"8. HDW's [Watkins'] engagement by Turner was not in writing and was somewhat informal in nature. As a result, there is an issue as to the extent of HDW's duties. However, it is common ground that HDW were not required to and did not perform any supervisory or inspection role with regard to the actual building works. It s clear that these important functions fell to be carried out by Mr Lucas as "the Supervising Officer", assisted by Unigate Western's Clerk of Works, Mr Gregory. 9. As I have already indicated, HDW were not engaged as architects for the project in the usual way. In my view, it is clear that their engagement was for the provision of "partial architectural services" and that their role was, to a significant extent, responsive in nature. HDW produced the basic drawings required for the construction of the dairy and such other relevant detailed information as Turner required, when and to the extent that they were required to do so by Turner. Thus, if Turner did require more detail of or information about any particular aspect of the general design, they would submit an appropriate query (usually in writing) to HDW who would then supply the necessary further detail or information .... In my view, the general nature of HDW's retainer by Turner was fairly and accurately summarised by Mr Horace Watkins in paragraph 4 or his first Witness Statement as follows:" "
"16. Indicate on plan the first floor construction and which is to have a fire resistance of 2 hours, and all supporting elements to the floor are also to have a fire resistance of two hours."
"2 hour fire rated wall taken up tight to underside of external roof sheets and roof underdrawn with fire liner protection for a distance of 1.500 minimum either side of wall."
"Your Attention Is Drawn To The Following All work to comply with the appropriate building regulations, local authority byelaws, conditions of consent and stipulations etc. And requirements of statutory bodies. ... All work to comply with the appropriate British Standard Institution codes of practice. All materials and components to comply with the appropriate British Standards Institution specifications ... In all case of doubt or discrepancy please refer to Architect for instructions."
"Whether under purlin lining should be erected/suspended over ceiling/if not? Suspension to same. Ceiling specification and tiles. 1.500 fire barrier and cavity barrier."
"Fire Barrier 2 hours F[ire] R[ated] to cover this area. Body-Moir to sort out methods of support for suspended ceiling."
"It was agreed that the under purlin fire lining would finish 1.500m away from the first floor Mezzanine walls, and for the 2 hour fire barrier to be suspended across the office and laboratory areas. This would omit the necessity of fixing upstand closures over the Mezzanine area only."
"Supplying and fixing 1200x600x9mm Supalux Natural finish fixed through 9mm Supalux Fillets into a concealed galvanised grid system on rigid hangers, all to form 2 hour fire resistant lining£13.58 per m 2 Ditto as upstand n.e. 300 mm wide£6.58 per m.l. Cut and fit to "
"5.4 Mr David Hopkins put forward a system for fire sealing the expansion joints in the block fire walls and also to the fire doors and frames by Man McGowan Limited. This material was accepted in principle and work to proceed accordingly."
"To confirm our recent verbal advice to your Mr A Parker that the horizontal slot holes to the First Floor slab – (N.C.C.) rooms will be infilled and fire stopped in concrete to 2 hours fire resistance."
"Fire-stopping is to be provided at the junction of the compartment wall and roof."
"Further to your letter dated 30th ultimo, and the subsequent telephone conversation per your Mr Flynn and the writer we would confirm the following... (b) Reference item (2) of your letter, please find enclosed two No copies of our drawing no. 853/93 - for your information, we would mention that this drawing was issued to the contractor mid-June 1982."
"39. Apart from the complete absence of any direct evidence that such was the purpose for Drawing 93 or that Turner used it to construct the fire detailing in question ... Drawing 93 was not issued until the fire lining work and compartment walls were almost complete (80% and 90% respectively). Furthermore, the drawing was clearly not concerned with any of the compartment walls, because the compartment walls were designed to be 215mm thick and, in the case of the compartment walls on gridlines 2 and 3, were situated at right angles to the portal frames and not, as depicted in Drawing 93, running in the same direction as the portal frame. I agree with the submission made by Mr Taverner QC on behalf of HDW that it is likely that Drawing 93 depicts a location at the head of the wall along gridline D between gridlines 2 and 3, looking north or south and it is to be noted that "
"Dotted line thus indicates Block work taken up above ceiling level to underside of roof as fire barrier (my emphasis) ..."
"58. The question whether a particular defect in a building comes within the scope of an Architect's duty of care to a subsequent occupier will depend upon the original design and/or supervisory obligation of the Architect in question. The Architect will not owe any such duty of care in respect of defects for which he never had any design or supervisory responsibility in the first place. In the ordinary way, the Architect's design and supervisory responsibilities will be those which are required of him by the express and implied terms of the contract under which he is retained there will be a concomitant duty of care in tort in respect of each such responsibility. These propositions do not appear to me to be controversial and I did not understand Mr Dennys to argue otherwise. 59 It was Mr Dennys' submission that it was clear from the terms of HDW's retainer by Turner that "the scope of (HDW's) retainer ... extended to the provision of all necessary details to indicate compliance with theBuilding Regulations 1976 as amended; and adequate construction details to enable the dairy to be completed in accordance with HDW's design intent." (See paragraph 20 of Mr Dennys' written Opening Submissions). In effect, it was this submission which founded Turner's fundamental assertion that HDW "agreed ... to design a two hour fire rated compartment wall along gridline 2. [HDW] had a duty to ensure that the said design complied with the appropriate Building Regulations" (see paragraph 4 of the Part 20 Claim). It is in respect of that alleged design responsibility that it is said that HDW were negligent and in breach of their duty to use reasonable care and skill: see paragraphs 3 and 9 of the Part 20 Claim and paragraph 3(a) and (b) of the Reply to the Part 20 Defence. "60. However, as I have already explained in my findings of fact, HDW's position as Architects in connection with this project was an unusual one. HDW were subcontracted to provide "partial" architectural services" to Turner who were not only main contractors for building the dairy but who had themselves contracted with Unigate Western to carry out the further necessary work of design. So it was that, in accordance with the agreement between them, HDW provided Turner with the necessary basic drawing for the construction of the dairy, but they were never required nor did they agree to produce a detailed design for the construction of a fire resistant detailing at the head of the compartment walls or of the adjacent fire lining. HDW produced a drawing 11C, not as a detailed design of the work needed to achieve the required fire rating (nor was it ever regarded as such), but as a drawing which gave Newport the information which had been requested for Building Control purposes. If and insofar as Drawing 11C can be said to involve any work of design by HDW, it was entirely satisfactory for such purposes (i.e. Building Control). 61. As it happens, Drawing 11C also provided Turner with a clear and sufficient specification for the construction of the compartment walls, floors and adjacent fire lining in order to achieve the required fire rating. Turner were experienced contractors and they retained specialist sub-contractors to carry out the necessary fire lining work. If Turner needed any further information or detail as to the method or precise form of construction of any of those elements of building design, they would have asked HDW to provide it but they never did. In my judgment, the nature of HDW's retainer as architects for the provision of "partial services" to Turner was such that HDW were not under any obligation or duty to provide any such information or detail with regard to the construction of the compartment walls and/or fire lining, in the absence of a request from Turner that they should do so. In other words, it was for Turner to take the initiative in seeking such further information or detail. For those reasons, I have come to the firm conclusion that HDW did not agree to provide "a complete" design for "a 2 hour fire rated compartment wall along gridline 2" as alleged and the design responsibility for such a wall was never any part of HDW's contractual obligations to Turner whether express or implied. Accordingly, I am also satisfied that HDW did not owe any concomitant duty of care in tort in respect of any such design responsibility (either to Turner or Unigate UK) it follows that the Part 20 Claim must therefore fail for that reason, whether or not, any resulting defect in the building was a latent defect."
"The drawings provide the design parameters for Turner(s) to follow. This was a sufficient indication of the design intention to a reasonably competent building contractor such as Turner(s) that they were to construct the wall and the necessary details in accordance with the overriding requirement that it should be a compartment wall with a 2-hour resistance."
"If Turner had required any further detail with regard to the particular design or method of construction required to achieve any of the specified requirements of Drawing 11 C with regard to the compartment floors, walls or fire lining, it would have been open to them to seek clarification or further detail from HDW in accordance with the contractual arrangement which existed between them, but Turner never did. No query was ever raised as to whether what was specified could be built and I am not persuaded that the specified requirements presented any particular difficult constructional problem for a contractor of Turner's experience. Furthermore, so far as concerns the detailed design of the fire lining, as Mr Forbes Bramble indicated in his evidence, I am satisfied that this could properly be left to the expertise of the specialist sub-contractor who was engaged to carry out the necessary work, as is frequently (if not invariably) done in such cases. "
"31. It was common ground that Boddy-Moir were specialist sub-contractors for this type of work. I am satisfied that, as specialists in this field, Boddy-Moir would have been fully aware of the need to provide suitable upstands to the fire lining so as to comply with the relevant Building Regulations and to make it fire resistant to the required standard ie by taking the upstands through the polystyrene insulation so that it was tight up against the underside of the metal roof sheets and fire stopped and there was no evidence to suggest otherwise." 32. There is also no reason to doubt that, as specialist sub-contractors, Boddy-Moir would have been able to carry out the detailed design of the fire lining, including the upstands, to achieve the required fire resistant rating. Nor is there any reason to doubt that Boddy-Moir did design the fire lining in question including upstands, although details of that design are no longer available. Boddy-Moir's quotation of16 March 1982 clearly indicated that suitable upstands for the fire lining were to be provided. Boddy-Moir were specialist sub-contractors who could properly be expected to appreciate the need to take the upstands tight up against the underside of the metal roof sheets and, where necessary, through the polystyrene insulation, so as to satisfy the requirements of the Building Regulations and common sense. If any clarification or further detail of the specified requirements had been required to enable Boddy-Moir to complete any aspect of their detailed design of the fire lining, HDW would have been asked to supply it, but they never were asked to do so. Given that Boddy-Moir were specialist sub-contractors, this is not particularly surprising. I accept the evidence of Mr Forbes Bramble to the effect that fire lining work of this type is invariably done by specialist sub-contractors, that they are skilled operatives with specialised know-how, skills and materials to whom the architect issues directions as to what to do 'at his peril' (see transcript: Day 5, pages 99 to 100) and that: "
"9. Insofar as the compartment wall failed to provide 2 hour fire protection as alleged in the claimant's claim, then such failure was due to a design defect arising from (HDW's) negligence and/or breach of duty ... Particulars (i) the polystyrene was detailed to run over the top of the wall; (ii) there was no return upstand detail to close the fire sheets to the metal roofing."
"63. It is clear from the terms that both Part 20 Claim and the Reply to the Part 20 Defence, that the allegations of negligence are based on what are said to be the shortcoming of Drawing 93. However, for the reasons given earlier in this judgment, I am satisfied that Drawing 93 had nothing to do with the design or construction of the compartment walls or the adjacent fire lining. Furthermore and also for the reasons given earlier, Drawing 11C satisfied Newport's building control purposes and it also provided a clear and sufficient specification for and (as it happens) a sufficient indication of an appropriate design intention for the proper construction of the compartment walls and adjacent fire lining. In my judgment, HDW did use reasonable skill and care in the production of Drawing 11C and, therefore, none of the alleged defects with regard to the compartment walls and/or fire lining can be said to result from any breach of duty of care on the part of HDW with regard to it. "64. Conclusion . Having regard to the firm nature of my conclusions on the first three issues and to the existing length of this judgment, I do not consider it necessary to deal with Issue 4. Accordingly, I have come to the conclusion that for the foregoing reasons this Part 20 Claim must be and is hereby dismissed."
" ... even if not contractually obliged to do things, if what Wat[kins] did do as a matter of fact was done without exercising the due and requisite professional skill and care, and such was causative of foreseeable and recoverable loss to the appropriate class, then they would be liable."
"Basically, the requirements upon H D Watkins were to provide sufficient drawings to obtain planning consent, provide sufficient drawings to obtain Building Regulation consent, to provide sufficient drawings to enable Turners to construct the project and over and above those basic drawings any other drawings to be provided. We had a phrase for it, we called it 'drawings on demand'. In other words if Turners felt that they needed a specific drawing for a specific matter and it hadn't been already prepared, then they would request it and H D Watkins would produce it."