“We are informed that you were appointed by the developers/contractors, Greensand Homes Limited to design the foundations which were constructed in accordance with your design. Please may we, therefore, have copies of all the drawings you prepared for the design and construction of the foundations.”
“We are endeavouring to contact Greensand Homes Limited to obtain consent to release the documents you require.”
“Our client was appointed by Greensand Homes Limited (‘Greensand’) to design the foundations for your client’s Property, which we understand has been damaged as a result of heave of the clay subsoil. . . . ”
“Trench fill foundations to be to designated mix GEN 3 concrete to BS5328, 1991, width 600mm under 265mm walls and 430mm overlap. Final foundation depths and widths to the approval of the Building Control Officer on site.”
“[39] Having considered, as I do, the factors in the judgment of Sumner J, and taking all the facts and circumstances into account, and balancing all the points made, and bearing fully in mind the overriding objective, I do not think that it will be just to permit the second defendant to withdraw their admission. Had they investigated the claim properly, they would, in January 2006, either have made the admission, or set out in the pre-action letter the position as they properly understood it. In the latter event, there would have been a proper opportunity for the claimant to make the appropriate investigations and decide how to proceed. 40 In all the circumstances, I conclude that the claimants would suffer substantial prejudice if the defendant was permitted to withdraw its admission and the application is dismissed.”
“[27] Mr White says that, in the light of BSF’s new case, attempts have been made to contact KWE Designs, now alleged by BSF to have designed the foundations for plot 1. He has been unsuccessful in his attempts in the last six weeks to contact KWE Designs. He is concerned that, if he is able to do so, KWE Designs will now argue that any claim against them in respect of the design of the foundations is statute barred: the property was completed in July 2000. He contends that the syndicate has been at pains to investigate the claim, comply with the pre-action protocol, and set out a fully pleaded case.” . . . “[32] There can be no doubt that BSF is the author of its own position. Ever since its response to the claimant’s solicitors’ letter before action, dated the 16 November, 2005, which it gave on the 9 January, 2006, BSF has asserted that it was appointed to design the foundations of the property which are the subject matter of the action. This continued after BSF had filed its formal pleadings in the action. It is clear that, at the time of the original response, the limitation period had not expired, and the claimant would have been able to investigate any claim by BSF that it had not designed the foundations, and that KWE Designs had done so. [33] BSF contends that the relevant date is the date on which the particulars of claim were filed, namely the 2 October, 2006, by which time the claim may well have been statute barred. But in terms of prejudice this cannot be correct; detailed correspondence between solicitors took place between the 16 November, 2005, and the 7 July, 2006. On the basis of that there was no threat of the claim between these parties being statute barred, or that BSF was the wrong defendant. There can be no doubt that, if BSF had denied that they had designed the foundations, the claimant’s solicitors would have carried out investigations and been enabled to make a decision as to whether or not to proceed, before the expiry of the limitation period in July 2006.”
“[36] On the other hand, I must also take into account that, if I refuse the amendment, BSF will be unable to put forward an arguable and important defence. I also take into account that this is a claim for professional negligence against the defendants, as consulting engineers, but I cannot but be surprised that, if BSF is now correct, the claim was treated so lightly in the course of extensive correspondence, and even after litigation had started. BSF, on their own admission, did not make any sufficient effort to check the facts before settling their detailed defence.”
“[14] “This new regulatory scheme [under the Civil Procedure Rules] has been so carefully crafted that in our judgment the rule-makers cannot have intended a pre-action admission of liability to be embraced by the words ‘A party may admit the truth of the whole or any part of another party’s case’ inCPR r 14.1 ”
“[35] I also accept that, in order to show that the withdrawal of a pre-action admission is likely to obstruct the just disposal of the case, it will usually be necessary for the claimant to show that he will suffer some prejudice which will affect the fairness of the trial. Examples of this kind of prejudice were discussed during the hearing. In the light of an admission, the claimant might agree to the destruction of an item of real evidence; he might agree that an expert's inspection is not necessary and it might no longer be possible for one to take place. Witnesses might have died or lost contact. The possibilities are legion. Funding difficulties might also give rise to real prejudice, if the evidence were to show that the claimant had changed his position in reliance on the pre-action admission. . . .”