“4. Sender-keeps-all stop-gap measure As noted above, from the panel’s review of the pleadings and consideration of the oral submissions made on31 March 2006 , it appears urgent to enable Digicel to commence some form of interconnection as quickly as possible even if interim rates cannot be set as of31 March 2006 . Accordingly, a sender-keeps-all arrangement is provided for in the order below until interim rates are put in place. A sender-keeps-all measure has inherent limitations – for both parties – on their ability to plan retail pricing strategy and other financial items since neither knows yet what its interconnection revenues and costs will be. Nevertheless, in this case, better something than nothing. Digicel has the option to proceed on the basis of sender-keeps-all for a short period but remains free to wait until the interim application is addressed before commencing commercial service. Since prices cannot operate in a vacuum, terms and conditions would be necessary for this short period. While some fundamental points persist in the text of the reference interconnection offer (RIO), the parties are agreed on most of the text, which can be used in its latest form until revised by decision of the panel or agreement of the parties.”
“347. In their lengthy written closing submissions, the Claimants did not put forward any specific submissions at all as to why I should hold that the arbitration process would have been completed earlier than31st March 2006 , if physical interconnection had been completed earlier than that date. Similarly, the Claimants put forward no submission to the effect that contractual interconnection would have been concluded before31st March 2006 , but for the matters alleged against TSTT. This was a remarkable state of affairs. It meant that even if I held that TSTT had acted unlawfully in delaying physical interconnection, the Claimants put forward no reasoned case that contractual interconnection (or an alternative way forward imposed by an arbitration panel) would have come about before31st March 2006 . TSTT drew attention to this point and the absence of any submission on it from the Claimants when, in turn, TSTT made its written closing submissions. This prompted the Claimants in their oral closing submissions to submit, for the first time, that if physical interconnection had been completed before31st March 2006 then the dispute resolution procedures would have led to a conclusion earlier than31st March 2006 , but to the same effect as the actual decision of31st March 2006 . 348. I can see how it can be argued that if physical interconnection had been completed a good deal earlier than31st March 2006 , then there might have been a chance of the dispute resolution procedures being expedited to produce a decision by the arbitration panel that might have been before31st March 2006 . Conversely, if physical interconnection were only completed a few weeks before31st March 2006 , it becomes much less likely that those procedures would have been expedited to any marked extent. In the end, the debate on what, to my mind, is a critical element in the assessment of the case on loss of a chance came down to the Claimants asserting that it was obvious that they were right on the point, without seeing any need to examine the individual steps in the period January 2006 to March 2006 in order to see how, and if so when, the actual timetable towards the decision on31st March 2006 might have been shortened. Conversely, TSTT submitted that there was simply no material before the court which would enable me to reach a judicial conclusion in favour of the Claimants on this point. … 350. … Finally, if physical interconnection might have been brought forward, but only by a few weeks at the most, then I do not think that I could reach the conclusion on the material (or more properly the lack of material) before me that there was a real or substantial chance that the arbitration procedures would have been appreciably speeded up so as to produce a decision from the arbitration panel, favourable to Digicel T&T, on any date earlier than the date of the actual decision,31st March 2006 . …”
“It is difficult to assess whether TSTT’s mode of conducting its defence of the claim against it was influenced by the Claimants’ statement in opening that the Claimants did not claim on the basis of a lost chance. Nonetheless, the stance adopted by the Claimants in this respect does not encourage me to be too adventurous in speculating as to the possibility that the Claimants might have lost a chance of being better off, if Mr Espinal had not had his conversation with Ms Bejar in late September 2005.”