“to award such sum as the arbitrator may determine in respect of one or both of the following matters, that is to say— (i) compensation to the person who objects to the works in respect of loss or damage sustained by that person in consequence of the carrying out of the works, and (ii) consideration payable to that person for the right to carry out the works.”
“..what the operator must pay for is the right to carry out the works; which right carries with it the right to keep the works on (or under or over) the relevant land in accordance with whatever terms and conditions the arbitrator awards. The price payable must be fair and reasonable but will take into account everything that the operator acquires by carrying out the works. Because the price is one that is fair and reasonable it will not include a ransom value. Accordingly, I consider that the arbitrator came to an erroneous conclusion.”
“(10) In this paragraph “relevant land” means land which is used wholly or mainly either as a railway, canal or tramway or in connection with a railway, canal or tramway on that land, and a reference to the person with control of any such land is a reference to the person carrying on the railway, canal or tramway undertaking in question.”
“Subject to the following provisions of this code, the operator shall, for the statutory purposes, have the right in order to cross any relevant land with a line, to install and keep the line and other electronic communications apparatus on, under or over that land and— (a) to execute any works on that land for or in connection with the installation, maintenance, adjustment, repair or alteration of that line or the other electronic communications apparatus; and (b) to enter on that land to inspect the line or the other apparatus.”
“(4) The operator shall not execute any works on any land in pursuance of any right conferred by this paragraph unless— (a) he has given the person with control of the land 28 days’ notice of his intentions to do so; or (b) the works are emergency works.” ..... “(6) If, at any time before a notice under sub-paragraph (4) above expires, the person with control of the land gives the operator notice of objection to the works, the operator shall be entitled to execute the works only— (a) if, within the period of 28 days beginning with the giving of the notice of objection, neither the operator nor that person has given notice to the other requiring him to agree to an arbitrator to whom the objection may be referred under paragraph 13 below; or (b) in accordance with an award made on such a reference; or (c) to the extent that the works have at any time become emergency works.” ...... “(8) If within the period of 28 days beginning with the giving of a notice under sub-paragraph (7) above [in respect of emergency works] the person to whom that notice was given gives a notice to the operator requiring him to pay compensation, the operator shall be liable to pay that person compensation in respect of loss or damage sustained in consequence of the carrying out of the emergency works in question; and any question as to the amount of that compensation shall, in default of agreement, be referred to arbitration under paragraph 13 below.” (a) he has given the person with control of the land 28 days’ notice of his intentions to do so; or (a) if, within the period of 28 days beginning with the giving of the notice of objection, neither the operator nor that person has given notice to the other requiring him to agree to an arbitrator to whom the objection may be referred under paragraph 13 below; or (c) to the extent that the works have at any time become emergency works.”
“(b) shall award to the person requiring the payment of compensation such sum (if any) as the arbitrator may determine in respect of the loss or damage sustained by that person in consequence of the carrying out of the emergency works in question.” (i) compensation to the person who objects to the works in respect of loss or damage sustained by that person in consequence of the carrying out of the works, and (ii) consideration payable to that person for the right to carry out the works.”
“(5) In determining what award to make on a reference under this paragraph, the arbitrator shall have regard to all the circumstances and to the principle that no person should unreasonably be denied access to an electronic communications network or to electronic communications services. (6) For the purposes of the making of an award under this paragraph— (a) the references in sub-paragraphs (2)(e) and (3)(b) above to loss shall, in relation to a person carrying on a railway, canal or tramway undertaking, include references to any increase in the expenses of carrying on that undertaking; and (b) the consideration mentioned in sub-paragraph (2)(e) above shall be determined on the basis of what would have been fair and reasonable if the person who objects to the works had given his authority willingly for the works to be executed on the same terms and subject to the same conditions (if any) as are contained in the award.” (a) the references in sub-paragraphs (2)(e) and (3)(b) above to loss shall, in relation to a person carrying on a railway, canal or tramway undertaking, include references to any increase in the expenses of carrying on that undertaking; and (b) the consideration mentioned in sub-paragraph (2)(e) above shall be determined on the basis of what would have been fair and reasonable if the person who objects to the works had given his authority willingly for the works to be executed on the same terms and subject to the same conditions (if any) as are contained in the award.”
“If that goes for compensation under paragraph 13 (2) (e) (i) it is difficult to see how a different approach is warranted for paragraph 13 (2)(e)(ii), which is introduced by the same words.”