"Contract Amendment No 3 dated19 November 1999 . 11. Hull No. 1740 was the second of two, effectively identical, Vessels which the Builder agreed to build for the Owner. By November 1999, disputes had arisen between them with regard to both Vessels. The Builder alleged, but the Owner denied, that substantial extra cost and delays had been and were being incurred by reason of changes to the design and specification, for which the Owner was responsible. The Owner believed that the Builder was inefficient and was not entitled to any additional payment or extension of time, so far as Hull No. 1740 was concerned, under the Modifications and Change Orders provisions of Clause 6. In the background was what the Owner saw as the parlous financial condition of the Builder, whom it believed might be forced into liquidation. The Builder is and was a subsidiary of Harland and Wolff Holdings Ltd, which is owned or majority owned by a Norwegian company, Fred Olsen Energy ASA. 12. The commercial pressures by November 1999 were very great and the stakes were high. The situation as it was then is described in the third Recital to Contract Amendment No 3 "(C) The Builder has made claims in excess of£130 million under the Shipbuilding Contract and the equivalent contract for Hull No. 1739 in respect of (i) certain alleged breaches by the Owner and the Owner of Hull 1739, (ii) the costs associated with alleged changes to the Specifications to the Shipbuilding Contract and the equivalent contract for Hull No. 1739, and (iii) increases in the steel weight of the Vessel and Hull No. 1739, all of which claims are denied by the Owner, the owner of Hull 1739 and GMIDC [the "
"One cannot spell out of an express provision for recovery of the additional costs of construction, an implied provision for payment to the Builder of unpaid instalments or for a right of deduction therefrom in respect of the cost of construction."
"Owner shall be entitled to set-off all sums due to it pursuant to this clause against the installment of the Contract Price payable pursuant to Clause 8.3.5"
"This renders it unnecessary to deal with the Owner's subsidiary arguments concerning its alleged ability to set-off against the Delivery Instalment sums due to it under Clause 7.6 of the Contract … These points no longer arise although had they fallen for consideration I would have been unable to resolve them without inviting the arbitrators to furnish further reasons. In that regard I should mention in all fairness that the Tribunal was plainly under great pressure to produce an early award and in such circumstances understandably directed only a small part of their reasons to these subsidiary issues."
"For and including, but not limited to, additional services which are requested by Owner, but are not provided for in any Project Change Order and facilities usage for Owner's Subcontractors. Owner's Suppliers … "
"(7) On an appeal under this section the court may by order – (a) …. (b) ….. (c) remit the award to the tribunal, in whole or in part, for reconsideration in the light of the court's determination .."
"We do not consider that the sum otherwise due from the Owner should be reduced for this reason, in the circumstances of the present case."
"to take possession of the Vessel in its unfinished state and complete the Vessel in accordance with this Contract and the Specifications either at the Builder's Yard or elsewhere, at Owner's sole option …" iv) I entirely agree with Potter LJ and Sir Martin Nourse that the plain meaning of that provision is that if the owner chooses to take the action open to him under clause 15.2(ii) it must take possession " and complete the vessel in accordance with the contract and the Specifications" (my emphasis). There is to my mind no warrant for construing the word "and" disjunctively or for construing that phrase as if it read "and (if the Owner wishes) complete the Vessel …". v) The phrase "at Owner's sole option" is governed by the expression "either at the Builder's Yard or elsewhere"
"In circumstances of Builder's default . . . the Owner . . . shall be entitled by Notice to the Builder EITHER: i) to cancel this Contract . . .OR ii) to take possession of the Vessel in its unfinished state and complete the Vessel in accordance with this Contract and the Specifications either at the Builder's Yard or elsewhere, at Owner's sole option."
"The only sensible construction is in my view that the words 'at Owner's sole option' qualify or have as their subject matter the alternatives separated by the disjunctive 'and' as in 'to take possession of the Vessel in its unfinished state' and 'complete the Vessel in accordance with this Contract and the Specifications either at the Builder's Yard or elsewhere'. So understood, there is no obligation to complete the Vessel let alone to do so in accordance with the Contract and the Specifications. Indeed the language used is in any event the language of entitlement, not that of imposition of obligation."
"Given that the contract remains in existence notwithstanding the Owner's exercise of the right to take possession of the unfinished Vessel, we do not see any insuperable difficulty either in principle or in practice in applying the contract terms to the period following the Notice when the contract work is being done by the Owner . . . rather than by the Builder, whether at the Builder's Yard . . . or elsewhere. We need not elaborate on this."