“…development shall be taken to be begun on the earliest date on which any of the following operations comprised in the development begins to be carried out”
“From the plans available. the vehicular carriageway of the permitted access would be slightly less than 15m wide, to the west of the pedestrian island shown at the site entrance. The Council’s witness not only accepted that the works outlined above had taken place, but that the area treated as in Bundle 4 was ‘within the approved layout’ or ‘overlapped’ it. He also accepted, in principle, that most of the works described could be ‘material operations’ within section 56. Leaving the planning permission aside, I have not a scintilla of doubt that the works under Bundle 4, and some at least under Bundle 3, would by themselves amount to operational development under section 55 [of the 1990 Act]. The issue therefore becomes one of whether they were ‘comprised in the development’.”
“That in turn depends on whether the development had been begun by the agreed date…”
“25. The Council base their case here principally on the nature and purpose of the works carried out. First, there is no evidence to support their earlier assertion that the PermaZyme treatment would be incapable of bearing heavy traffic. Their witness also readily acknowledged that he was not ‘qualified to say’ whether it was capable of forming a permanent road. None indeed of the evidence about its properties was significantly challenged. Further, given the readily available information about it, I cannot see any relevance in the fact that the process was previously unknown in this country, even if correct. 26. The Council drew attention to the alignment of the road as shown on the plans, not only those in the Bundles, but also those submitted in May 2002, described as detailed design drawings for the highway works. One of these [the number is given] shows the final approved scheme, with the existing access in less distinct form, and a hatched overlay from the new access described as ‘temporary access re-alignment for waste disposal site. 27. Even on that plan however there is, as acknowledged, a considerable ‘overlap’ with the approved scheme, so much so that the Council’s witness himself described it as a ‘subtle variation’. It takes the form of a slightly northward ‘hump’ at about the point where the new access would, temporarily, join the existing route. Though no evidence was called from the designer, this might well have been to ensure good visibility while the existing route remained in use, which from the letter quoted above, appears to have been the intention for the removal of spoil. As a question of fact however, the works carried out accorded with the approved plans, at least in the overall layout, save for this one ‘subtle variation’.”
“28. There was no submission that the works were carried out in breach of a condition precedent. Even if approval for them should strictly have been sought pursuant either to condition 6 of the outline permission or under the 1993 Agreement, the fact that it was not does not of itself mean that they were carried out for some purpose unrelated to the development permitted. On-site access routes might vary throughout the course of construction for any number of reasons. The Appellants’ evidence, unsurprisingly, was that they had a contractual obligation to maintain access to the waste station. The works carried out were not in the formation of an altogether different access route to that approved, but included a minor ‘temporary re-alignment’ of it. The Council had no answer to the question of what purpose there could have been in carrying out those works, where a perfectly good access to the waste disposal site existed already, if they were unrelated to the permission. Even if further works might be needed later to the road base or surface, given their location, I consider that these were operations carried out in the course of laying out, if not constructing, part of the only approved access road. They went in my assessment well beyond the mere preparatory works and amounted to an unequivocal act in the implementation of the permission.”
“The access road(s) shown on the plan(s) submitted shall be constructed in accordance with specifications (including details of lighting and drainage) to be submitted to and approved by the Local Planning Authority and the works in connection therewith shall be commenced within six months of the commencement of any other part of the approved development or such longer period as may be approved by the Local Planning Authority and completed prior to occupation of the buildings hereby approved. Reason: To ensure a satisfactory design and that the proposed development does not prejudice the free flow of traffic or the conditions of general safety along the neighbouring highway.”
“No working shall take place except in accordance with a scheme to be agreed with the local planning authority.”
“As I understand the effect of the authorities to which I am about to refer, it is only necessary to ask the single question; are the operations (in other situations the question would refer to the development) permitted by the planning permission read together with its conditions? This permission is controlled by and subject to the conditions. If the operations contravene the conditions they cannot be properly described as commencing the development authorised by the permission. If they do not comply with the permission they constitute a breach of planning control and for planning purposes will be unauthorised and thus unlawful. This is the principle which has now been clearly established by the authorities.”
“37. In general, operations carried out in breach of a condition cannot be relied upon as material operations capable of commencing the development within the meaning of s.56(2).”
“10. The worked out areas shall be progressively back-filled and the areas restored to levels shown on the submitted plan or to a level to be agreed by the Local Planning Authority in accordance with a restoration scheme to be agreed by the Local Planning Authority before extraction is commenced.”
“The need for a local planning authority to spell out any requirement of prohibition in clear terms applies with particular force where the condition is said to prevent not merely some detail of the development, but the commencement of any development pursuing to the planning permission.”
“In my judgment, the principle argued for by the defendant applies only where a condition expressly prohibits any development before a particular requirement, such as the approval of plans, has been met.”
“I would therefore respectfully agree with the view of Ouseley J in Hammerton [(2002) EWHC Admin 2307] that irrationality of enforcement action falls within the public law exception to the Whitley principle”
“development shall be taken to be begun on the earliest date on which any material operation comprising the development begins to be carried out.” section 56(4) explains what is meant by “material operation”
“any operation in the course of laying out or constructing a road or part of a road”