"I certainly think it would shorten matters if I identified one or two matters about which I can express firm views irrespective of any other evidence that is forthcoming."
"I am content that those three findings feature for the purpose of your closing submissions but I indicate now that what constitutes costs plus may yet require further elucidation by both of you."
"Which is why I had some reservations about the third point. Obviously I have expressed that in an ex tempore way. If one or either of you through your instructing solicitors care to reduce that as the preliminary indications given, that can feature as part of your skeleton arguments and obviously arguments addressed around those with that final caveat that I indicated to you. I apprehend that it may or may not be necessary, but I suspect it will be, that there will be argument as to what constitutes costs plus in the context of this case."
"I do not consider that I gave an ex tempore judgment on this issue on23 October 2009 but rather I made preliminary findings of fact I do of course recognise [and then he quotes from a case] As a general rule tribunals should be careful to ensure that the parties have an opportunity to make submissions on any matter that affect the outcome of the case."
"I have no hesitation in preferring the evidence of Messrs Grant and Warren on this issue."
"(vii) The Defendants are under a duty to take all reasonable steps to mitigate their losses and if they fail to do so their damages will be reduced accordingly… (viii) The burden of proof is on the Claimant to show that the Defendants could reasonably have mitigated their loss and what the loss would have been had they done so."
"Where the Employer fails to give the contractor an opportunity to rectify defects in the work, that amounts to a failure to mitigate the losses."
"The Defendants do intend to repair their roof. Although anxious to ensure that the job was done within their means I am satisfied that they would not want to leave the family home with an unsatisfactory roof. Although I consider that Mr Whitehorn's offer to repair was genuine I do not consider that the Defendants acted unreasonably in refusing it. Past experience of Mr Whitehorn's roofers and no enforceable guarantee justifies an insistence on third party contractors."
"As regards the snagging and other patent items identified on the Scott Schedule I find on the evidence that: a) the Defendants were aware of the ‘snagging’ and other patent items (because they were in occupation of the house and the claimant was not); b) the Defendants failed to notify the Claimant of these items; c) the Claimant had the resources to remedy the defects; d) the Claimant was not given the opportunity to return to site to rectify these items; e) the Claimant was denied the opportunity to request his own work as sub-contractors to return to the site to rectify defects in their own works; f) therefore, the Defendants failed to mitigate their losses in respect of these items (ie those items which were reasonably apparent to the Defendants in the occupation of the house)."
"In my view there is a fallacy at the heart of Mr Rainey's argument. It jumps from the true proposition that no remedial costs have yet been incurred to the false proposition that no loss has yet been incurred. The loss was incurred on3 July 2001 and the fact that in the end the judge – correctly so we are holding – favoured a computation of most of the loss by reference to the cost of a restoration not yet conducted does not alter the date of the loss. Informing therefore the judge's exercise of discretion to award interest under s. 35A of the Act of 1981 should have been "the basic principle … that interest will be awarded from the date of loss"