“2.5 If the Seller is prevented from completing the building of the Apartment on the Property within a reasonable time after this Agreement because of: 2.5.1 strike or lockout of workmen; 2.5.2 inability (for whatever reason) to obtain building materials or labour; 2.5.3 accident or act of God; 2.5.4 bad weather; or 2.5.5 any other avoidable cause then the Buyer will have no claim against the Seller. This Agreement shall not be cancelled nor shall the Buyer be entitled to compensation or damages resulting from a delay. The Seller will take all reasonable steps to prevent any delay arising.”
“6.1.1 Completion date is twenty working days after the date of the contract but time is not of the essence of the contract unless a notice to complete is served.”
“6.8 Notice to Complete 6.8.1 At any time on after completion date a party who is ready, able and willing to complete may give the other a notice to complete. 6.8.2 The parties are to complete the contract within ten working days of giving a notice to complete, excluding the day on which the notice is given. For this purpose, time is of the essence of the contract.”
“A reasonable time for completing the property and taking the necessary steps to complete the sale expired by no later than the end of December 2008. You were aware at that time that property values were falling and as a consequence of the delay it will now be very difficult if not impossible for our clients to obtain a satisfactory mortgage offer. Our clients’ former solicitors wrote for an explanation of the delay on30 January 2009 and received a reply from your solicitors, Chadwick Lawrence LLP, dated10 February 2009 (copy attached). In that letter, you blamed the delay on [the contractor], stating that the handover date in the building contract ‘is and always has been9 February 2009 ’. On that basis, if we are wrong in contending for a completion date of December 2008, then the deemed date for completion is a reasonable time after9 February 2009 to allow for compliance with the legal formalities. In these circumstances, it is clear that completion has been unreasonably delayed, beyond the deemed completion date, and your clients are in repudiatory breach of the [Contract]. On behalf of our clients, we hereby give you notice that our cl ients accept your breach as discharging the [Contract]. Accordingly, we are instructed to require repayment of our clients’ deposit of£17,295 , together with interest, within 14 days of the date of this letter.”
“I am not convinced that there is, in fact, any dichotomy between the observations of Sargent LJ and Lord Templeman. It does not seem to me that Lord Templeman was going so far as to say that in no circumstances can delay be so unreasonable to give rise to an inference of repudiation. What he was saying, as I see it, is that, where time is not of the essence and there has been unreasonable delay, one cannot always infer that there has been a repudiation: one has to look at all the circumstances. However, that does not mean that delay alone cannot give rise to the inference of repudiation. There is nothing in Lord Templeman's reasoning or conclusion to negative the view that, in an appropriate case, delay can be so long that, because of the absence of any explanatory or mitigating circumstances, the right inference is that the delay amounts to a repudiation of the contract.”
“I rely on the following overall factors in particular over and above the mere time lapse and the circumstances and evidence (including that of the experts) set out or referred to above (all of which I take into account): • The overall time frame of 21/2 years for completion of the development, 6 months or so beyond the revised anticipated programmed completion date must be considered, but, as said, in its context. • I accept that there was delay caused by the factors mentioned by Mr Barker. However, these were all built in to the reprogramming of the project and due allowance made. In any event they cannot solely explain the 124 day delay when the evidence of the contract and project meetings suggested no more than a 7 week delay due to flooding. Even if another 8 weeks is added to this (Mr Barker’s factor of 6-8 weeks as normal), a delay of 14 weeks is nowhere near 124 days (17-18 weeks). By March 2009 (and certainly by September) the developers were even behind their own projected programme allowing for all the delays. • I do not see why the contractors own financial circumstances (or lack of finance) or the delay caused (if any) by the failure to comply with planning conditions should be visited on the defendants. Clearly there was trouble but precisely what, and what was being done about it was not adduced in evidence in any detail. • The purchasers including the defendants were told long after it had become apparent to the claimant it could not be adhered to, that December 2008 was the projected completion date, yet having arranged to market their house on the letting market, and to obtain a 90% mortgage to valuation (interest free), when the time came to obtain access for a valuation (entirely consistent with the date of anticipated completion, December 2008) they were repeatedly refused. As a result they lost their mortgage which expired as I find and accept on31 December 2008 notwithstanding the terms of the earlier offer. The defendants kept the claimant informed of their mortgage and valuation position but the claimant’s position was that other mortgage products were out there. However, they did not show me any evidence that the defendants could have obtained a satisfactory mortgage by these means. Moreover their evidence was that the defendants had tried and failed: they needed a 90% mortgage, values were falling, and interest only products were being taken off the market. • Even before March 2009 the defendants were being told various dates for completion: in June 2008 it was anticipated completion would be in December 2008, in October it changed to February 2009, in December they were told completion was due “shortly”, in the same month it became at least April, in January it was March/April, later the same month it was May 2009, in February it was “possibly … May”
“The consideration of whether there has been a breach of an obligation to perform within a reasonable time is not limited to what the parties contemplated or ought to have foreseen at the time of the contract. In my judgment, the correct interpretation of authorities such as Hick v. Raymond & Reid[1893] AC 22 is that adopted by His Honour Judge Richard Seymour QC in Astea (UK) Ltd v. Time Group Ltd[2003] EWHC 725 ,[2003] All ER (D) 212 , where he said that the question whether a reasonable time has been exceeded is "a broad consideration, with the benefit of hindsight, and viewed from the time at which one party contends that a reasonable time for performance has been exceeded, of what would, in all the circumstances which are by then known to have happened, have been a reasonable time for performance. That broad consideration is likely to include taking into account any estimate given by the performing party of how long it would take him to perform; whether that estimate has been exceeded and, if so, in what circumstances; whether the party for whose benefit the relevant obligation was to be performed needed to participate in the performance, actively, in the sense of collaborating in what was needed to be done, or passively, in the sense of being in a position to receive performance, or not at all; whether it was necessary for third parties to collaborate with the performing party in order to enable it to perform; and what exactly was the cause, or were the causes of the delay to performance. The list is not intended to be exhaustive. " I do not seek to improve upon that formulation. It shows that, even if the contract had required Peregrine to complete the installation within a reasonable time, the fact that the parties had contemplated at an earlier stage that completion would be effected by a certain date would not necessarily mean that a failure to complete by that time would involve a breach of the obligation to complete within a reasonable time.”
“There are three points which emerge from this. First, the task of the court is to look at the position as at the date of purported termination of the contract even in a case of actual rather than anticipatory breach. Second, in looking at the position at that date, the court must take into account any steps taken by the guilty party to remedy accrued breaches of contract. Third, the court must also take account of likely future events, judged by reference to objective facts as at the date of purported termination.”