"Where (a) a defendant makes a Part 36 payment which the claimant does not accept, (b) the defendant then makes a significant amendment to his case on the basis of information which had always been available to him, and (c) the claimant then promptly accepts the Part 36 payment which he has previously refused, in general the answer should be that the claimant is the successful party."
"The Edwin Coe applicants have a separate argument on costs. They say that the information on revised catch data mitigating income, which they only received on 5 th April 2000 (but which they should have received on 28 th February 2000) changed fundamentally the nature of the claim, in that it had the effect of reducing significantly the sums which the Edwin Coe applicants were entitled to receive for period 2 losses. They say that the Government should pay all their costs in relation to these issues. They say, as I have already set out, that the fact that this information was decisive in their decision to accept the Part 36 payments is to be inferred from the fact that they sought a ruling from me on the admissibility of the evidence on Day 22 of the trial, and that they accepted the payments a few days after I had ruled that the evidence was admissible. The Government says that if one considers the report of the Edwin Coe fisheries expert, Mr Cox, in November 1999 and his evidence at trial, it is reasonable to infer that the delay in providing the data made no difference to the Edwin Coe applicant's conduct of the case and consideration of the part 2 offers, since catch data as mitigating income was only used by Mr Dyson as a reasonableness check and not for the purpose of substantive calculations. I have no means of resolving this conflict. The Edwin Coe applicants have, as is their right, chosen not to waive privilege. There is no reason to suggest that they should have done so. My ruling was given on Day 22 of the trial, after much evidence had been given. I am unable, on the evidence before me, to say or to infer what influenced the Edwin Coe applicants to settle their remaining period 2 claims. The furthest I can go on the evidence is to take some account of the chance that the additional data may have had an effect in relation to the period 2 claims in influencing the decision of the Edwin Coe applicants. This can best be done by extending the period for which the Government must pay the costs in relation to these issues. In relation to these period 2 claims, the Edwin Coe applicants are to be entitled to their costs to 14 th February 2000. Thereafter they must pay the Government's costs in relation to these issues."
"[that] last … principle requires an appellate court to exercise a degree of self restraint. It must recognise the advantage which the trial judge enjoys as a result of his 'feel' for the case which he has tried. Indeed, as it seems to me, it is not for an appellate court even to consider whether it would have exercised the discretion differently unless it has first reached the conclusion that the judge's exercise of his discretion is flawed. That is to say, that he has erred in principle, taken into account matters which should have been left out of account, left out of account matters which should have been taken into account; or reached a conclusion which is so plainly wrong that it can be described as perverse – see Alltrans Express Ltd v CVA Holdings Ltd[1984] 1 WLR 394 per Lord Justice Stevenson at 400 C-F and Lord Justice Griffiths at p. 403G-H."
"I would agree entirely with Mr Porter that were one able to quantify reliably the amount of additional quantities of non-quota species caught by the applicants' vessels then credit may have to be given. However the answer to Mr Porter's proposition is that I do not see how one can establish what additional quantities if any were caught. There is no legal requirement to record non-quota species in EU log books during the base period: …."
"The overriding objective in part 1 of the CPR is that the court should deal with cases justly, including a requirement that as far as is practicable the court should ensure that the parties are on an equal footing. The detailed rules are contained in part 44 (costs) and part 36 (payments into court) and can be summarised as follows: (1) The court has an overall discretion as to whether costs are payable by one party to another, and if payable the amount of those costs and when they are to be paid (part 44.3 (1)(a)(b) and (c)). (2) If the court decides to make an order, the general rule is that the unsuccessful party will be ordered to pay the costs of the successful party, but the court may make a different order (part 44(3)(2)(a) and (b)). (3) It is to be inferred from part 36 rule 20 and the case of Findlay v Railway Executive[1950] 2 All ER 969 that a party which accepts a part 36 payment after the expiry of time for accepting such a payment becomes from that date the unsuccessful party when considering the principle in (2) above. (4) In deciding what order to make, the court must have regard to all the circumstances, including (a) the conduct of the parties, (b) whether a party has succeeded on part of his case, even if he has not been wholly successful, and (c) any payment into court or admissible offer to settle made by a party (whether or not made in accordance with part 36) (part 44.3(4)). (5) The conduct of the parties includes all conduct, both before and during the proceedings (part 44.3(5)). (6) … (7) A part 36 offer or payment requires the permission of the court if it is an offer to settle part of the claim or has been accepted more than 21 days after the offer of payment is made, unless the parties have agreed costs. In such cases, the liability for costs shall also be decided by the court; see part 36.11(3) and part 36.15. … (8) Although it is expressed only to apply at trial, part 36.20 provides guidance where a party accepts a part 36 offer or payment after the 21 days. It provides that where at trial a claimant (a) fails to better a part 36 payment or (b) fails to obtain a judgment which is more advantageous than a defendant's part 36 offer, unless it considers it unjust to do so, the court will order the claimant to pay any costs incurred by the defendant after the latest date on which the payment or offer could have been accepted without needing the permission of the court. In reaching a conclusion on this issue, the court must take into account the consideration set out in part 36.21(5). … Although a party which fails to accept a part 36 payment until after the expiry of time for accepting such a payment is deemed to be the unsuccessful party, this is only a starting point. The court must take into account all the circumstances in which the payment is made, and in particular the circumstances in part 36.21(5) in deciding whether it would be unjust to award the defendant its costs from that date, i.e. (a) the terms of any part 36 offer, (b) the stage at which such part 36 payment was made, (c) the information available to the parties at the time when the part 36 offer or payment was made, (d) the conduct of the parties with regard to the giving or refusing of information for the purposes of enabling the part 36 payment to be evaluated. Although it was decided under the old Rules of the Supreme Court, in Ford v GKR Construction Limited[2000] 1 WLR 1397 at 1403 810, Lord Woolf MR commented in relation to both the old and the new rules that the court has power to make orders other than that costs follow the event where a party fails at the end of the trial to recover a sum larger than the payment into court. He emphasised that the general rule should not apply where it was unjust that it should do so: "
"The court may also take into account the circumstances which have given rise to a change of mind (whether or not to accept the payment into court). In particular, if the court was satisfied that the change of mind arising from a reassessment of the risk in the light of new material was attributable to the defendant's failure to produce that material at an earlier date (or now in contravention of some protocol), it might take the view that the plaintiff should not be required to bear all or some part of the intervening costs. If the defendant has failed to do what the rules or an order of the court require within the time prescribed, then the price of obtaining the permission of the court to do later what he should have done earlier may be that the plaintiff should have the chance to take the money out of court without penalty. The reason is that the costs which have been thrown away were not incurred by reason of a misreading of the position by the plaintiff on the basis of material which was or should have been available but by reason of the absence of available material which he should have had if the defendant had complied with his obligations."