“The burden on a prospective appellant in these areas is nevertheless hard to discharge. In my view, the more complicated and technical the facts, the harder generally speaking is the burden. The reason again is obvious. The more complicated and technical the facts, the longer and more expensive would be this court’s enquiry, whether by review or rehearing, and the more disproportionate would be the whole exercise for the parties and the court alike. Importantly, this court would have the disadvantage of not having heard any of the witnesses, including the experts, give oral evidence. I venture to think that, at the extreme, some questions of fact may be so complicated and technical that they should only be investigated in detail judicially once, provided that the resulting decision is not palpably incompetent.”
“The judge’s factual conclusion … was a composite amalgam of a large number of particular judgments where an assessment of the weight and persuasiveness of each of the experts as witnesses was of critical importance. … it would, I think, be a travesty of the appellate process to interfere with the judge’s composite judgment here … unless it were shown that he made one or more glaring and important misjudgments.”
“The provision of technical site supervision and quality control by Arup/CEPA Slipform shall be based on the formation of a joint team. The detailed arrangements and associated fee are to be the subject of discussion and agreement at a later stage.”
“… confirm that the design intent is being fulfilled.”; and “The team will cover approval of foundations for construction.”
“During site construction the Site Team will determine whether the design intent is being fulfilled and inform the Slipform Construction Manager of any work which is not fit for purpose together with proposals and plans to remedy the situation.”
“As I understand it, the duty under the design agreement is to carry out the design. In order to achieve this, it may be necessary to have further information about the ground conditions. If this is the case, the designer will advise the client that more information is to be obtained. The client may enter into a separate agreement with the designer to provide or supervise the further investigations or instruct a third party to carry out the task. There is a clear distinction between the separate ground investigation and the verification of the design assumptions, which is an integral part of the designer’s duty. The ground investigation itself is not within the normal contractual requirements of the original design contract.”
“Put shortly, Dr Redding was recommending a ground investigation by accurate and detailed mapping as his preferred way forward. He amplified his views in oral evidence. He envisaged recording on a map the variations in rock strength in the area in question, marking the orientation and dip of the discontinuities, and the nature and extent of weathering or alteration of the rock. The rock strength would be assessed by a point load machine.”
“There is no allegation that Dr Redding’s revised estimate was negligent. In my view it was not negligent but it had to be understood in the context that it was a preliminary assumption which was to be subject to a detailed process of verification. It was important to emphasise, as Dr Redding did in both the original and revised memorandum, and again in oral evidence, that the estimate was intended to enable the design to be progressed in its preliminary form. Dr Redding said clearly in oral evidence that he had been surprised to discover that his preliminary design assumptions were used for the final design. I accept his evidence. His was intended to be a working assumption which would need to be verified before work on the final design was complete. The verification process could have been expected to provide the design team in London with an assessment either confirming the design assumption or indicating the changed assumption that the designers would need to take into account. In his oral evidence Dr Endicott [one of Arup’s expert witnesses] agreed that a degree of reassessment was required as the design went on. Dr Oldroyd in London did not wait for any confirmation of the crucial assumption as to the maximum load bearing stress before starting the detailed design of the boiler unit.”
“There was already a gap in Arup’s chain. Dr Redding made what he intended to be a highly provisional assessment which had been implemented by the design team as a firm assessment. Dr Oldroyd’s witness statement (para 41) made it clear that it was for the Geotechnical team to undertake particular studies. He would wait until they responded with the relevant information and until he received further information he would proceed on the basis of the existing assumption.”
“Dr Oldroyd explained in his statement that he understood that it was intended that Dr Redding’s assessment should be confirmed by further ground investigation work. He said that there was also to be surface mapping and visual inspection by the Arup geologist on the site who was supervising the ground investigation. It is apparent that Arup agreed to proceed with the detailed design leaving the load bearing assumption (which Dr Littlechild thought was conservative) to be verified later.”
“It follows from this that Mr Manning and Arup knew that the existing information on ground conditions was unreliable and needed to be subjected to a detailed and careful verification process, the results of which were communicated to the design team. They also knew that there was a particular concern that the quality of rock was variable under the main power plant including the boiler house.”
“5 Bases to be founded on un-fractured rock. All formations to be approved by CEPAS and where necessary brought to level and consolidated using mass concrete as directed by CEPAS.”
“It was essentially different in character to the task which Dr Redding had expected to be undertaken before the detailed design stage (or at the latest in the verification of the completed detailed design). It was not based on detailed geological mapping required to verify a preliminary design assumption.”
“None of this evidence is consistent with Mr Pascall undertaking a detailed verification whether by mapping or otherwise to confirm or modify Dr Redding’s preliminary design assumptions. … I am satisfied that the exercise which he was undertaking was a form of verification that the ground would sustain the bearing pressures that he had been given by Dr Oldroyd on the basis that the geological team had already reached a firm assessment. It was clearly not the type of systematic verification contemplated by Dr Redding in January 1996. It amounted to using a hammer and taking a view on the basis of his great experience, but it was not a detailed examination.”
“I find that Mr Pascall is an excellent geologist who found himself, rather against his will, in Sual with a very ill defined role which did not include a specific task of verifying the load bearing capacities of the rock in the boiler area. If he had by chance found evidence in the course of his cursory examination, which was inconsistent with the bearing capacities which he had been given by Dr Oldroyd, he would no doubt have recorded it in the site report, or raised the problem in a document which would have been retained and to which my attention would have been drawn. Clearly, whatever he did, it did not put him on enquiry that Arup was taking a serious risk in designing the boiler house on this site. Short of this he would not have any incentive to flag up problems to the design team in London (or to his superiors) at a time when Arup had already completed the detailed design and he had not been given the specific task of verifying the design assumptions.”
“Formations for the original G2 and G5 footings comprised fresh/moderately to completely decomposed Grade III/IV rock with open fractures caused by blast damage. The highly weathered and blast damaged rock was the primary cause of the settlement of the pad foundation.”
“The very process of investigation has made the task of reaching conclusions on the cause of the damage a more complicated one. Mr Bowden said in re-examination that because Arup had used rock breakers to break the ground around the foundations it was difficult to tell later whether the damage was caused by blasting or by the rock breakers. Mr Higson agreed in cross-examination that it was difficult to tell whether or not there was damage caused by blasting. Arup’s expert, Dr Endicott, had to concede in cross-examination that there was no evidence of blast damage at G2 and none on three sides of G5 although there was some evidence of cracks and open joints at a trial pit on the fourth side. Even here he qualified his answer by saying that it might be a local feature, although the associated question of the presence of loose debris required further analysis. Arup’s case in the end is that it is extremely difficult to reach a conclusion as to the failure of G2 and G5 but because the contractors have (they say) a proven record of incompetence, the cause must be blasting. They say that the conditions had changed dramatically from those found by Mr Pascall and that this must have been caused by the incompetence of the contractors.”
“What Mr Pascall was undertaking was a rough and ready exercise confirming generally that the basis for the design was correct. It was far removed from the detailed systematic mapping which Dr Redding had envisaged and which became particularly important in view of the qualifications on the estimate of 3MPa which Dr Redding had made. The record which Mr Pascall made of his visit and his inspection on 23rd July was cursory and reflected (as he thought) the unimportant nature of the task and his attitude to it. This was also reflected in the fact that he did not present any report to the design team and threw away any notes made on site presumably because he thought that they were of no importance. I conclude that Mr Pascall was not attempting to and did not fulfil Arup’s obligation to verify its provisional estimate of a bearing capacity of 3MPa in the course of his inspection. In this, he was not personally acting negligently. The task of verification which in the circumstances of this case required detailed and systematic mapping was never undertaken by Arup. In this regard Arup was negligent.”
“Arup’s case is predicated on the premise that the settlements were large and occurred at an extraordinary low load which cannot be explained by the known and observed geology on the site. Secondly, they say that the condition of the G2 and G5 formations in 1997 was very different from those that Mr Pascall had observed in July 1996. They go on to say that their theory is made the more plausible by the poor performance of the contractors on site and is supported by the fact that the thickness of the blinding measured in August 1996 did not correspond with the thickness of the blinding measured in 1997. Thus it must be inferred, so they say, that the formations were altered by the contractor after July 1996. Arup also say that Mr Brice’s witness statement (albeit contradicted in his later evidence) indicated that G5 was altered after the time of Mr Pascall’s inspection, that the contractor’s records show further excavation after the23rd July 1996 , and that whereas Mr Pascall said that he did not see loose, blasted rock or fill left in situ, there are strong indications that the formation suffered from such defects at the time when they were examined in 1997”
“I have concluded that the formation levels were not lowered after23rd July 1996 . I have also concluded that the ground that was found beneath the foundations G2 and G5 in 1997 was in situ ground. Paragraph 58.8 of the Particulars of Claim identified the physical properties of the ground both in July 1996 and in May 1997. I have specifically rejected Arup’s contention that the damage was caused by damage through blasting or the use of fill or loose rock fragments in so thin foundations.”
“In so far as it is necessary to elaborate how the movement of the foundations occurred, I accept the theory of Professor Hudson, set out in his evidence, as being on the balance of probabilities the most likely explanation.”