“ 5. Walls and framing of towers and pontoon externally and internally inspected. No cracks and damage to joint found. 6. Item 18 – ingress of seawater into ballast compartments Nos. 3, 4, 18. Cause of ingress – weak slide valves of de-watering and ballast pumps. Perform continuous check of water level and pumping out as necessary. 7. Stormy weather conditions, sea water on pontoon-deck, leakage of seawater into ballast compartments Nos. 9, 10. Probably through manholes of ballast compartments located under floating workshop. ”
“1 … Early in the morning on July 10th 2006 I have actually reported to the Chief of Expedition that the divergence with a typhoon EVENIAR has passed as a whole safely, and the small damages received as a result of a storm will be eliminated. The permanent monitoring of water in the tanks through sounding pipes and trial test pumping out of water from the tanks by bilge pumps during July 9–10 have shown that ingress of seawater in ballast tanks and dry compartments were not occurred. Ballast pumps during this period were not used at all.”