"I consider that Bennett J was entitled to exercise the court's discretion as he did, and that his decision discloses no error of law. Thus the fact that he might (at least arguably) have granted permission and then consolidated the two proceedings, or have granted permission for [judicial review] and then stayed it pending the Part 7 decision, is of no consequence. 2. The endeavour to erect a public law case outside the Regulations seems to me artificial. The Regulations determine and so are coextensive of the parties' public law powers and rights. The content of procedural fairness is determined directly or by implication by the Regulations. An irrational decision by a public authority is in principle, I would have thought, a nullity in any forum: whether a quashing order can then issue is truly secondary. 3. This is not the kind of case in which damages would be insufficient compared with a public law remedy. It concerns losses on a potential commercial contract, whether these are quantified by pre-estimate or by periodical payments in parallel with calls-offs given to the eventual contractor. (Why HMG would prefer this to nullification or re-tender if it loses, I do not at present understand.) 4. To the extent that there are disputes of fact (see skeleton paragraph 13(1)), JR is actually the less appropriate route. 5. The contrast drawn with contracts worth less than£100,000 is relevant only if public law reaches parts which Part 7 proceedings cannot reach, and this - in the present context - I do not accept. 6. I am sorry that it was left to the MoD to draw the amendment to the Part 7 claim, allowed by the Master on the day judgment was given, to my attention. It reinforces the view reached Bennett J. 7. I would have been prepared to enlarge time had I considered an appeal viable."