“a direction of the Secretary of State shall determine for the purpose of these Regulations whether a development is or is not EIA development.”
“No significant cumulative effects are likely given the type and scale of the proposed development.” 44…It is not possible, in my view, to suggest that the Dreamland project or its effects were ignored at that stage… 47… At the Inquiry… the appellant had a full opportunity to deploy every argument and give evidence in relation to the cumulative effects to make good her argument that an assessment was required… 49 [The] conclusion [in the Inspector’s Report] as to traffic is of some significance … because it shows that whilst it was taken into account, the conclusion was there was no combined effect of the two projects; rather, the effect on traffic in the area would be the consequence of the Dreamland development and not of a combination of Arlington and Dreamland. 50 Similarly… there was consideration of sewage discharge and ample evidence of complaint and concern by those who lived in the area leading, no doubt, to [a condition] being imposed. 52 It seems to me….impossible to say that the Inspector failed when considering the screening direction to take into account the Dreamland project. On the contrary, it was taken into account but when considered cumulatively with Arlington, it did not lead to the view that significant environmental effects were likely. Lord Justice Moses set out passages from paragraphs 298 – 300 of the Inspector’s Report which concluded with an expression of agreement with the earlier screening decision. He added (at paragraph 53) “The Secretary of State came to the same conclusion.”
“Vehicular access to the Dreamland site is currently via junctions on Belgrave Road. The main pedestrian access is via Marine Terrace. Vehicular access to the proposed Arlington development would be via a new road which has the ability to link into the Dreamland site”
“no significant cumulative effects are likely given the type and scale of the proposed development”. 15. Lord Justice Moses concluded that, in the light of this material, it is “not possible to suggest that the Dreamland project or its effects were ignored” at the stage of the screening decision (Judgment, paragraph 44). I respectfully agree. The extract from the analysis and checklist which I have set out shows that cumulative impact was considered. Indeed, it would be highly surprising if it had not been as it was an allegation of a failure to consider it which had featured prominently in the pre-action protocol which prompted this reconsideration of the screening decision. (2) The Inspector’s Report 16. All this can be said with similar force in relation to the Inspector’s Report. At an early stage in his Report (paragraph 6) the Inspector listed fourteen matters which the Appellant “considers render the [screening decision] defective”
“At the Inquiry….the Appellant had a full opportunity to deploy every argument and give evidence in relation to the cumulative effects to make good her argument that an [EIA] was required”
“On the contrary, it was taken into account but when considered cumulatively with Arlington, it did not lead to the view that significant environmental effects were likely.” (Paragraph 52) On one level, this analysis has force. I do not think that the Inspector failed to consider the cumulative effects of the Arlington and Dreamland projects as he perceived them. However, it may then be necessary to identify the methodology which underlay the perception. I find this task easier to carry out when analysing the Secretary of State’s decision letter dated13 June 2013 . (3) The decision of the Secretary of State dated13 June 2013 19. The essential part of the decision of the Secretary of State was expressed as follows (at paragraph 24) : “The Secretary of State notes that the Inspector relied on the [screening direction] of18 July 2012 and has not seen any reason to question [it] … The appeal proposals are not part of a wider project that takes in the Dreamland site and furthermore there is no need for a cumulative assessment with the Dreamland scheme, given its status and the uncertainty that surrounds the…. Compulsory Purchase Order which is the subject of a legal challenge. Taking into account the written submission and evidence presented to the inquiry, including that concerning the matters to which Louise Oldfield draws attention, the Secretary of State does not consider that these lead him to question his ‘screening directions’… and he is content that an [EIA] is not required before the determination of this appeal.” (Emphasis added)
“The wording might have suggested that but it plainly does not mean it since, as the last sentence and the reference to the appellant’s submissions make clear the Secretary of State was well aware that the effects of both projects were considered cumulatively in reaching the decision that no EIA was needed.” 22. He then referred again to his interpretation that the Inspector and Secretary of State had judged that “the significant environmental effects were likely to be the free-standing consequences of the Dreamland project and not of both projects considered cumulatively”. 23. On any view, paragraph 24 of the Secretary of State’s decision letter is not a masterpiece of drafting. The statement that the Arlington proposal is “not part of a wider project that takes in the Dreamland site” is true to the extent that the two sites were always treated as separate projects. Hence the separate planning briefs. However, as Lord Justice Moses observed at an earlier stage of his judgment (paragraph 40): “The development of Dreamland could not be ignored or put to one side when considering the environmental effects of Arlington and their significance in order to fulfil the requirements of [paragraph 3 and 4 of Schedule 4] the Regulations.”
“ECJ case-law has addressed the issue of ‘salami-slicing’, i.e. the practice of splitting projects into sub-projects so that each of these falls below the screening thresholds or criteria and therefore avoids the objection to undergo an EIA”
“The proposed drainage strategy is acceptable to Southern Water. The point of connection to the public sewer should be confirmed by a capacity check. The details of sewage water disposal will need to be confirmed. We request that should this application receive planning approval, the following condition is attached to the consent: ‘Construction of the development shall not commence until details of the proposed means of foul and surface water sewage disposal have been submitted to, and approved in writing by, the local Planning Authority in consultation with Southern Water’. This duly informed the screening decision. Therefore, the Inspector’s Report recommended a similar (but not identical) condition and it was later attached to the planning permission by the Secretary of State. 28. Lord Justice Moses concluded (at paragraph 28) that this history refuted the allegation of project-splitting. It demonstrated that foul and surface water disposal had been properly considered at every stage and that, by dealing with them through the medium of a condition, the Secretary of State was not hiving off an important issue. He was addressing it and doing so by permissible means. I have no doubt that that conclusion is correct. Moreover, as Ms Wigley appears to accept, foul and surface water disposal is her best point on project-splitting. Its failure makes it unnecessary for us to consider other points which are covered in the Administrative Court judgment on this issue. 29. Conclusion It follows from what I have said that I would dismiss this appeal. I observe that the development of the Arlington site has received a great deal of consideration. Plainly the area adjacent to the seafront in Margate is in need of urgent need of appropriate regeneration. Apart from this relatively narrow appeal, there is no remaining objection to MPRL’s proposals for the site, subject to the conditions attached by the Secretary of State to the planning permission. I do not question the genuineness of the Appellant’s concerns but it is a fact that no objection is now pursued as to the qualitative nature of the planning permission as granted. No Wednesbury point is or could be taken. Lady Justice Macur DBE : 30. I agree that this appeal should be dismissed although for slightly different reasons to those given by my lord, Maurice Kay LJ. 31. For the reasons given by my lord I agree that the Inspector’s decision that “the significant environmental effects were likely to be the free standing consequences of the Dreamland project and not of both projects considered cumulatively” is unimpeachable. If the Secretary of State had not merely noted the Inspector’s process and decision, but expressly adopted the same rationale there could be no arguable appeal. As it is the second sentence in paragraph 24 of the letter dated13 June 2013 introduces what I am satisfied is the incorrect assertion that “there is no need for a cumulative assessment with the Dreamland scheme given its status and the uncertainty…”
“ECJ case-law has addressed the issue of ‘salami-slicing’, i.e. the practice of splitting projects into sub-projects so that each of these falls below the screening thresholds or criteria and therefore avoids the objection to undergo an EIA”
‘Construction of the development shall not commence until details of the proposed means of foul and surface water sewage disposal have been submitted to, and approved in writing by, the local Planning Authority in consultation with Southern Water’