“a Was the Claimant under an obligation to complete the whole of the mechanical and electrical works on the Dudley Hospitals PFI project? No. b … c If not, (1) What work was the claimant obliged to carry out? To carry out design, procurement and site works for the M&E works for the project consistently with the Construction Contract but limited in value to£14 million . (2) What were the terms and conditions concerning the quality of the work that the Claimant carried out? Implied terms that the work would be carried out in a good and workmanlike manner. (3) What were the payment terms or on what basis is the Claimant to be paid for the work it has done? EDS were entitled to be paid a reasonable sum for the works carried out, up to a limit of£14 million .”
“Our offer currently excludes the cost associated with design. The ownership of the services design will remain with yourselves until such time as your designers, Hoare Lea & Partners, are ‘passed’ to ourselves, always allowing time for Hoare Lea and Drake & Scull to reach an understanding. … We understand the terms of our sub-contract will be a ‘stepped-down’ version of the Construction Contract and that the Sub-Contract details together with the Paper Apart One, if applicable, will be available for examination week commencing25th June 2001 . We also understand that we will be given early access to your Mr. Brinley-Codd in order to expedite our understanding of the documents and the early resolution of any concerns appertaining thereto.”
“10. … The level of LAD (liquidated and ascertained damages) was discussed at that meeting. Mr. Bradburn gave evidence that he thought that the figure of£125,000 a week was agreed at that meeting. Mr Wallace’s evidence was that£150,000 was agreed. Mr Wallace accepted (Day 6, p 127) that some of the documentation issued by both parties after 3rd July tended to support Mr Bradburn’s figure. Mr Wallace gave evidence that there was an error between himself and one of his colleagues, Mr Rodgers (the Deputy Head of Procurement at SRM). By the time he spotted the error the level of damages had been issued to EDS and therefore he could no longer further negotiate and he “swallowed [his] position”
“CONFIRMATION This Order is issued to allow the commencement of design and the procurement of long lead-in items for the above project to ensure compliance in every respect with the contractor’s programme for the whole of the Works. The value of this order shall be limited to the maximum amount of£1,000,000 (One Million Pounds). This Order shall be cancelled and superceded by The issue of the formal Sub-Contract Order/Agreement. This order shall only be effective upon your signing and returning a copy of the attached letter to signify your acceptance of the terms contained therein. Enc: Letter to Sir Robert McAlpine (in 16 no. pages).” for the above project to ensure compliance in every respect with the contractor’s programme for the This Order shall be cancelled and superceded by The issue of the formal Sub-Contract Enc: Letter to Sir Robert McAlpine (in 16 no. pages).”
“This purchase agreement shall be governed and construed in accordance with the Laws of England and the parties hereto irrevocably submit to the exclusive jurisdiction of the English Courts.”
“The important issue in my view is to ensure that the work now proceeds as quickly as possible and we should allow the relevant documentation to catch up as soon as it can. I would confirm my understanding that the process for achieving this will be for you to issue a short form order in a suitable format as you have already done, which would be followed at the end of this week by a set of subcontract terms for us to review and conclude the formal subcontract. The intention is that we would acknowledge this order by issuing a letter in the form also attached to your short-form order.”
“The letter as sent by EDS on20th August 2001 consisted of eight pages. It included reference to a large number of documents. I set out below some important passages from both versions. The passages on the left are taken from Mr. Wallace’s version, attached to the order; those on the right from the EDS version, sent on20th August 2001 . We undertake, when called upon to do so, to enter into a Sub Contract with you for the design and construction, testing and commissioning of the Mechanical and Electrical Engineering Services at the Dudley Hospitals Project. Our Sub Contract appointment will be governed on the basis [of] the following terms, conditions, programme, price, specification and ancillary documentation all in our possession as follows:- We undertake, when called upon to do so, to enter into a Sub Contract with you for the design (in so far as we are to design) and construction, testing and commissioning of the Mechanical and Electrical Engineering Services at the Dudley Hospitals Project. Our Sub Contract appointment will be based on the Sub-Contract Conditions received17th July 2001 [reference given] and schedules attached thereto [reference given]16th July 2001 together with the documents listed below and SRM fax dated19/07/2001 re Clause 22. There follows in each case a list of documents. Those lists are similar, but not the same. Document number 20 is described as follows: Construction Contract, Draft 14, dated 03/05/01 pages 1-140 inclusive (Note: draft number and date lined through), converted into a Sub Contract in which the entitlements liabilities and obligations of the Contractor under the Construction Agreement shall be converted to the entitlements liabilities and obligations of us the Sub Contractor under the Sub Contract. The Liquidated and Ascertained Damages levied by the Employer under the Construction Agreement of£28,715 per day or part thereof shall be adjusted in respect of the Sub Contract to Liquidated and Ascertained damages levied by the Employer at£17,857 per day or part thereof in the Sub Contract. or part thereof, in the Sub Contract, for a maximum period of 18 months. Under the heading “Design work to be carried out by Hoare Lea and Partners” there are included the following passages: This design work and the Specifications are contained in the following drawings and specifications which form part of the Sub Contract. Drake and Scull Ltd are required to comply with these drawings and specifications. Drake and Scull Ltd will appoint Hoare Lea to carry out the remaining items in the Hoare Lea and Partners Scope of Services. Nothing contained in the requirement that Drake and Scull Ltd shall use Hoare Lea and Partners to carry out the remaining items in the Hoare Lea and Partners Scope of Services shall in any way limit the comprehensive obligations of Drake and Scull Ltd to design the Works. The requirement that Hoare Lea and Partners carry out the balance of the Hoare Lea and Partners Scope of Services shall not be construed to be a nomination and Drake and Scull Ltd shall be liable for the balance of performance of Hoare Lea and Partners scope of Services as if they had selected Hoare Lea and Partners as their Consultant to do that work. This design work and the Specifications are contained in the following drawings and specifications which form part of the Sub Contract. Drake and Scull Engineering Ltd are required to comply with these drawings and specifications. It is assumed that the existing drawings and documents referenced in Appendix A are in accordance with the Construction Contract requirements and are free from errors and omissions. Any costs associated with rectification of these materials/drawings/designs has been excluded from our price. Drake and Scull Engineering Ltd will appoint Hoare Lea to carry out the remaining items in the Hoare Lea and Partners Scope of Services. [Paragraph omitted]. The requirement that Hoare Lea and Partners carry out the balance of the Hoare Lea and Partners Scope of Services shall not be construed to be a nomination and Drake and Scull Engineering Ltd shall be liable for the balance of performance of Hoare Lea and Partners scope of Services as if they had selected Hoare Lea and Partners as their Consultant to do that work.”
“CONFIRMATION This Order is issued as an addendum to our previous Order Number 26790014, to allow the commencement of design and the procurement of long lead-in items for the above project to ensure compliance in every respect with the Contractor’s programme for the whole of the Works. The value of this order shall be limited to the maximum amount of£2,000,000 (Two Million Pounds), (ie£1,000,000 on Order Number 26790014, and£2,000,000 on this Order). Aggregate total of£3,000,000 (Three Million Pounds) for both Orders. This Order shall be cancelled and superceded by the issue of the formal Sub-Contract Order/Agreement.”
“We undertake, when called upon to do so, to enter into a Sub Contract with you for the design (in so far as we are to design) and construction, testing and commissioning of the Mechanical and Electrical Engineering Services at the Dudley Hospitals Project. Our Sub Contract appointment will be based on the Sub-Contract Conditions received17th July 2001 [reference given] and schedules attached thereto [reference given]16th July 2001 together with the documents listed below and SRM fax dated19/07/2001 re Clause 22. … Construction Contract, Draft 14, dated 03/05/01 pages 1-140 inclusive (Note: draft number and date lined through), converted into a Sub Contract in which the entitlements liabilities and obligations of the Contractor under the Construction Agreement shall be converted to the entitlements liabilities and obligations of us the Sub Contractor under the Sub Contract. The Liquidated and Ascertained Damages levied by the Employer under the Construction Agreement of£28,715 per day or part thereof shall be adjusted in respect of the Sub Contract to Liquidated and Ascertained damages levied by the Employer at£17,857 per day .... We also accept that such appointment [ie of HLP] will include the following arrangements: ….”
“… The parties had long been negotiating, no doubt originally in the hope, and later in the expectation, of reaching agreement and entering into a sub-contract. They both intended that sub-contract to be made by the execution of a formal document. I shall assume for the purposes of this [part of the] argument that all important points had been agreed by the time that the letter of 20th August was signed and sent to SRM. It was intended, as stated by the terms of the order of3rd July 2001 , that the order would be cancelled and superseded by the issue of the formal “Sub-Contract Order/Agreement”
“We are also concerned that the order that you are currently working against is to a value of£3m and we have just signed off a gross to the end of February of circa£2.8 million . The clock unfortunately is now ticking and we need to have this matter resolved very quickly if it is not to affect payments etc.”
“CONFIRMATION This Order is issued as an addendum to our previous Order Numbers 26790014 and 26790090, to allow the continuance of design and the procurement of long lead-in items for the above project to ensure compliance in every respect with the Contractor’s programme for the whole of the Works. The value of this order shall be limited to the maximum amount of£5,000,000 (Five Million Pounds), (ie£1,000,000 on Order Number 26790014,£2,000,000 on Order Number 26790090 and£5,000,000 on this Order). Aggregate total of£8,000,000 (Eight Million Pounds) for three Orders. This Order shall be cancelled and superceded by the issue of the formal Sub-Contract Order/Agreement.”