“11.1 the Site Assembly Costs are known and certain by exchange of all Site Assembly Agreements and the Infrastructure Costs are known and certain to the extent that tenders for the carrying out of the works within a practicable timescale have been received and accepted and the costs thereof (including any fees) thus calculated 11.2 (in the event that clause 10 has effect) the payment due from the Vendor under clause 10.2 is known and at such time when such costs are so identified and known, then any further payments then due and payable to the Vendor under the said clauses 5.1.2 to 5.1.5 hereof after deducting amounts due to the Purchaser under clause 8.3 and 10 hereof shall be payable to the Vendor such payment being made within ten days thereof ”
“Here completion has occurred and the land has been conveyed. The subsequent payments provided for by clause 5 cannot be treated in isolation as simple, unpaid instalments of the purchase price of the land. In every case of this kind it is necessary to analyse carefully what the real consideration for the payment in question is (cf Hyundai Heavy Industries Ltd v Papadopoulos[1980] 1 WLR 1129 ). What the [Hughes/Chelverton Agreement] provided for was for Mr Hughes to receive a net sum calculated by the interaction of clause 5 on one hand and clauses 8.3 and 10 on the other. The netting off was not a mere matter of convenience. It reflected the commercial reality that the increased value of the land by reason of the grant of permission was conditional on the costs of effecting the development remaining within viable limits. If Mr Hughes were to be entitled to receive the overage payment without any reference to the level of [the Costs] he would be getting something for which the contract did not provide. ”
“[97] In any event, a construction of the [Hughes/Chelverton] agreement which had the effect of entitling Mr Hughes to additional purchase consideration in respect of the planning consents without taking full account of the costs of putting the site into a state where the development the subject of those planning consents could be implemented would, in my judgment, be to fly in the face of 'business common sense' (to use Lord Diplock's expression in The Antaios (see para [72] above)). The provision for additional purchase consideration in clause 5 reflects the fact that the grant of a relevant planning consent will increase the value of the Chelverton Land in the hands of Chelverton. But that increase in value must inevitably be dependent upon the amount of the preparatory costs which a developer will have to incur. So I can see no commercial sense in an additional purchase consideration which does not reflect the amount of those costs.”
“[Mr Hughes] is obliged to deduct from any payment to which he would otherwise be entitled under the agreement dated9 April 1998 (“the Agreement”) the amount of Infrastructure and Site Assembly costs incurred by Chelverton, Sainsbury and Groveholt provided that they are Infrastructure or Site Assembly costs within the meaning of the Agreement, save to the extent that [Mr Hughes] would have been entitled as against Chelverton to reduce the amount of the costs to be deducted under clause 11 of the Agreement by reason of a breach of contract by Chelverton or for any other reason.”
“When it implies a term in a contract the court is sometimes laying down a general rule that in all contracts of a certain type - sale of goods, master and servant, landlord and tenant and so on - some provision is to be implied unless the parties have expressly excluded it. In deciding whether or not to lay down such a prima facie rule the court will naturally ask itself whether in the general run of such cases the term in question would be one which it would be reasonable to insert. Sometimes, however, there is no question of laying down any prima facie rule applicable to all cases of a defined type but what the court is being in effect asked to do is to rectify a particular - often a very detailed - contract by inserting in it a term which the parties have not expressed. Here it is not enough for the court to say that the suggested term is a reasonable one the presence of which would make the contract a better or fairer one; it must be able to say that the insertion of the term is necessary to give - as it is put - "business efficacy" to the contract and that if its absence had been pointed out at the time both parties - assuming them to have been reasonable men - would have agreed without hesitation to its insertion.”
“15.9 To the extent that the Actual Costs exceed£5 million plus VAT they shall be borne by the Seller and the Seller agrees to indemnify the Buyer On Demand against All Costs and Expenses in Excess of£5 Million Plus VAT Incurred by the Buyer in connection with the Infrastructure Works and/or the Site Assembly Process.”
“On the other hand, it may then be argued that having taken the opportunity to renew their contract, the parties must be taken to have entered into a new contract on the date of the (last) variation to it. If the latter view is correct, it may also alter the nature of the factual matrix of fact which may be considered in considering the contract.”
“The Court of Appeal clearly determined that Mr Hughes in claiming his entitlement to an enhanced price for the Property was subject to a requirement to give credit for the works that were carried out to enable that enhanced value to be achieved. What the Court of Appeal did not do was give any guidance as to how that exercise was to be decided. It arises under the Hughes/Chelverton Agreement but Chelverton of course is not a party to the current dispute. Self-evidently Groveholt is not a party to that Agreement. Equally the works do not appear to necessarily have been done under the auspices of the Hughes/Chelverton Agreement. I say necessarily because no disclosure has taken place and as I have set out above there are other contractual arrangements between different parties which were applicable to the work. In particular it is significant that whilst Chelverton disclaimed the Hughes/Chelverton Agreement it did not disclaim the benefit of the Chelverton/Groveholt Agreement and in particular the obligations on behalf of Groveholt to carry out the Infrastructure Works and its indemnity against the obligations arising under the Novation Deed.”
“89. Mr Hughes has raised various arguments one of which is a matter of construction that no claims can be made if the work was done by Sainsburys but not under the Chelverton/Hughes Agreement. Such an argument in my view is not open to Mr Hughes as a result of the Court of Appeal decision which plainly decided that if work was done that enhanced the value then credit must in some way be given for that. It was the examination of that principle which led to the changes in stance of Groveholt during the Part 24 hearing as set out above. Disclosure in my view is necessary (not in all probability limited to the parties to this litigation) in order to see how the Infrastructure Works were carried out. This is not as Mr Strauss QC submitted seeking to look at ex post facto events as an aid to construction of the Hughes/Chelverton Agreement; it is more a question of finding out what actually happened. Subject to the overriding decision of the Court of Appeal it seems to me that all arguments remain open and cannot be finally determined at this stage. ”