“Grounds for summary judgment The court may give summary judgment against a claimant or defendant on the whole of a claim or on a particular issue if- (a) it considers that- (i) that claimant has no real prospect of succeeding on the claim or issue; or (ii) that defendant has no real prospect of successfully defending the claim or issue; and (b) there is no other compelling reason why the case or issue should be disposed of at a trial.” (a) it considers that- (i) that claimant has no real prospect of succeeding on the claim or issue; or (ii) that defendant has no real prospect of successfully defending the claim or issue; and (b) there is no other compelling reason why the case or issue should be disposed of at a trial.”
“I now enclose the two sets of contract documents relating to Phase 1 for your checking and signing. These should then be returned to this office for forwarding to the Employer. The contract documents will then be used as a basis for Phase 3 with that works being a variation to the contract based on the agreed sum for Phase 3.”
“The quotations and final detailed design for the mechanical and electrical subcontracts are still being finalised and I expect to have them shortly.”
“Phase 3 generally will comprise the following: … • The mechanical subcontract installation, comprising the supply and installation of a wet underfloor heating system over the Lewis plates; the installation of 2 no. Rayburn logburning stoves (supplied by others) and a two-way logburning stove with heat exchanged, all with insulated stainless steel flues; ... • The design and installation for the mechanical systems will be carried out by Affleck Mechanical Services Limited.” • The mechanical subcontract installation, comprising the supply and installation of a wet underfloor heating system over the Lewis plates; the installation of 2 no. Rayburn logburning stoves (supplied by others) and a two-way logburning stove with heat exchanged, all with insulated stainless steel flues; • The design and installation for the mechanical systems will be carried out by Affleck Mechanical Services Limited.”
“Heating 10.05 Complete the design and install all pipework and equipment associated with the ground floor underfloor heating and the radiators and towel rails to the upper floors. … 10.06 Attend at the same time as Pioneer as required to permit installation of the flues, serving the Rayburns and wood burner, through the roof for flashing with copper.”
“Further to our meeting this morning, I confirm the following; 1. Your tender issued on 28th June included a programme with a completion date of6th April 2012 . You tabled at the meeting today a revised draft programme with a completion date of15th February 2012 . 2. This programme will need to be adjusted with firm dates, after Pioneer have given information relating to the completion of their work including that of Mastercraft. 3. Consideration will be given to splitting Phase 3 into 2 parts (say Phases 3a and 3b), with a separation point arrived at by the removal of the scaffolding and the sleeping accommodation, and consequently the barge being taken off hire. Phase 3 may continue after the removal of the accommodation to complete works started (i.e. possibly the stone floors). 4. You are instructed to carry out the works relating to Phase 3a, this to include an immediate instruction to place an order with Affleck Mechanical to carry out the work in accordance with the specification as included in your tender submitted by email on28th June 2011 . 5. It is intended that Phase 3b will either continue without interruption or may be deferred until the spring of 2012. Edward Iliffe would want to reserve the right to review any future instruction regarding Phase 3b, which therefore cannot at this stage be fully guaranteed.”
“Certificate of Progress Payment issued under the JCT Intermediate Building Contract with Contractor’s Design 2005”
“After discussing the project with our installer he had some concerns about the proximity of the flues to the timbers in certain places. The regulations state there should be a minimum of 50mm from the outside of the flue to combustible materials. Our bracketry ensures that the 50mm is maintained however where the flue runs between joists or beams it may be that there will need to be some modification of the timbers to comply with the regulations. Also once the flue has been installed any subsequent boxing in would need to take this into account. This will need to be pointed out to Feltham as any modifications or cutting back of timbers would be their responsibility.”
“7.3 All the remaining causes relate to the chimney and there is nothing inherently unlikely in a roof fire being caused by a chimney. Building Regulation J3 notes: “Combustion appliances and fluepipes shall be so installed, and fireplaces and chimneys shall be so constructed and installed, as to reduce to a reasonable level the risk of people suffering from burns or the building catching fire in consequence of their use.”