"The delayed releases and failure of Mace to manage other Trade Contractors involved frustrated all attempts made by Hurst to implement the Works in an efficient, economic, sequential and continuous manner, the result was enforced fragmentary implementation of the Works. The same factors also compelled the deployment of substantial additional and extended resources, including labour, site supervision, plant and equipment."
"Total of Final Account 3,445,815.06 Less total of sums previously Paid to the Trade Contractor 2,839,960.90 THE FINAL PAYMENT payable to the Trade Contractor 605,854.16."
"In consideration of the agreement that final payment is to be made by the Client, we hereby agree that payment to us of THE FINAL PAYMENT will be accepted by us in full and final settlement of all our claims (other than claims in respect of Value Added Tax) arising out of or in connection with the Trade Contract works which have accrued up to and including the date of this statement. We agree that nothing contained in this statement shall relieve us of any of our obligations pursuant to the Trade Contract including, but not limited to, our obligations set out under clause 8 ('Practical Completion and Defects Liability') of the Trade Contract."
"Unless otherwise instructed by the Construction Manager pursuant to Clause 20.6, the Trade Contractor shall not execute any variation required by the Construction Manager nor comply with any Instruction issued by [him]... unless the Trade Contractor shall have first submitted to the Construction Manager in writing within 5 working days of the Construction Manager's Instruction ..." - and a number of requirements are set out of which the most significant for our purpose is clause 20.3.4: "an assessment of the amount of any direct disruption costs to which the Trade Contractor might be entitled;"
"23.6.4 The Construction Manager will issue to the Trade Contractor interim statements of account which will detail all instructions issued to the Trade Contractor which will entitle the Trade Contractor to an adjustment to the Trade Contract Sum under the terms of this trade contract. The Trade Contractor will value the interim statements of account and shall return the interim statements of account within seven days of receipt to the Construction Manager accompanied by all necessary information, measurements and calculations in substantiation thereof. Following agreement by the Construction Manager, the Trade Contractor will be required to signify his agreement and acceptance of the valuation of the instructions detailed in the interim statements of account. 23.6.5 Either before or within 28 Working Days after completion of the Trade Contract Works, the Trade Contractor shall send to the Construction Manager all further documents necessary for the purposes of the final measurement and valuation of the Trade Contract Works which will be completed within the period stated in item 14 of Appendix 1. A final statement of account for the Trade Contract Works shall be provided to the Trade Contractor by the Construction Manager and the Trade Contractor shall signify his agreement by signing and returning such statement within seven days of receipt thereof and such signature shall be conclusive evidence that the amounts shown therein are accepted by him in full and final settlement of the amount of the Trade Contract Sum."
"In my judgment, he was an honest witness, entirely lacking in guile who did his best to recollect what had happened in the early months of 2001. Without the aid of contemporary documents he was unable to recollect the sequence of events and, even with the assistance which they gave, he did not pretend to have a detailed recollection of the discussions which he had had with Mace's Mr Rumsey. He could, however, be sure that certain things were not raised by Mr Rumsey at any time during the discussions which took place between January and April 2001 and, as to that, I believe his memory is reliable - had these matters been raised not only would they have stuck in his memory but, more importantly he would have acted differently at the time; most significantly, I think he would have informed Mr Grant and involved him in the ongoing process."
"When this 'Final Account' is compared with the December 2000 and January 2001 ISA Forms, it is apparent that Mr Mell had done nothing more than list, in numerical order, the CMIs which had had values attributed to them (either agreed values or a Hurst value), the CMIs where the words 'to follow' had been included and, in the case of CMI 274, where it had been indicated that its value was included in CMI 288. The only additional and possibly new information shown was that given below the list, where Mr Mell noted four further items which were said to require CMIs. 32. The explanation for the production of these documents given by Mr Mell in his witness statement was, that he had been approached by Mr Rumsey: '... who asked whether it would be possible to agree a cost for a number of the CMIs. Whilst there was no particular need for me to do this whilst they were being dealt within the interim applications, I did appreciate that Mace were faced with the task of doing this with numerous other trade contractors and therefore it would be of assistance to them if we could tie up these items. It was certainly of no disadvantage to [Hurst] and it was my understanding that David Rumsey was to leave the Project at some stage and certainly it was to Mace's advantage that someone with first-hand knowledge was able to deal with this... At Mr Rumsey's request, I submitted a document to Mace headed 'draft Final Account' on12 January 2001 . It was clear that the document could not be a 'final' account given that we were still on site and so intervening events could effect our actual carrying out of the works. Further, there were further CMIs to price which would be included in the final account. However, the document was what could be described as the first element of the final account as it finalised the cost to carry out CMI's 1 to 399 in terms of labour, plant and material together with the additional preliminary costs agreed within CMI's 51 and 288. (paragraph 3.1 and 3.5 of Mr Mell's witness statement - my emphasis) Apart from the erroneous reference to CMI 399 rather than CMI 333 in paragraph 3.5 of the witness statement, the last sentence of this paragraph conveniently encapsulates one of the essential submissions which Hursts makes. The description given by Mr Mell to the sum of£3,442,831.87 at which he had arrived as 'total to Final Account' is consistent with his believing that the exercise being undertaken was that described in this final sentence."
"Mr Mell said that at no stage in their discussions had Mr Rumsey stated that he was looking for CMIs 1-399 to be priced to include all disruption/loss and expense claims. He said that he had regarded the discussions as routine/day to day events at which values of some only of the CMIs which, in the overall context, involved only comparatively minor sums had been raised. What Mr Mell said appears to me to be consistent with what MLEP stated at paragraphs 19 and 20 of the Defence."
"In my judgment, when Mr Mell prepared his 'Final Account' of12th January 2001 , when he met with Mr Rumsey in February and April 2001, and when he signed the27th April 2001 Document, he did not understand that he was being requested to deal generally with the issue of contractual claims and to allow for them, and there was no reason why he should have thought that he was. Mr Mell can be criticised for not reading the27th April 2001 Document with some care before he signed it, copied it (or arranged for someone else to copy it) and placed the copy in the site files. However, in my judgment the fact is that he did nothing more than glance at it before he signed it. He did not appreciate at the time that he was being invited to do more than 'firm up' valuation figures which would continue to be included on the ISA forms for the remainder of the project and then be taken into the FSA in due course. He did not appreciate that, by the terms included on the last page, Mace was inviting Hurst to forego any and all as yet unrecognised contractual claims for additional costs that it might have. These terms had been included, without any prior hint that they were to be there and they were, unfortunately, overlooked by Mr Mell."
"I generally don't do final accounts, and I - when I produced this document. I know it says 'final account'. I can't deny what it says, but the value of all those is purely labour, plant, material. Nothing else. Nothing more, nothing less. It's been a mathematical exercise. I didn't put any grades or emphasis on to it. I actually thought I was doing Mace a favour. I was just doing what they asked me to do."
"...were it necessary to do so in this case, I would hold that where A intends B to be mistaken as to the construction of the agreement, so conducts himself that he diverts B's attention from discovering the mistake by making false and misleading statements, and B in fact makes the very mistake that A intends, then notwithstanding that A does not actually know, but merely suspects, that B is mistaken, and it cannot be shown that the mistake was induced by any misrepresentation, rectification may be granted. A's conduct is unconscionable and he cannot insist on performance in accordance to the strict letter of the contract; that is sufficient for rescission."
"...there is nothing unfair in holding them to the agreement which, to its knowledge, was the only one which MK's representatives intended to make. I would have no hesitation, if necessary, in holding that 'knowledge' in this context includes 'shut-eye' knowledge."
"It is respectfully submitted that there are the following flaws in the Judge's approach: (i) He failed to give any or any appropriate weight to the use by Mr Mell of the words 'Draft Final Account' in the letter of 12 January and 'Final Account' on the accompanying document. The evidence of Mr Grant was to the effect that a Final Account would include loss and expense. Accordingly, the Judge ought to have given weight to the fact that the description that Mr Mell himself gave of the document was that it was a "
"...had it been proved that Mr Rumsey had actual knowledge that Mr Mell was mistaken as to the contents of the27th April 2001 Document or that, in this regard, Mr Rumsey wilfully shut his eyes to the obvious or that he wilfully and recklessly failed to make such enquiries as an honest and reasonable man would make?"
"49. The possible factual situations which might have happened are these - (1) Mr Rumsey, as he had said in the witness statement upon which Mr Mell commented in his evidence, personally handed the27th April 2001 Document to Mr Mell and invited him to sign it (without explaining to him that Mace had included in the document a previously unheralded invitation to Hurst to forego all as yet unrecognised contractual claims up to the date of signature). If he did so and saw that Mr Mell signed it without first taking time to read carefully through it, the probability is that he had actual knowledge of Mr Mell's mistake as to the effects of the document; alternatively, (2) Mr Rumsey, as he had said, personally handed the27th April 2001 Document to Mr Mell (without explaining to him that Mace had included in the document a previously unheralded invitation to Hurst to forego all as yet unrecognised contractual claims up to the date of signature) but Mr Rumsey did not invite Mr Mell to sign it then and there. In the alternative, in line with the established site practice, Mr Rumsey forwarded the document to Mr Mell for him to collect from the Hurst site correspondence tray, (without including a covering note or in any other way drawing Mr Mell's attention to the fact that Mace had included in the document a previously unheralded invitation to Hurst to forego all as yet unrecognised contractual claims up to the date of signature). On either of these possible bases, the probability is that Mr Rumsey was wilfully shutting his eyes to the risk that Mr Mell would not notice the newly introduced, potentially prejudicial, words which he had no reason to suspect might be there. Alternatively, at the very least, on either of these possible bases, Mr Rumsey would have been a person wilfully and/or recklessly failing to take such steps as an honest and reasonable man would take if he knew (as on my findings Mr Rumsey did know) that the document he had prepared did not simply reflect the agreement(s) on CMI values which had been reached earlier that month after protracted negotiations."
"The27th April 2001 Document differed from the monthly ISA statements in two significant respects. First, the bold headings at the top of each page were changed; the word 'final' was substituted for 'interim' in the typescript; the word 'draft' was added to the typescript but it was crossed through in manuscript and the words 'Stage 1' were added in manuscript. Secondly, in place of the standard wording which was included as the last page of each of the monthly ISAs [the judge refers back for the text of those] there was a very obviously different last page for this document."
"Mike Grant, Director Mike Grant will be the Account Director and will have overall responsibility for the project. He will visit site on a regular basis. Jim Mell, Project Manager Jim will be based on site and will be responsible for the successful delivery of the project to the specified quality, in accordance with the programme and within budget constraints and for producing method statements in accordance with Health and Safety requirements. He will be the team leader and chief point of contact with Mace."
"Mr Mell was not engaged by Hurst to act generally on the company's behalf in the management of its business nor did anyone with actual authority to manage Hurst's business (eg Mr Grant) hold him out as having that authority. Mr Mell was engaged by Hurst to act on the company's behalf in the management of a particular project undertaken on contractual terms agreed between MLEP and Hurst. It is well established that, persons engaged by a contracting party to act on its behalf in the fulfilment of a contract, are not to be taken to have power to vary the terms of the contract - see Sharpe v Paulo Railway Company (1873) LR 8 Ch App 597 where the extent of the authority of the Railway Company's engineer-in-chief in relation to the construction of a railway in Brazil was considered. The point was succinctly dealt with by Lord Romilly MR at page 605, where he contrasted the engineer's power to give directions 'within the limits of the contract' with his inability to vary the contract itself. Of course, a power to agree to vary some or all of the contract terms might be expressly given to a particular Project Manager in a particular case but, in this case, when Mr Mell's job description is examined no such power was expressly given to him and I cannot see any possible basis for its implication. Cause 32.2 of the Trade Contract provided for variations to the terms of the Trade Contract to be written and signed by the contracting parties; a director of the company, Mr Grant, was actively involved with the project and he was notified to Mace/MLEP as the person with overall responsibility for it; it was Mr Grant, not Mr Mell, who had a general authority to act for the company in the management of its business."
"In those circumstances, it is submitted that it is not correct to characterise the 27th April document as being outside the trade contract. Hurst's primary position is that that document fell fair and square within the terms of the Trade Contract."