"184. I have already summarised Dr. Cairney's view that the propensity for water ingress through the sealant gap was considerable …. However, the opinion of the experts was that the gap was not a significant water pathway. This view is best summed up in the evidence of Mr. Doherty, Cumbrian's principal expert, in this passage: …." and he quoted verbatim the passage set out above, followed by his finding "
"impermeable membrane"
"… Cumbrian's contractual obligation was to provide an impermeable membrane."
"Cumbrian, as a further difficulty in its impossibility case, inconsistently asserted as its first and principal line of defence that the membrane was defect-free. Its contention was to this effect: "
"JUDGE: Are you able to say whether that appears to be an appropriate protocol for the carrying out of this probe test? A. I think on the face of it it seems entirely reasonable. I would like to think with hindsight I guess I might feel we should obviously be cautious about whether the probeholes are going to prove what was intended but I am afraid I cannot say I would have done any differently … obviously subsequently we are slightly disconcerted to find the results do not seem to prove what we intended [them] to." (Day 6 p. 128)" and: "
"110. In truth, the principal means of determining the required depth at any particular location was by eye, namely seeing from the top of the excavation when the colour and consistency of the material being excavated changed and then, by eye and by use of the staff, seeking to excavate a further 1 metre into what appeared to be the clay."
"None of Cumbrian's witnesses appeared to appreciate that there was a lens or window of alluvium …." (para. 111). Mr Marrin says that there was no evidence to support this (Grounds 7 and 8), referring also to the Judge's further statement that: "
"... a person liable in respect of any damage suffered by another person" (ie BICC), to recover contribution "... from any other person [ie Cumbrian] liable in respect of the same damage (whether jointly with him or otherwise)."
"... the amount of the contribution recoverable from any person shall be such as may be found by the court to be just and equitable having regard to the extent of that person's responsibility for the damage in question."
"16 As a result of the negligence breach of duty and breach of contract by the First Defendant and the breach of contract by the Second Defendant the plaintiffs have suffered loss and damages."
"(1) Leachate volumes generated from the containment area have increased year on year since completion of the specified works in 1990. It is likely that that trend will continue in the future. (2) Currently the Plaintiff dispose of the leachate by agreement with the ... authorities."
"(3) the Plaintiffs have suffered and will suffer as follows: A Existing Losses [total£2,452 , 827] B Further Consultancy Costs Consultation fees for further investigative works.£109,200 (estimated) ... To provide an effective long-term solution for the containment site will require additional investigations and a new design. It is projected that this work will be completed by the middle of 1997. Implementation of the design is likely to take a further year. C Projected Future Costs (pro rata current costs) From January 1997 to December 1997 ... Sub-Total£205,836 Total Estimated Extrapolated Costs£2,767,863 The Plaintiffs also claim as damages the costs of implementing the new design. Particulars of such costs will be provided as soon as the Plaintiffs are able to do so."
"£1,350,000 paid ... in settlement of the Plaintiff's claims ... exclusive of costs."
"Option 1: Repairs to the existing containment [purpose: to minimise the quantity of leachate produced from the containment] Cost estimate:£2.7 million to£2.9 million plus annual running and maintenance costs. Option 2: Creation of a new landfill Cost estimate:£6,093,256 Option 3: Construction of a leachate treatment plant with discharge to a foul sewer ... if the necessary permits for discharge to foul sewer can be obtain then this could be a practical solution for the management of the site. Cost estimate:£354,800 plus other costs."
"231 The damage suffered by BICC was physical in nature, being the water that ingressed into the containment after the containment works had been completed. The damage was not the cost of treatment of the leachate nor the cost of the additional protective measures or treatment plant, nor the costs of bringing proceedings in an attempt to recoup these costs. These costs represent the damages flowing from, are claimed as the result of, and are potentially recoverable for that water ingress damage."
"... there was no suggestion during the trial that the figures ... were inflated or unreasonable."
"Thus the 'damage' for which Parkman was sued and for which it agreed to pay compensation was the water ingress into the containment." (paragraph 274). Although this conclusion derives from the authorities to which the judge referred, it seems artificial to categorise the "damage" suffered by BICC as the physical ingress of water into the containment, rather than the costs incurred by BICC in treating the water that leaked from the containment and removing the impurities borne by it. This could be regarded as a case of economic not physical "damage"
"297 Thus, in assessing a just and equitable sum, my starting point is that Parkman has incurred a liability to pay BICC£1,950,000 for damages commonly caused by all three parties to the contribution proceedings."
"304 I do not believe that a fair and equitable apportionment requires precise mathematical calculation."
"In its context, the 'responsibility' referred to relates to factual responsibility in a causal sense, moral responsibility in the sense of culpability and organisational responsibility in the sense of where in the hierarchy of decision-making and in the organisational structure leading to the damage the contributing party was located."
"If it has no such entitlement under section 51, Parkman seeks to claim contribution towards the entire settlement sum under the Civil Liability (Contribution) Act."
"... the costs of and incidental to all proceedings in ... the High Court ... shall be in the discretion of the court."
"(3) The court shall have full power to determine by whom and to what extent the costs are to be paid."