“i) MTH says that what should be omitted is the component of the original Contract Price included for the provision of the LISA (making due allowance for the fact that she carried out 2 of the 62 foundations); but ii) E.ON contends that the deduction should be the product of applying a rate (or alternatively a cost) to the amount of time it alleges that the LISA would have taken to carry out the contract works if it had in fact done so. 5 E.ON says that, because the LISA had proved inadequate, MTH would have taken a very long time to install all the foundations using her. Consequently, applying either a rate or a cost to the time that MTH would have taken if it had completed the contract using the LISA has the result that the sums for which E.ON contends as appropriate deductions are greatly in excess of the sums for which MTH contends. MTH submits that the appropriate deduction (net of additions referable to working with the Resolution) is just shy of€12,900,000 , whereas E.ON submits that it is either just under€57,250,000 (its primary case) or just under€34,650,000 (its secondary case).”
“Part L of the Contract was entitled "Schedule of Prices, Payment Profile & Draft Programme": a) Schedule L1.1 was a segregation (or breakdown) of the Contract Price of€ 101,454,052 . It showed, at a high level, what sums were attributed to specified elements of the Works. In particular: i) Manufacture of the foundations totalled just over€60 million Made up of€23.964 million for manufacture of the monopiles and€36.043 million for the transition pieces which together made up the foundation. ; ii) Transportation of the foundations totalled just under€3.6 million ; iii) Installation of the foundations totalled€22.1 million ; iv) The Wait on Weather Allowance Meaning payment for those days on which sea conditions rendered impossible the safe execution of parts of the Works. was€3.58 million . b) Schedule L1.2 provided prices for alternatives and extras; c) Schedule L1.3 (which was expressly referred to in Clause 31.3) provided a Schedule of Rates "which will be used for the evaluation of Variation Orders". The rates for the provision of manpower were to be fully inclusive of all costs and charges including site and establishment overheads. Materials, plant and sub-contract work mark-ups were stated generally to be on a cost-plus basis but certain categories of plant (including the day rate for foundation installation vessel spread) were separately specified; d) The draft programme provided for the LISA and its vessel spread to be mobilised to site by16 June 2007 and included a period of 142.2 days thereafter for the installation of the foundations. Of this: i) 127.2 days related to the installation of the 60 WTG foundations; and ii) 15 days related to the installation of the met mast (which was subsequently omitted) and the two substation foundations. iii) Part E of the Contract provided (at E1.8) that the 142 day foundation installation programme comprised 104 days of installation and 38 days of anticipated Waiting on Weather.” ii) Transportation of the foundations totalled just under€3.6 million ; i) 127.2 days related to the installation of the 60 WTG foundations; and ii) 15 days related to the installation of the met mast (which was subsequently omitted) and the two substation foundations. iii) Part E of the Contract provided (at E1.8) that the 142 day foundation installation programme comprised 104 days of installation and 38 days of anticipated Waiting on Weather.”
“The Employer has secured the services of the MPI Resolution…. This Variation Order formalises the Employer making available the MPI Resolution, and certain project equipment and services, to the Contractor for use to install to install (sic) foundations at the Robin Rigg site, in order to mitigate delays to the Works. The agreed deployment of the MPI Resolution partly replaces some of the working time for vessel LISA A from the scope of the Agreement. … Contractual arrangements shall be as follows: • E.ON contracts directly with MPI for the vessel operational with the personnel and equipment detailed as Employer or MPI responsibility in [an attached document]. … • MTH provide supervision on Resolution … • MTH manage/coordinate the overall foundation installation operation by LISA, Resolution and any other vessels.” • E.ON contracts directly with MPI for the vessel operational with the personnel and equipment detailed as Employer or MPI responsibility in [an attached document]. … • MTH provide supervision on Resolution … • MTH manage/coordinate the overall foundation installation operation by LISA, Resolution and any other vessels.”
“The Employer has secured the services of the MPI Resolution. This Variation Order formalises the agreed provision by the Employer of the MPI Resolution, and certain project equipment and services, to the Contractor for use to install wind turbine generator foundations at the Robin Rigg site, in order to mitigate delays to the Works. The agreed deployment of the MPI Resolution reduces the work that will be undertaken by the vessel LISA A. … Contractual arrangements shall be as follows: • MTH retain overall contractual responsibility for design, supply, transportation, storage, handling, and installation of foundations in accordance with the Agreement. … • E.ON contracts direct with MPI for the vessel operational with the personnel and equipment detailed as Employer or MPI responsibility [in an attached document] … • MTH manage/coordinate the overall foundation installation operation by LISA, Resolution and any other vessels” • MTH retain overall contractual responsibility for design, supply, transportation, storage, handling, and installation of foundations in accordance with the Agreement. … • E.ON contracts direct with MPI for the vessel operational with the personnel and equipment detailed as Employer or MPI responsibility [in an attached document] … • MTH manage/coordinate the overall foundation installation operation by LISA, Resolution and any other vessels”
“31.3 DISAGREEMENT ON ADJUSTMENT OF THE CONTRACT PRICE If the Contractor and the Employer are unable to agree on the adjustment of the Contract Price, the adjustment shall be determined in accordance with the rates specified in Part L, Schedule L1.3 Schedule of Rates. If the rates contained in the Schedule of Rates (Schedule L1.3) are not directly applicable to the specific work in question, suitable rates shall be established by the Engineer reflecting the level of pricing in the Schedule of Rates (Schedule L1.3). Where rates are not contained in the said Schedule, the amount shall be such as is in all the circumstances reasonable. Due account shall be taken of any over- or under-recovery of overheads by the Contractor in consequence of the Variation.”
“In valuing VOs 5, 9 and 10, the varied work should properly be characterised as a Variation (by omission and/or addition) of part of the Works, within the meaning of the first sentence of Clause 31.1.of the Contract”
“E.ON seeks to meet this objection by basing its calculations on MTH's projections of time the LISA would have taken per foundation and extrapolating it forwards. However, as the factual summary set out above shows, MTH's estimates of time that it would take were constantly shifting, and there is no reason to suppose that the estimate of 3.83 days per foundation given on22 June 2008 was more reliable than the estimate of 3.97 days per foundation given on22 May 2008 , or vice versa. To the contrary, on11 July 2008 the Claimant noted that the average cycle time for the LISA was likely to increase to in excess of six days. When asked why E.ON had not based its calculations on that estimate, the only reply given was that perhaps E.ON had been too generous, which is neither compelling nor convincing.”