“3.2 Operating Rate ● The respective Operating Rates listed below shall apply, as particularly provided for in Clause 2 of this SCHEDULE III and in Clause 16.4 of this CONTRACT, except when the Moving Rate, Standby Rate, Repair Rate, Force Majeure Rate, or Zero Rate is applicable for such period, unless otherwise expressly provided in this CONTRACT. 3.2.1 Option A Operating Rate:$498,500 USD/Day… 3.14 Day Rate Adjustment 3.14.1 The Operating Rate is comprised of two elements: (1) the capital element, which, dependent upon the application of the relevant Operating Rate in accordance with Clause 3.2 above, shall remain firm and fixed for the entire TERM of this CONTRACT; and (2) the remaining part, the operating cost element, including the operating cost components itemized below, which operating cost element totals USD 152,869 (comprised of USD 67,009 and GBP 42,930) as of September 14, 2007, being the date of CONTRACTOR’s commercial proposal for the provision of WORK utilizing the MODU pursuant to this CONTRACT. The operating cost element (including its respective components) is subject to adjustment as defined below:… 3.14.5 The base line operating cost element, including its itemized cost components, forming part of the Operating Rate as of September 14, 2007, are set out below and shall be verified or corrected on or about the COMMENCEMENT DATE and thereafter as subsequent adjustments occur, subject to COMPANY’s audit rights pursuant to Clause 23 of the CONTRACT. The first amendment/variations of the operating cost element shall be effective as of the COMMENCEMENT DATE and shall encompass all actual cost changes commencing as of September 14, 2007, with regard to each of the respective cost components other than ADMINISTRATION and REPAIR and MAINTENANCE costs, for which the initial set of cost changes shall be measured from the applicable indices for September 2007, as referenced above. 3.14.6 On a calendar quarterly basis following the COMMENCEMENT DATE, the operating cost element referred to above and forming part of the Operating Rate will be increased or decreased, on the basis of actual costs incurred during the preceding calendar quarter with regard to all of the operating cost components other than ADMINISTRATION and REPAIR and MAINTENANCE costs, for which the initial set of changes shall be measured from the applicable indices for September 2007, as referenced above, all in order to reimburse either the CONTRACTOR or COMPANY as appropriate. The final quarter payment to CONTRACTOR under this CONTRACT in respect of operating costs shall take the form of a lump-sum payment within three (3) months from termination of the CONTRACT.” 3.2.1 Option A Operating Rate:$498,500 USD/Day… 3.14 Day Rate Adjustment 3.14.1 The Operating Rate is comprised of two elements: (1) the capital element, which, dependent upon the application of the relevant Operating Rate in accordance with Clause 3.2 above, shall remain firm and fixed for the entire TERM of this CONTRACT; and (2) the remaining part, the operating cost element, including the operating cost components itemized below, which operating cost element totals USD 152,869 (comprised of USD 67,009 and GBP 42,930) as of September 14, 2007, being the date of CONTRACTOR’s commercial proposal for the provision of WORK utilizing the MODU pursuant to this CONTRACT. The operating cost element (including its respective components) is subject to adjustment as defined below:… 3.14.5 The base line operating cost element, including its itemized cost components, forming part of the Operating Rate as of September 14, 2007, are set out below and shall be verified or corrected on or about the COMMENCEMENT DATE and thereafter as subsequent adjustments occur, subject to COMPANY’s audit rights pursuant to Clause 23 of the CONTRACT. The first amendment/variations of the operating cost element shall be effective as of the COMMENCEMENT DATE and shall encompass all actual cost changes commencing as of September 14, 2007, with regard to each of the respective cost components other than ADMINISTRATION and REPAIR and MAINTENANCE costs, for which the initial set of cost changes shall be measured from the applicable indices for September 2007, as referenced above. 3.14.6 On a calendar quarterly basis following the COMMENCEMENT DATE, the operating cost element referred to above and forming part of the Operating Rate will be increased or decreased, on the basis of actual costs incurred during the preceding calendar quarter with regard to all of the operating cost components other than ADMINISTRATION and REPAIR and MAINTENANCE costs, for which the initial set of changes shall be measured from the applicable indices for September 2007, as referenced above, all in order to reimburse either the CONTRACTOR or COMPANY as appropriate. The final quarter payment to CONTRACTOR under this CONTRACT in respect of operating costs shall take the form of a lump-sum payment within three (3) months from termination of the CONTRACT.”
“I do not see how, if the Day Rate Adjustment is a sum (and not a mechanism) Stena would become entitled to a percentage of that sum”
“The Operating Rate is comprised of two elements…”). Only the capital element is described as fixed (“shall remain firm and fixed”): the operating cost element is not so described, and that cannot be counted for error or bad draftsmanship. It follows that the operating cost element is not “firm and fixed”
“In this respect, the COMPANY shall not be entitled to investigate the make-up of rates and lump sum fees included in this CONTRACT”
“and thereafter as subsequent adjustments occur”
“The first amendment/variations of the operating cost element shall be effective as of the COMMENCEMENT DATE…”