/Contract Administrator shall give an extension of time by fixing such later date as the Completion Date for the Works or Section as he then estimates to be fair and reasonable.” .1 Variations and any other matters or instructions which under these Conditions are to be treated as, or as requiring, a Variation; … .6 any impediment, prevention or default, whether by act or omission, by the Employer, the Architect/Contractor Administrator, the Quantity Surveyor or any of the Employer’s Persons, except to the extent caused or contributed to by any default, whether by act or omission, of the Contractor or of any of the Contractor’s Persons; … .13 force majeure.” … 3. … The Contractor will remain wholly responsible for the carrying out and completing of the Pre-Construction Services.”
“The Contractor in submitting the Contractor’s Proposals for the Contractor’s Designed Portion … thereby confirms that it is satisfied that: … .4 any of the Works designed by the Contractor will fully comply with the Statutory Requirements and in accordance with the Employer’s Requirements and this Contract.”
“The Contractor shall assume responsibility for the Employer’s Requirements in all respects pursuant to the terms and Conditions of this Contract.”
“If in the execution of this Contract the Contractor incurs or is likely to incur direct loss and/or expense for which he would not be reimbursed by a payment under any other provision in these Conditions … because the regular progress of the Works or any part of them has been or is likely to be materially affected by any of the Relevant Matters, the Contractor may make an application to the Architect/Contract Administrator. … .”
“The following are the Relevant Matters: .1 Variations (excluding those where loss and/or expense is included in the Confirmed Acceptance of a Variation Quotation but including any other matters or instructions which under these Conditions are to be treated as, or as requiring, a Variation); … .6 any impediment, prevention or default, whether by act or omission, by the Employer, the Architect/Contractor Administrator, the Quantity Surveyor or any of the Employer’s Persons, except to the extent caused or contributed to by any default, whether by act or omission, of the Contractor or of any of the Contractor’s Persons.” .1 Variations (excluding those where loss and/or expense is included in the Confirmed Acceptance of a Variation Quotation but including any other matters or instructions which under these Conditions are to be treated as, or as requiring, a Variation); … .6 any impediment, prevention or default, whether by act or omission, by the Employer, the Architect/Contractor Administrator, the Quantity Surveyor or any of the Employer’s Persons, except to the extent caused or contributed to by any default, whether by act or omission, of the Contractor or of any of the Contractor’s Persons.”
“The term ‘Variation’ means: .1 the alteration or modification of the design, quality or quantity of the Works including: .1 the addition, omission or substitution of any work; .2 the alteration of the kind or standard of any of the materials or goods to be used in the Works; .3 the removal from the site of any work executed or Site Materials other than work, materials or goods which are not in accordance with this Contract; … .” .1 the alteration or modification of the design, quality or quantity of the Works including: .1 the addition, omission or substitution of any work; .2 the alteration of the kind or standard of any of the materials or goods to be used in the Works; .3 the removal from the site of any work executed or Site Materials other than work, materials or goods which are not in accordance with this Contract; … .”
“This is the list of items of services that are intended to be dealt with during the pre-commencement period. 1. Obtain consent relating to the planning condition in respect to highway and construction management. 2. Obtain consent relating to other relevant planning conditions that require discharging prior to commencement of works in respect to SUDS, Rainwater Harvesting and pool backwash system. … .”
“… 2. No fee allowance has been made for any Planning, Party Wall Agreements or Council Rates. 3. Working hours will be … as stipulated in the Planning Consents… 4. PTP will submit the necessary applications to discharge planning conditions, negotiate and manage the process. Walter Lilly will provide necessary documentation and information relating to any CDP works to satisfy the planning conditions in connection with the SUDS, rainwater harvesting and pool back wash system. … .”
“… 2. In accordance with the terms of the Contract, the Date of Possession in the Contract shall be deemed to be19 February 2013 and the commencement date for the Works shall be deemed to be18 March 2013 . The Date for Completion for the Works shall be deemed to be9 November 2014 .”
“1. Subject to the terms of the Judgment as a whole the preliminary issues are answered as follows: … ii. Issue 1.2: No iii. Issue 2: This depends on whether or not the relevant conservation area consent had been obtained. If it had, the answer is No. If it had not been obtained, the answer is Yes. … vi. Issue 4: No, as explained at paragraph 65-69 of the Judgment and the amplification handed down on5 May 2016 . vii. Issues 5.1.1, 5.1.2, … and 6.1: No, as explained at paragraphs 51-64 of the Judgment. The obligation to be implied is the one set out at paragraph 58 of the Judgment. … .” 2. For the avoidance of doubt and by way of clarification of the judgment dated24 February 2016 : 2.1. The words “unreasonable”, “unreasonably” and “capriciously” in paragraph 61 of the Judgment and “capricious” in paragraph 67 of the Judgment refer to conduct that is unreasonable in the Wednesbury sense (see Associated Provincial Picture Houses Ltd v Wednesbury Corporation[1948] 1 KB 223 and the line of cases that have followed it); 2.2 The references in paragraph 61 and 67 to the loss or risk lying where it falls, mean that in the event of delay caused by the unreasonable conduct of the local authority, neither party is to have any claim against the other in respect of such delay. Thus, for example, the Claimant cannot recover from the Defendant any loss and expense occasioned by such delay and the Defendant, likewise, cannot recover damages (whether liquidated or otherwise) from the Claimant in respect of such delay. This does not mean the Claimant is entitled to an extension of time, even if in some circumstances the result is the same.” … ii. Issue 1.2: No iii. Issue 2: This depends on whether or not the relevant conservation area consent had been obtained. If it had, the answer is No. If it had not been obtained, the answer is Yes. … vi. Issue 4: No, as explained at paragraph 65-69 of the Judgment and the amplification handed down on5 May 2016 . vii. Issues 5.1.1, 5.1.2, … and 6.1: No, as explained at paragraphs 51-64 of the Judgment. The obligation to be implied is the one set out at paragraph 58 of the Judgment. … .” 2.1. The words “unreasonable”, “unreasonably” and “capriciously” in paragraph 61 of the Judgment and “capricious” in paragraph 67 of the Judgment refer to conduct that is unreasonable in the Wednesbury sense (see Associated Provincial Picture Houses Ltd v Wednesbury Corporation[1948] 1 KB 223 and the line of cases that have followed it); 2.2 The references in paragraph 61 and 67 to the loss or risk lying where it falls, mean that in the event of delay caused by the unreasonable conduct of the local authority, neither party is to have any claim against the other in respect of such delay. Thus, for example, the Claimant cannot recover from the Defendant any loss and expense occasioned by such delay and the Defendant, likewise, cannot recover damages (whether liquidated or otherwise) from the Claimant in respect of such delay. This does not mean the Claimant is entitled to an extension of time, even if in some circumstances the result is the same.”
“The Employer will use all due diligence to obtain in respect of the Works any permission, consent, approval or certificateas is required under, or in accordance with, the provisions of any statute or statutory instrument for the time being in force pertaining to town and country planning.”
“The obligation for the obtaining of planning permission and other relevant planning approvals under the contract lies with Mr Clin as “Employer” under the implied term as to planning permission. The consequent allocation of risk is addressed in the relevant express terms of the contract.”
“No. See the answer to preliminary issue 4.”
“There are cases where the loss should be shared, and there are cases where it should be wholly borne by the employer. There are also cases which do not fall within either of these conditions which are the fault of the contractor, where the loss of both parties is wholly borne by the contractor. But in the cases where the fault is not that of the contractor the scheme clearly is that in certain cases the loss is to be shared: the loss lies where it falls. But in other cases the employer has to compensate the contractor in respect of the delay, and that category, where the employer has to compensate the contractor, should, one would think, clearly be composed of cases where there is fault upon the employer or fault for which the employer can be said to bear some responsibility.”
“… I write further to my officer’s visit to the above mentioned properties on3rd July 2013 regarding demolition work undertaken. Whilst the extent of demolition at this time was not substantial demolition and a breach of [thePlanning (Listed Buildings and Conservation Areas) Act 1990 ] had not occurred, my officer was shown plans from the on site engineer that indicated the following demolition works:- • rear elevation of both 48 and 50 to be demolished below the cill of the first floor windows, • the whole of the internal envelope of both buildings from third to lower ground level to be demolished • the removal of the roof from each property • the removal of the ground and lower ground front bay of 48 Palace Gardens Terrace You are advised that the extent of demolition proposed above is considered substantial demolition requiring Conservation Area Consent from the Council. I confirm that such an application has not been sought or obtained. I must also advise you that carrying out unauthorised substantial demolition works to a building in a conservation area is an offence underSection 9 of the Planning (Listed Buildings & Conservation Areas) Act 1990 . Any person found guilty of such an offence is liable [to] a fine of up to£20,000 upon conviction in the Magistrates’ Court [and an unlimited fine if convicted by the Crown Court]. Continued non-compliance can result in further prosecutions for a similar offence, incurring similar fines. The Council may also issue a conservation area consent enforcement notice, which is served on all parties having a material interest in the property. It is entered on the Local Land Charges records which could make the future sale or financing of the property more difficult. If it is your intention to proceed with the above demolition works, I would wish to receive an appropriate application within 28 days of the date on this letter. You will need to demonstrate why the above demolition works are structurally necessary and what temporary works you are proposing to secure the stability of the buildings. I would also wish to receive written confirmation of your intentions, within 21 days of the date on this letter. If you fail to do so, and the works proceed without the necessary consent, I will consider initiating formal prosecution proceedings in this matter. If you do not understand what you are being asked to do, please contact the case officer whose name is at the top of this letter. Even if you do so, the above deadlines and requirements must still be met. I confirm that I have also written to the architects, PTP Architects London Ltd in this matter. …”
“The council’s letter was not a “Requisite Consent” as defined in clause 1.1 of the contract. Whether it constituted a “Statutory Requirement” will depend on the full factual context established by the evidence.”
“Walter Lilly’s obligation or entitlement under clauses 2.1.1 and 2.3.7 of the contract will depend on the court’s conclusion, in the light of the evidence, as to whether every permission, consent, approval or certificate lawfully required under the statutory scheme for town and country planning had been granted at the material time.”