Mr M Falconer v Falconer Building Projects Ltd: 8003006/2025
JUDGMENT
The claim is struck out under the provisions of rule 38(1)(d) of the Employment Tribunal Procedure Rules 2024 on the grounds that it has not been actively pursued.REASONS
[1]On 15 January 2026 the Tribunal wrote to the claimant seeking further specification of the claim with a view to issuing a judgment under Rule 22 of the Employment Tribunal Procedure Rules 2024 as the respondent had not provided a Response Form. No reply was received from the claimant.[2]On 6 February 2026 the Tribunal wrote to the claimant reminding him to reply to the earlier correspondence. No reply was received from the claimant.[3]On 17 February 2026 the Tribunal gave the claimant an opportunity to give written reasons by 3 March 2026 or to request a hearing in order to consider why the claim should not be struck out on the grounds that it has not been actively pursued. No reply was received from the claimant.[4]The claim is therefore struck out under rule 38(1)(d) of the Employment Tribunal Procedure Rules 2024.