Ravengate Estates Ltd v Horizon Housing Group Ltd & Anor [2008] EWCA Civ 16

[2008] EWCA Civ 16Case No B2/2006/2265
IN THE SUPREME COURT OF JUDICATURE
COURT OF APPEAL (CIVIL DIVISION)
Case No LB224259
ON APPEAL FROM CENTRAL LONDON COUNTY COURT
HHJ LINDSAY Q.C.
Venue Royal Courts of Justice, Strand, London, WC2A 2LLDate 31/01/2008LORD JUSTICE MUMMERYLORD JUSTICE JACOBMR JUSTICE MANN
RAVENGATE ESTATES LIMITEDClaimant/(1) HORIZON HOUSING GROUP LIMITEDFirst Defendant/Respondent(2) PERSONS UNKNOWNSecond Defendant
(Transcript of the Handed Down Judgment ofWordWave International LimitedA Merrill Communications Company190 Fleet Street, London EC4A 2AGTel No: 020 7404 1400, Fax No: 020 7831 8838Official Shorthand Writers to the Court)
MR. Peter Knox Q.C.(instructed by Messrs. Martin Shepherd & Co) for Appellant.MR. Martin Hutchings (instructed by Cook & Partners Solicitors) for Respondent.
JudgmentMr Justice Mann :
[1]This judgment deals with one point arising as to costs, consequential upon the dismissal of this appeal. The parties are agreed that, in the light of the dismissal of the appeal, the appropriate order as to costs is that the appellant should pay the respondent’s costs, to be assessed if not agreed. The one point on which there is disagreement is as to whether or not there should be an interim payment of the respondent’s costs. The respondent seeks such a payment in the sum of £15,000. In support of that application it has submitted a schedule of costs. With the exception of one sum exceeding £3,000 for a surveyor, there appears at first blush to be nothing particularly excessive about that schedule. The surveyor’s costs are puzzling; we cannot see why surveyor’s costs were necessary or appropriate for the purposes of this appeal. At any rate, there is a serious question mark over the recoverability of that part of the costs.[2]That brings the costs down to a sum a little over £20,000. Were it not for the factor which I shall mention in a moment, based on that bill, we would have been prepared to order an interim payment of £12,000 - £13,000. However, we are told that there are outstanding costs issues in relating to the hearing below. At the trial the defendant/respondent was ordered to pay costs up to 30th January 2006 on a standard basis, with the appellant/plaintiff paying the respondent’s costs on an indemnity basis thereafter. The assessment arising out of those orders has yet to be completed. Mr Knox QC for the appellant tells us that it is considered that there will be a balance due on that order to the appellant in a sum of about £10,000. We have had no information to back that up, but assume for the purposes of this judgment that there is a significant chance that the appellant will be owed some costs as a result of the hearing below. In the light of that, and bearing in mind the relatively limited sums which we would otherwise have been minded to order by way of an interim payment for the costs of the appeal, it seems to us that the fair course is not to upset or distort the flow of payments from one party to another as a result of the overall assessment but to decline to make an order for an interim payment. This is not a case in which it can be seen that on any footing the successful respondent is going to end up with a large sum when all the other liabilities have been netted off.

Lord Justice Mummery:

[3]I agree.

Lord Justice Jacob:

[4]I also agree.