“Drax has credible plans to convert three of the six coal units at Drax Power Station to biomass. Since the beginning of April we have been running our first biomass converted unit (Drax Unit #2) …. The conversion of this second Drax unit is technically feasible during 2014. However, this is dependent on securing the early rights to sufficient sustainable biomass delivered to Drax. However, as set out in the Justification section below, the ability to contract for sufficient sustainable biomass is underpinned by the supply chain making the necessary timely investment in capacity. … Fuel sourcing We continue to make progress with our negotiation with a variety of existing producers and potential suppliers for the full volume required for the second unit conversion …. … Timing of second unit conversion Subject to receipt of a FIDe CfD (by October 2013), our current plan is for this second unit (Drax Unit #3) to be taken offline for the final conversion works during Q2 2014 and start generating as a fully converted biomass unit around a month later.”
“Drax can confirm that, subject to the revised timetable and the receipt of a FIDe CfD (by March 2014), the Drax second unit biomass conversion (Drax Unit #3) could be delivered within Q2 to Q4 2014.”
“It is the forward contracting of biomass fuel and establishment of a supply chain itself which is more relevant to allowing unit conversion than a stock build …. In respect to forward contracting as identified in the original submission Drax will need to contract 4.6mt of biomass per year to support the fully operational capacity of the second and third unit conversions.”
“What we are saying is that it is the issues with the development of the pellet supply chain that are critical to the timing of our conversions (which we have explained in detail both in our application, and in the supplementary response), and it is this issue which will cause the 15-18 months delay. Failing to act promptly will undermine our ability to place the necessary full-chain contracts for the delivery to Drax of the full volume of pellets … required for each of these converted units ….”
“This Phase 2 application for a FIDe Investment Contract relates to Drax’s conversion of a second coal unit (Drax Unit #3, the ‘Unit’) out of its six coal units to biomass (the ‘Project’). … If Drax is allocated an Investment Contract the Project could be delivered between1 April 2014 and31 December 2014 . This application assumes a ‘target commissioning date’ that falls between these two dates …. … Criterion 1 – Project Deliverability As set out in the Phase 1 application … the conversion works for the biomass conversion for the second unit is technically feasible during 2014. However, the date on which commissioning is fully feasible depends on our ability to secure a FIDe Investment Contract and early assurance that sufficient sustainable biomass can be delivered to Drax ….”
“As regards the Qualification Criteria, your explanation should include, for example, an explanation of how the project continues to satisfy the investment hiatus requirements [i.e. the Key Criterion].”
“Please set out the reasons why you consider in the absence of being awarded an Investment Contract there would be a significant risk that the electricity generation to which it would relate would not occur or would be significantly delayed.”
“We confirm that the proposed change in the TCD will not have any potential impact on the Qualification Criteria or the Evaluation Criteria for the Drax Unit #3 project. In particular, the justification for the award of an Investment Contract was to support the need for timely investment in the development of the capacity of the longer-term sustainable biomass supply chain, which remains exactly as set out in our Phase 1 and 2 submissions.”
“… We confirm that subject to confirmation of these details in your binding application and the statements below, we have provisionally evaluated this change [i.e. to the target commissioning date] as not requiring a change to the project’s qualification or evaluation scoring. We have not at this stage reassessed your project’s compliance with the Phase 1 Qualification Criterion 2.ii. that without an Investment Contract there is a significant risk that the electricity generation to which the Investment Contract relates will not occur or will be significantly delayed. We will reassess this criterion based on your response to Section 8 (investment hiatus) of your binding application. In this regard, we would remind you that each application will be considered individually on its own merits and that each application should therefore state clearly the reasons why the unit conversion project concerned is at risk of delay or cancellation in line with the Phase 1 qualification criterion.”
“As set out in our Phase 1 and Phase 2 submissions, the need to secure and deliver to Drax the required sustainable biomass feedstock on the right timescales and at enduring competitive prices is essential to support the conversion to biomass of Unit #3 and generation from that Unit. We provided in our Phase 2 submission … the contracted and pipeline position for biomass supplies for Unit #3 …. As we have highlighted in our submissions … we are dependent on successful new pellet plant developments … to meet our overall biomass requirements. Hence our strategic decision to invest upstream in the supply chain as well as pursuing (simultaneously) a range of pipeline opportunities. Our contracted fuel position remains very vulnerable to any operational delay/hiatus in the development of new pellet plants. The contractual certainty from a private law Investment Contract will provide the necessary increased confidence that our biomass supply and logistics chain is looking for in order to make the investment it needs to guarantee delivery of sufficient volumes of sustainable biomass to fuel the electricity generation from biomass conversion of this Unit ….”
“There is no reference anywhere in their clarification statement to the viability of accrediting under the RO. They do state that on a general basis not being awarded an IC, having been provisionally ranked equal first and deemed affordable, would result in a significant risk that generation would be significantly delayed in execution. However, all subsequent statements then related to the CfD as an alternative to an IC. Having revisited their Phase 1 resubmission under Phase 2 it is apparent that in that application they did compare the award of the IC with their equivalent position under the RO and this was taken into account in DECC’s assessment and the subsequent pass against the qualification criteria …. Overall, … the reviewer’s assessment is that Drax have demonstrated Investment Hiatus compared to the alternative of securing a CfD but there is not clear evidence of the viability of them accrediting under the RO …..”
“10. The binding application for unit #3 is the same as that for unit #1. The clarification letter makes the same general statements about the need for investment contract to raise the funding to support timely investment to develop the supply chain for sustainable biomass, including investment in port and rail (UK and overseas) directly and under take-off commitments. 11. For Unit #3, Drax asserts that there would be a delay of 12-14 months to the project, apparently resulting from a delay of 6-8 months for the award of a CfD under the enduring regime, and a further delay of 6 months resulting from the loss of confidence in the biomass market if Drax failed to be granted an investment contract. Little explanation or supporting evidence is given for this delay. We are not convinced that a delay until the generic CfD regime would result in a further 6 months’ delay to the sourcing of biomass fuel for Unit #3 for a period from some point in 2015 onwards. 12. Drax state that – unlike for unit #1 - they are confident that there are sufficient existing pellet plant facilities to secure the necessary short-term supplies of biomass. Drax is also confident that there are sufficient viable potential new pellet plants, sufficiently advanced, to secure medium to longer term biomass supplies for unit #3. This is expressed as being conditional on the award of an investment contract for unit #3. It is not clear whether these supplies of biomass would not be available if an investment contract was not awarded (and the unit was supported under the RO instead). 13. There is a further indication that there are sufficient supplies of biomass in the short term in the statement by Drax that they would have to wait to apply for an enduring CfD before being able to invest in the supply chain ‘beyond the short-term’. This implies that short term supplies do not need any further investment. 14. Drax state that they would take ‘state aid risk’ and proceed with their investments for unit #3 after receiving an investment contract but before State aid approval is given. It appears from this that it may therefore be possible for Drax to make these investments on the strength of the RO support which they are currently obtaining for co-firing, and could obtain for operating as a conversion in future. They do not explain why this is not the case. 15. Significant work towards converting unit #3 and sourcing fuel has already been undertaken. As set out in schedule 3 to the binding application, the unit will be co-firing for a period up to April 2015, and the full conversion appears to be being delayed until payments under the investment contract can be made. Given that some renewable energy will be produced by co-firing, and that short term supplies of biomass do not appear to be a problem, it is not clear how much generation is likely to be delayed or cancelled.”
“However, your letter and binding application do not provide a cogent explanation of the risk of delay to the generation. DECC notes that: • It no longer appears from your submissions that the actual conversion of the Unit #3 plant itself is at significant risk of delay without an investment contract. This is in contrast to your submissions at Phase 1 and Phase 2 which indicated that conversion of Unit #3 depended on securing the rights to sufficient sustainable biomass. • Your recent submissions do not explain in a satisfactory manner how the alleged delays in fuel supply chain investment caused by the absence of an investment contract would prevent or delay generation. For example, if Drax is making the case that, without an investment contract, Unit #3 may convert but may not operate at full capacity, your submissions do not identify the amount of generation that might be delayed or the point at which delay might occur. • Your recent submissions do not explain why, in the absence of an investment contract, the delay referred to in your clarification letter could not be avoided by converting the plant under the Renewables Obligation (RO). This is in contrast to your submissions at Phase 1 and Phase 2 which indicated that a private law contract was important in enabling sufficient fuel to be sourced for Unit #3. Accordingly, having carefully considered the matter, including in light of your recent submissions, DECC is not satisfied that you have demonstrated that without an investment contract there is a significant risk that the electricity generation relating to Unit #3 will not occur or will be significantly delayed.”
“87. Although a Court will not lightly interfere with a decision of this nature, particularly when such a large sum of money is involved, and despite the attractive simplicity of Mr Chamberlain’s submissions, I am driven to the conclusion that the Claimant has succeeded in discharging the onerous burden of proving that the decision was unreasonable in the Wednesbury sense and that none of the reasons given by DECC in the decision letter can possibly sustain it. When properly understood, Drax’s application did satisfy the Key Criterion and no decision maker, properly informed, who accepted that Drax was telling the truth about the different impact on market confidence of a CfD or IC versus an RO, and about the need to build up the necessary continuous volume of supplies of biomass to fire the unit in future, could have concluded that it had failed to do so or that the information given by Drax was insufficient to satisfy him that it passed the test. ”
“91. The real problem, in my judgment, was not so much a result of deficiencies in the procedure that was adopted, as a result of the misunderstandings about Drax’s supposed change of position and the negative impact that DECC’s mistake about Drax’s failure to deal with the RO counterfactual obviously had upon the way in which the evaluation of whether it had satisfied the Key Criterion was then carried out. For that reason, I do not consider that the second ground of challenge adds anything of substance to the first.”
“The greater the policy content of a decision, and the more remote the subject matter of a decision from ordinary judicial experience, the more hesitant the court must necessarily be in holding a decision to be irrational. That is good law and, like most good law, common sense. Where decisions of a policy-laden, esoteric or security-based nature are in issue, even greater caution than normal must be shown in applying the test, but the test itself is sufficiently flexible to cover all situations.”