“The phase 9 CCTV contract Since Govia’s takeover of South Central, the Client has worked with you to restructure the scope of works to reach a mutually acceptable solution. The final shape of the contract is now clear. We list below the works instructed to date and the budgeted works awaiting instruction. We would now like to formalise your mutual agreement with the Client that the works below now represent the full extent of the “Phase 9” contract. The forecast value of Works that have been instructed or will be instructed totals£937,847 . Please note that we do expect to be able to instruct some additional works on the Epsom Downs line, which might have a value of around£60,000 but for budgetary reasons this is not certain and you should regard this as a bonus. We would be grateful if you would please sign the bottom of this letter and return to me in order to confirm your agreement.”
“(1) That there is no agreement between South Eastern and MJ as alleged in the notice of Adjudication dated24 February 2004 , whose terms, or whose material terms thereof, are recorded in writing, as required bysection 107 of the Housing Grants, Construction and Regeneration Act 1996 ; (2) That MJ no longer has any statutory right to adjudication under section 108 of the said Act; and/or (3) That MJ’s Notice of Adjudication dated24 February 2004 is an abuse of process.” 14. At the hearing before the judge, the following questions were identified: “(1) Has there been an agreement to which the claimant and the defendant have been parties and which is an agreement “in writing” within the meaning ofs.107 of the Act ? (2) If the answer to question (1) is yes, did the defendant still have the right to refer a dispute to adjudication unders.108 of the Act on24th February 2004 if the agreement had previously been discharged by the acceptance of the claimant’s repudiation? (3) If the answer to question (1) is yes, did the defendant still have the right to refer a dispute to adjudication unders.108 of the Act notwithstanding the letter of agreement dated11th February 2002 ? (4) If the answer to questions (1), (2) and (3) are all yes, a. Is the defendant’s notice of adjudication dated24th February 2004 an abuse of process? b. If so, what is the consequence?” a. Is the defendant’s notice of adjudication dated24th February 2004 an abuse of process? b. If so, what is the consequence?”
“1.04 TS stated that due to the splitting up of the contract to S/C and S/E the phases would be reallocated” (TS was a Condes representative). The next section of the minutes is headed “CCTV Phase 9 Programme”
“I am of course aware that some have doubted the wisdom of allowing parties to refer a dispute to adjudication so long after work under the contract has ceased. However, as long as there is any possibility of disputes arising under a contract, parties will have to live with the fact that an adjudicator’s decision may be sought. Indeed, there may be times, even at such a late stage, where it is desirable to have a quick and cheap procedure that can produce an effective temporary decision, particularly since this will not prevent parties from seeking a permanent decision through arbitration or the courts.”